PROJECT

Projects

Environmental & Social Review Summary

Project Number

38113

Company Name

CG CAP DES BICHES SENEGAL

Date ESRS Disclosed

May 13, 2016

Country

Senegal

Region

Africa

Last Updated Date

Feb 26, 2017

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Jul 1, 2016
Signed : Jul 11, 2016
Invested : Jan 13, 2017

Sector

Heavy Fuel Oil - Thermal Power Generation

Industry

Infrastructure

Department

Regional Industry - INF Africa

Project Description

The proposed project, developed by ContourGlobal Cap des Biches (CG CdB or the Company), is a 33 MW capacity project to extend an existing IFC project (IFC project #35175), a 53 MW combined cycle thermal power plant located in Rufisque (23 km east of Dakar) in Senegal (the “ Initial Project”) under construction since 2015. Together the Projects will operate on heavy fuel oil with an option to convert to natural gas. The Extension will be located adjacent to the Initial Project and within the permitted footprint of 2.99 ha, in the municipality of Rufisque West, therefore requiring no additional land. The closest residential area is the Darou Salum Azur district located 400 m to the East of the project area, and with an estimated population of 4,000 people.

The technical configuration, contractual and construction arrangements of the Extension are broadly the same as for the Initial Project: i) same engines (Wartsila 18V46), ii) same contractor (Wartsila) for the Engineering Procurement and Construction (EPC), and iii) same operation & maintenance arrangements. Extension works started on January, 2016 with plant start-up scheduled for September 2016. In 2015, IFC provided financing for the construction of the Initial Project. The proposed financing for the Extension is to provide a cross-currency swap of a loan equivalent of up to US$ 4 m.

This Environmental and Social Review Summary (ESRS) is an update of the ESRS prepared for the Initial Project (IFC project #35175) disclosed on May 4, 2015. Both CG CdB and the EPC contractor managed the construction of the Initial Project well and it is expected to be completed by late May 2016. The Initial Project has been materially compliant with the E&S requirements of IFC.

Overview of IFC's Scope of Review

IFC’s review consisted of appraising technical, environmental, and social information submitted by the sponsors, including:

review of, as well as, in-depth discussion on the Environmental and Social Impact Assessment (ESIA, ERM, March 2016), with the ESIA consultant team and the sponsor;
review of the E&S Management Plan (ESMP) dated March 2016.

The review also included a visit to the project site from March 15th to 16th, 2016 and discussions with relevant stakeholders including CG CdB project and management team, technical experts, the EPC contractor team, and affected communities. Appraisal also included close interaction with an OPIC E&S specialist in coordinating review efforts and agreement on the necessary corrective actions. The sponsor, ContourGlobal (CG) Group, is an existing IFC client specialized in developing, acquiring and operating electric-power assets around the world. IFC is supporting the Group in a 100 MW HFO power plant in Lome sponsored by CG Togo (27849 - Aug 03, 2009). IFC is also working with CG in Armenia, via the Vorotan Hydro transaction (33450 – February 10, 2014). The E&S performance of both of these projects based on IFC supervision records is currently rated as satisfactory.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
ERM 0335027 CG CdB Extension Updated ESIA 20160321 Final_TC_r01.pdf