Identification of Risks and Impacts:
As per national regulatory requirements, an Environmental Impact Assessment (EIA) report, consisting of an impact assessment section, an environmental protection plan, and an environmental monitoring program section, was prepared by an external consultant in 2012 for SLUB Phase 2. The EIA concludes that identified risks and impacts could be reasonably managed by implementing actions detailed in the environmental protection plan, and by effective monitoring of impacts. The EIA required disclosure of key findings and mitigations to local residents in the vicinity of the project site as part of the permitting process; and the same has been disclosed here together with this ESRS.
Policy:
The sponsor’s corporate sustainability policy, key tenets of which are available at the following web link, focuses on the five thematic areas of Environment, Health and Safety, Employees, Supply Chain, and Stakeholder Relations:
http://www.shangri-la.com/corporate/about-us/corporate-social-responsibility/sustainability/mission-statement/.
Management Programs (Construction Phase):
The sponsor at the corporate level adopted a set of internal Contractor Guidelines in September 2010, which define SL corporate requirements on such aspects as EHS permitting, contractor and sub-contractor training, a requirement for contractors to have in place a waste management plan including on-site hazardous material lists and material safety data sheets, and requirements on site-inspections, reporting, and record keeping, etc. The Contractor Guidelines are supported by “House Rules & Conditions” procedures detailing requirements for site management.
Accordingly, a reputed international engineering, procurement and construction (EPC) contractor was selected for the project, where, one of the key selection criteria included the contractor’s EHS capabilities.
Oversight by SLUB of construction-phase E&S impacts commenced with submission by the selected EPC contractor of its own EHS policy for review and approval by SLUB. This EHS policy document included description of: the overall occupational health and safety (OHS) goal for Phase 2 construction activities, key elements of the site OHS management plan, a flow chart delineating the on-site environmental management process and roles and responsibilities, key performance indicators, and description of pollution minimization and control pertaining to noise and vibration, erosion and sedimentation, and waste management and disposal.
In relation to OHS, the EPC Contractor’s EHS policy document included: (i) an overall policy statement stating: zero-incident-upon-project-completion as the key H&S goal; description of systemic-level factors (e.g. lack of effective communication within the construction workforce) which could lead to adverse health and safety incidents, and solutions to address those factors; 5 areas of high-risk work streams (e.g. scaffolding; working at heights) an
d means to address resulting risks (e.g. implementation of permit-to-work procedures; collection and analysis of near-miss statistics).
During Phase 2 construction, on-site inspections were conducted by project team members of SLUB, the main contractor, and sub-contractors, against requirements of the Contractor EHS policy and SLUB contractor management policy.
Management Programs (Operational Phase):
SLUB Phase 1 has implemented a set of standard operating procedures (SOPs) for hotel operations since June 2015 when Phase 1 operations commenced. These SOPs were developed by the SLUB hotel operation team, with oversight from the sponsor to ensure adherence to core requirements of the sponsor’s global corporate social responsibility policies which describe corporate commitments on aspects such as sustainability, environment, employees, and stakeholder relations.
SLUB Phase 1 SOPs cover various EHS management aspects such as those on the control of fire exit obstruction, a detailed fire emergency plan, fire alarm response procedures, handling of flammable and combustible materials, etc. Phase 1 Life and fire safety (LFS) SOPs also directly correspond to requirements as described in the sponsor’s Corporate Policy – Fire and Life Safety, which has 24 sub-policies describing various LFS aspects such as hazard elimination, personnel and organizational setup requirements, compartmentation, electrical fire safety, etc.
SLUB has put in place for Phase 2 a set of 13 Standard Operating Procedures (SOP) related to such operational aspects as: resolution of labor disputes; managing public protest events should these arise; emergency preparedness and response to scenarios of earthquakes, flooding, damages from lightning, major storms and snowstorms, telecommunication system breakdown, blackouts, etc. An LFS emergency response procedural document is also in place which is applicable to Phases 1 and 2 operations.
Emergency Preparedness and Response:
As indicated above, an operational LFS emergency response procedural document is in place which is applicable to Phases 1 and 2. This categorizes LFS events into 3 levels of severity (Codes 1-3) and outlines steps to be followed under each scenario. This document also includes an organizational chart whereby the SLUB Center General Manager has been assigned as the overall Crisis Management Team leader, to whom the Head of Security and Chief Engineer will be key reports.
Organizational Capacity:
During Phase 2 construction, project oversight was exercised by the SLUB senior project manager and his team members, to whom the EPC contractor person in charge, the SLUB chief architect, SLUB chief engineer, and their respective team members report on daily construction progress. The EPC contractor produced regular monitoring reports including monitoring against EHS parameters and KPI’s as set out in its overall site EHS policy. Contractor on-site safety inspectors regularly inspected site conditi
ons and recorded non-compliances.
When operations of Phase 2 commence, the Chief Engineer, Head of Security, and Life and Fire Safety officer will report EHS related performance information (on an exception basis) to the General Manager.