PROJECT

Projects

Environmental & Social Review Summary

Project Number

37808

Company Name

TOBENE POWER SA

Date ESRS Disclosed

Feb 16, 2017

Country

Senegal

Region

Africa

Last Updated Date

Aug 10, 2017

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Jul 27, 2017
Signed : May 31, 2017
Invested : Aug 8, 2017

Sector

Heavy Fuel Oil - Thermal Power Generation

Industry

Infrastructure

Department

CNGS6 - Gbl Infrastructure & Natural Resources/Infrastructure - CAF

Project Description

The proposed project, developed by Melec PowerGen Inc (MPG), a subsidiary of the MATELEC Group, consists of an increase in the installed capacity of the existing Tobene IPP (an HFO fired power plant convertible to gas operations in Senegal) from 96 MW to 115 MW, such that under its Power Purchase Agreement with Senelec it will provide increased a minimum guaranteed capacity, from 70 MW to 105 MW, including 115 MW for the peak demand during the peak season (June to October). The extension will be located within the permitted footprint of 4.5 hectares, requiring no additional land. The power plant is connected to the existing Tobene 225/90kV substation, located about 200m away from the project site.

The power plant is located in a scarcely populated area within the rural community of Taïba Ndiaye (about 29,000 inhabitants), regional department of Tivaouane, approximately 90 km north-west of Dakar, Senegal. The closest villages to the plant are Keur Malé (911 inhabitants), Minam (788 inhabitants) and Mbayène (1,300 inhabitants).  Minam, which is the closest village among the three, is located about 900 m from the plant.


In 2014, IFC provided financing for the development of the 96 MW plant, and is a ten percent equity holder of Tobene Power S.A. (“Tobene Power”), a Senegalese limited liability company established in 2011 by MPG for the construction and operation of the power station. Tobene Power will sell power under a 20-year Power Purchase Agreement to Senegal’s state-owned electric utility, SENELEC, which will be the sole off-taker. The project is a joint project with the World Bank which has provided a partial risk guarantee. The proposed IFC financing for the extension is (a) an IFC A Loan of up to EUR 8 million, (b) an IFC Equity investment of up to EUR 1 million, (c) a mobilization of third party capital through a combination of B loans and a parallel loan of up to EUR 18 million, and (d) the provision of an interest rate swap.

 

The construction of the initial 96 MW has already concluded and the power plant started operation in March 2016. Tobene Power is operated and maintained by MPG personnel (O&M contractor). Construction of the extension started in March 2016 with plant start-up scheduled for December 2016.

 

This Environmental and Social Review Summary (ESRS) is an update of the ESRS prepared for the initial 96 MW Tobene power plant project (IFC project # 33841) disclosed on June 11, 2013 (https://disclosures.ifc.org/#/projectDetailESRS/1120).

Overview of IFC's Scope of Review

IFC’s review consisted of appraising technical, environmental, and social information submitted by the sponsors, including:

  • review of, as well as, in-depth discussion on the Environmental and Social Impact Assessment (ESIA, ERM, March 2013), with the ESIA consultant team and the sponsor;

  • review of the Environmental Note for the expansion project (ERM, March 2016);

  • review of the E&S Management Plan (ESMP) dated March 2016; and

  • review of the Environmental and Social Impact Assessment for the expansion project (ESIA, HPR Ankh Consultants, October 2016)

     The review also included a first visit to the project site from March 15th to 16th, 2016 and a second visit on September 29th, 2016. In addition, the WBG teams are in close collaboration to improve its due diligence process including joint supervision visits and frequent follow-up on the action plan. The team also held discussions with relevant stakeholders including Tobene project and management team, technical experts, and affected communities. The sponsor, MATELEC Group, is an existing IFC client specialized in developing, acquiring and operating electric-power assets around the world.

     IFC is also supporting the MATELEC Group in a 67.5 MW HFO power plant located 1.5km from the village of Kounoune, 23km east of Dakar, Senegal (IFC project nr.22410 – Apr 6, 2005), and a 88 MW HFO power plant located 5 km from the town Thika, 38 km north-east of Nairobi, Kenya (IFC project nr.29801 – Sep 30, 2011). The E&S performance of Thika based on IFC supervision records is currently rated as satisfactory. However, the last site visit to Kounoune (May 2016) highlighted some improvement areas to achieve a satisfactory E&S performance.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
ESIA Tobene thermal power plant extension project.pdf