37633
CTGI RENEWBLE ENERGY EGYPT SOLAR 1 SAE
May 4, 2016
Egypt, Arab Republic of
Africa
Sep 30, 2022
B - Limited
Active
Approved : Sep 29, 2017
Signed : Oct 11, 2017
Invested : Jun 1, 2018
Solar - Renewable Energy Generation
Infrastructure
Gbl Infrastructure & Natural Resources
The project is a greenfield 50 MW photovoltaic (PV) plant being developed by a joint venture between Alcazar Energy and Enerpal Consortium (together the sponsor). The sponsor will own the project company “Alcazar Energy Egypt Solar 1 SAE”. The Engineering, Procurement & Construction (EPC) Contractor will be an EPC joint venture (EPC JV) between TSK and Enviromena, who will also undertake the role of the Operations and Maintenance (O&M) contractor for this project. Environmena were established in Abu Dhabi in 2007, as the first downstream solar company in the Middle East and North Africa. TSK was established as a public company in 1986 and began working in the solar PV field in 2006. It has participated in projects with a capacity of 400MW in PV. The total project cost is up to US$ 70-75 million with an IFC A loan of up to US$ 15 million and syndications of up to US$ 42.3 million, and the balance covered by equity.
The project will be located within Egypt’s New and Renewable Energy Agency (NREA)’s 37.5 km 2 Benban 1.8 GW PV solar park comprising 39 separate PV plots, situated 12 km east of the nearest village (Benban), and 15 km west of the Nile River. It is close to the Luxor-Aswan road, 40 km northwest of Aswan city, in the Aswan Governorate of Upper Egypt. The project capacity is approximately 64.03 MWp (DC) for a 50 MW inverter nominal power (AC) and occupies a 0.98 km 2 plot (SBN 13-2) in the central part of the Benban PV solar park. The Benban PV solar park is being constructed on open desert land that is owned by NREA. All of the 39 PV development sites are greenfield, and none have begun full construction. One project has started preliminary works and constructed some basic facilities on the site including office, dispensary, workers resting area, and installed underground septic tanks, none of which are yet operational. The area is mainly flat, with sand and gravel dunes, and with no notable natural vegetation and no human activities.
The project will be linked to substation 2 (SS2) on the eastern side of the Benban PV solar park, via an underground 22 kV transmission line installed by EETC. Substation 2 covers an area of 15,000 m2. To evacuate the energy produced by the 39 projects located at the solar park, in addition to the underground connections and substations, the EETC will also be responsible for designing and building 220 kV overhead transmission lines that will connect the solar park to existing transmission corridors. At a later stage, an additional 180 km double circuit 500 kV transmission line will be constructed by EETC north of the site. EETC will be responsible for the procurement and development of the corresponding environmental and social assessments (ESIAs) for all the elements listed above. All output generated by the project will be sold to EETC under a 25-year Power Purchase Agreement (PPA).
The project’s underground transmission line right-of-way will follow the route of the internal Benban PV solar park roads. The water necessary for the solar plants (predominantly to be used during construction and for PV panel cleaning during operations) is to be sourced from wells around the site. NREA is taking responsibility for commissioning the relevant studies of groundwater in the area and are liaising directly with the Ministry of Water Resources and Irrigation. Subject to the results of these studies, additional infrastructure may be required for the extraction and distribution of water within the Benban PV solar park. A Facility Manager Contractor (FMC) will lead and coordinate the water supply in collaboration with the developers on the site.
As mentioned in the section on PS1 below, a FMC will be hired to undertake or direct the management of cross cutting construction and operation activities for all the Benban solar park on behalf of the solar developers. This approach will assist in ensuring that environment, social and health and safety (ESHS) risks are managed consistently and there is a well-managed and coordinated response to overarching cumulative issues such as occupational health and safety, transport / traffic management, security, community engagement and corporate social responsibility, and labor, worker welfare and accommodation, among others.
The project will comprise a single axis tracking system of approximately 201,600PV panels (polycrystalline silicon modules) with a nominal capacity of 50 MW AC and a peak capacity of 64,51 MW DC. Power will be sent to an inverter and fed into the utility power grid system through EETC substation 3. The Transmission Connection Agreement (TCA) formed part of the original cost sharing agreement signed on the 30th November 2015. It is estimated that the project construction period (currently expected to start in October 2017) will last approximately 12 months with the project designed for a 25 plus year operational lifetime, with options to extend the lease after that date. The FMC will be responsible for managing water and wastewater services, waste management services, logistics and security services, stakeholder engagement and worker accommodation among other, all of which will be developed by October 2017 once the FMC is appointed. The project is expected to employ an average of 250 workers during construction (reaching a peak of 500) and is expected to employ 15-20 personnel during the operational phase of the project.
IFC’s appraisal of the project consisted of a meeting in Cairo with Alcazar Energy representatives on March 19 th -21 st and a site visit to the Benban PV solar park on March 22 nd 2017. In addition, IFC had follow up calls with Alcazar Energy and the EPC contractors to discuss the clients E&S documentation, the ESIA approvals and permit, the roles and responsibilities of the client and the EPC contractor, the implementation mechanism, staffing and hiring of the workers, the risks and impacts and mitigation measures.
IFC’s appraisal of the project focused on the sponsor’s capacity to manage ESHS risks and compliance with the Egyptian regulatory requirements and IFC’s Performance Standards. Specific items reviewed included: (a) the existing Environmental, Social, Health and Safety Management Plans (ESHS MPs) as currently approved by the local environmental authorities; (b) the robustness of the sponsor’s and EPC’s Environmental, Social and Health and Safety Management Systems (ESHS MS) to address existing, and future risks, and impacts; (c) environmental and occupational health and safety (OHS) procedures, plans, and records. (d) the sponsor’s human resources policies and management of contractors and subcontractors; (e) labor issues and workers working conditions; (f) environmental permits; and (g) waste management and hazardous materials management.
IFC’s appraisal in 2017 for Egypt Solar PV Feed in Tariff (FiT) program Round 2 builds on an initial appraisal conducted with the client in Cairo, Egypt between 13-17 December 2015 as part of FiT Round 1, and further appraisal meetings in Dubai, UAE from 29-31 March 2016, along with a review of environmental and social (E&S) aspects through interviews and review of ESHS documents provided. The meetings for Round 1 took place with one of the project sponsors Alcazar Energy, as well as Enviromena, part of the JV which will be the EPC and O&M contractor for the project. The sponsors’ E&S consultant EcoConServ which is assisting in the preparation of the Environmental, Social, Health and Safety Management Plan (ESHS MP) also participated. IFC reviewed the draft Environmental Impact Assessment (EIA) issued in March 2016, and the ESHS MP contained within it, which covered the construction, operation and decommissioning phases of the project. The non-technical summary for the Strategic Environmental and Social Assessment (SESA) commissioned by NREA for the Benban 1.8 GW PV Solar Park, and issued in December 2015, was also considered in this review, as were the conditions attached to the approval of this SESA on 17 March 2016 by the Egyptian Environmental Affairs Agency. These conditions generally pertain to the roles and responsibilities of NREA and the facilities management company (FMC) it appoints, as well as requirements at a project level such as on PV panel design.
IFC has an existing equity investment in Alcazar (Gaia Equity #35909, disclosed November 2014) and which is currently under supervision. This client’s performance has been satisfactory.