PROJECT

Projects

Environmental & Social Review Summary

Project Number

37093

Company Name

METROPOLITAN MUNICIPALITY OF ISTANBUL

Date ESRS Disclosed

Jan 6, 2016

Country

Turkiye

Region

Central Asia and Turkiye

Last Updated Date

Dec 1, 2016

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Feb 8, 2016
Signed : Mar 16, 2016
Invested : May 30, 2016

Sector

Transit and Ground Passenger Transporation

Industry

Infrastructure

Department

Regional Industry INF MCT

Project Description

The proposed investment is an IFC A/B loan of up to EUR 110 million to support Metropolitan Municipality of Istanbul (“MMI”) to finance the construction and electromechanical works of the 5.3 km Kabatas-Mecidiyekoy metro line including three stations (at Kabatas, Besiktas and Darphane), the second phase of a new Mahmutbey – Kabatas line. The metro line will be constructed on the European side of Istanbul and will establish an important east-west public transit axis running through eightnorthern districts of Istanbul and interconnecting four existing tram/metro lines. Construction of the metro project would help MMI to reduce road congestion and promote alternative environmentally-friendly modes of public transportation in Istanbul.

The project is being procured by MMI using a competitive public tendering process. The project included 3 phases of which IFC will be financing only phase 2;
Mahmutbey – Mecidiyekoy (Phase 1): The winning bidder was a Turkish construction consortium Kalyon/Kolin/Gulermak JV. The contract was signed on December 18, 2013, with contractual completion due by the end of 2016;
Mecidiyeköy – Kabatas (Phase 2): The winning bidder was the Turkish construction company, Alarko Taahut Grubu (“Alarko”). The contract was signed on May 13, 2015, with contractual completion due by the end of 2017. The construction started at the end of the May 2015. The line will be connected to phase 1 at Mecidiyekoy station platform, which will be constructed as a part of phase 1;
300 metro vehicles (Phase 3): The tender was conductedon May 25, 2015, with a bid opening date of July 15, 2015. The tender process is still ongoing in line with Public Procurement regulations..

The project sponsor is Metropolitan Municipality of Istanbul, serving a population of nearly 15 million inhabitants. Istanbul is the largest metropolitan municipality in Turkey. It hosts nearly 20% of the national population and has a diversified economic base. The project will be implemented by MMI’s railway systems department and operated by Istanbul Ulasim (“IU”), the municipal enterprise responsible for operating Istanbul’s urban rail network.

MMI is an existing client of IFC since 2008 and has been involved in the successful construction of similar underground metro line projects in recent years. As part of a larger financing package arranged by BNP Paribas Fortis, IFC supported the expansion of the metro system by providing a loan for the 22 km long Kadikoy-Kartal metro line (project # 27309, disclosed August 5, 2008) on the Asian side of the city. That line was successfully completed in August 2012 and carried an average weekday ridership of 215,000 passengers during 2014. Ongoing supervision of the existing investment indicates that MMI’s and IU’s environmental and social performance is generally satisfactory.

MMI has hired EMAY Uluslararasi Muhendislik ve Musavirlik A.S. (“EMAY”), for the control of the design, and monitoring of the contractors, including environmental, social, occupational health and safety requirements, during construction phase of the proposed project.

During the construction of phase 2, tunnel boring machines (TBM) will be used for the majority of the tunneling work. The New Austrian Tunneling Method (NATM), which involves controlled blasting using explosive charges in rock sections, will be used for the last 750 m – 1 km section starting around Gayrettepe to Mecidiyekoy. Stations will be constructed by cut and cover method, where the station locations will be excavated, then it will be built, starting from the foundation upwards and finally the structure will be back-filled. At Kabatas and around Mecidiyekoy, there will be two shaft areas where work equipment, vehicles and TBM will be placedto tunnels by use of cranes. Although most of the project works will occur underground, a total of 2.4 ha of surface land will be used temporarily during the construction period and around 0.24 ha will be required permanently for these facilities. The temporary affected land comprises public recreational spaces which are currently used as green areas near military houses at Darphane and parks, which includes a section of Findikli Park at Kabatas and Besiktas Meydan at Besiktas.

Overview of IFC's Scope of Review

The scope of this project review, conducted between August and September 2015, included assessment of the company’s environmental, health and safety and social (EHSS) management capacity and performance in relation to IFC’s Performance Standards and relevant World Bank Group (WBG) Environmental Health and Safety (EHS) Guidelines. The review relied on documents and reports made available by MMI, IU, Alarko and EMAY and observations and interviews by IFC staff during meetings in their head offices in Istanbul and site visits to the project route.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
Project Presentation Document.pdf
Environmental Impact Assessment Certificate.pdf
IBB Metro Hatti_Turkce ESRS ESAP_Lutfen Ingilizcesini baz aliniz.pdf