GHG Emissions: The project is designed to have a net plant efficiency of about 46% in combined cycle mode. The MAN 18V48/60 is a dual fuel engine and can be switched from liquid fuel to gas operation mode without retrofitting requirements. Should Senegal succeed in introducing natural gas in the country's fuel mix, Tobene will undertake a cost-benefit analysis of operating the plant on natural gas and will assess the feasibility on doing so. In the previous ESIA, with a guaranteed capacity of 70 MW, the estimated annual GHG emissions were about 350,000 tons of CO2 equivalent. Therefore, the estimated GHG emissions of six 18 MW MAN 18V48/60 engines using HFO and operating at full installed capacity is 540,000 tons of CO2 equivalent. This represents a contribution of less than 3% of the country’s annual emissions.
Air Emissions and Ambient Air Quality: The ESIA consultant monitored concentrations of NO2 and SO2 (using passive diffusion tubes) at five (5) monitoring sites from September 18 to October 12, 2012. As data were collected only during three weeks during the rainy season, they cannot be extrapolated to obtain the annual average concentration of pollutants and determine if the airshed is classified as degraded or non-degraded according to the relevant air quality standards. In addition, no data were collected for particulate matter.
Considering the limited data available, the average concentrations of NO2 in the five locations, from September 18 to October 12, are well below the relevant air quality standards. On the other hand, the average concentrations of SO2 in the five locations, from September 18 to October 12, are below the Senegalese standards but above European standards. According to the ESIA, the high concentration in SO2 could be explained by the presence of a phosphate mine close to the study area.
Air dispersion modeling – using the US EPA approved CALPUFF modeling system – was performed to assess the potential impacts associated with the atmospheric emissions of the six MAN 18V48/60 engines running on HFO. Modeling assumed a fuel with a sulfur content of 2%, stack heights of 65 m, indicative flue gas emissions provided by MAN, and engines operating 24 hours/day. The average sulfur content in the fuel received during 2015 was 0.4%, well below the assumed 2% used in the modelling, hence results indicate a worst-case scenario. Is important to note that flue gas emissions provided by MAN do not exceed Senegalese standards and IFC EHS Guidelines for thermal power plants in non-degraded airsheds. Also, a first stack emissions testing for NOx and SO2 was carried out in March 2016 by an independent expert confirming that emissions by the power generating engines are within the relevant standards.
As no baseline air quality data is available, the air dispersion modelling only shows the project contribution to air quality, and not the predicted environmental concentrations. As a general rule, in non-degraded airsheds, the IFC EHS General Guidelines suggests that a project should not contribute more than 25% of the applicable air quality standards. According to the air dispersion modelling, project contribution to the concentration of pollutants is within 25% of the applicable air quality standards. The only exception involves NO2 hourly average concentrations where the model predicts up to 9 non-continuous excesses per year; these maximum NO2 hourly average concentrations will occur close to the plant and outside residential areas and sensitive receptors.
Tobene Power will conduct monthly ambient air sampling during the first two years of operation to demonstrate air quality is within acceptable limits (ESAP action nr. 7). Should ambient air quality exceed relevant air quality standards, Tobene Power will implement additional pollution control measures to further reduce stack emissions to comply with relevant emissions guideline for degraded airsheds (ESAP action nr. 8). Tobene Power will engage a consultant, approved by the lenders, to confirm that there are no cumulative impacts on the quality of the airshed due to operations of a neighboring mine and associated power plant.
Noise:Baseline noise levels for the existing plant (without extension) monitored at two receptor points located at the limit of the residential areas are within permissible national and IFC ambient noise limits during daytime post operations commencing. The ESIA addendum for the extension states that, based on the results of the modeling, the noise level increase due to the addition of the new engine should remain within the levels accepted by the IFC/WBG EHS guidelines. Noise levels were not measured at night, but as noise levels at daytime were 44 dB(A), it is expected that nighttime noise levels are also within permissible national and IFC ambient noise limits during nighttime. As the 96MW power plant is already in operation, noise levels were monitored in various workstations and at the plant boundary. Average noise level in the machine room is 104.8 dB(A), thus Tobene Power shall implement appropriate hear protection systems for exposed workers. Noise levels measured at the boundary of the site were 66.1 and 65.9 dB(A) and therefore within the relevant standards. Tobene will periodically monitor noise levels at the closest sensitive receptor points (not only at site boundary) outside of the plant boundaries to ensure these are within permissible national and IFC ambient noise limits (ESAP action nr. 9).
Dust: In relation to increase in dust due to increase in traffic and other activities, Tobene is watering access routes and routes inside the construction site to reduce the amount of nuisance dust.
Water consumption: Water comes from an underground pipeline which is part of the SDE (Sénégalaise des Eaux) distribution system. During operations an approximate volume of 210 m3/day will be required for the power plant’s industrial purposes, of which 30m3/day for the extension.
Wastewater Treatment:Industrial wastewater is collected, directed and treated by a de-oiling station. To ensure the correct operation of the de-oiler, Tobene will conduct monthly analysis of the water effluents of the project, including all parameters covered in the Senegalese legislation and IFC/WBG EHS guidelines (ESAP item nr 10). Sludge from the de-oiler is disposed by a qualified hazardous waste disposal operator. Tobene will also implement good practices in terms of run-off management and ensure that also potentially contaminated rain water is treated in the de-oiling station. The average volume of industrial wastewater is about 7 m3/day, and the treated industrial wastewater will be discharged into an evaporation pond which is under construction adjacent to the project site. As this pond is outside the project site, Tobene Power will build a fence around the evaporation pond and install warning signs to prevent access from people and livestock. (ESAP action nr.13). Sanitary wastewater from temporary and permanent installations is collected in septic tanks and its contents are regularly disposed by a government approved service provider. No water course is located in the project’s area of influence, but soil is characterized by the presence of sand formations considered to be relatively permeable. In conclusion, the project is considered to have a moderate impact on groundwater if the mitigation measures are not appropriately implemented. If groundwater shows contamination with oil or other hazardous constituents, Tobene Power will implement the necessary corrective actions to avoid contamination.
Solid Waste Management: Waste generated during the operation phase will include domestic waste (e.g. offices, canteen), and hazardous waste, such as sludge from the de-oiler, oil and containers, used filters, oily rags, and waste from the laboratory and maintenance workshops. Contracts are already in place with licensed waste management and hazardous waste management companies for the collection, treatment, and disposal of waste. Tobene Power will implement a hazardous waste system to track hazardous waste – including contaminated media removed from the project site – from the time it leaves the generator facility where it was produced, until it reaches the off-site waste management facility that will store, treat or dispose of the hazardous waste.
Hazardous Materials: Tobene Power will document a hazardous materials management plan and a waste management plan to describe the process of purchase, transport, storage, handling and disposal of hazardous materials and hazardous waste. These procedures and the content of material safety data sheets (MSDS) will be used to train employees about the safe handling of hazardous materials. As part of Tobene Power’s spill prevention and control plan, secondary containment will be constructed wherever liquid hazardous materials or liquid wastes are stored, and emergency response equipment (e.g. spill response kits, self-contained breathing apparatus, safety showers and eye-wash fountains) will be located close to the areas where hazardous materials are stored (ESAP action nr.11). Construction of secondary containment around the 3,000 m3 HFO storage tank will finalized by September 2016.