PROJECT

Projects

Environmental & Social Review Summary

Project Number

37086

Company Name

OSTRO ANDHRA WIND PRIVATE LIMITED

Date ESRS Disclosed

Feb 5, 2016

Country

India

Region

South Asia

Last Updated Date

Dec 1, 2016

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Apr 15, 2016
Signed : May 6, 2016
Invested : Nov 17, 2016

Sector

Wind Power - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry - INF Asia & Pac

Project Description

The project involves development of two wind farms with a combined capacity of 197.4MW in Ramagiri, Kambadur and Kanaganapalli mandal of Anantpur district of Andhra Pradesh, India (the “project”). The project will be developed by two Special Purpose Vehicles (SPVs) namely Ostro A.P Wind Private Limited of 98.7 MW and Ostro Andhra Wind Private Limited of 98.7 MW (hereafter referred to as the “Company”). Both the SPVs are wholly owned subsidiaries of Ostro Energy Private Limited (hereafter referred to as “Ostro”). Ostro along with its subsidiaries is currently operating wind projects of a total capacity of 76 MW in the state of Rajasthan, and 325 MW is under construction in the states of Rajasthan, Andhra Pradesh and Madhya Pradesh, India.

The project involves procurement, erection, testing, commissioning, operation and maintenance of 94 wind turbines, with a unit generating capacity of 2.1MW each to be supplied by Suzlon Energy (hereafter referred to as “Suzlon”).The companies have signed term sheet with Suzlon and finalization of a lump sum turnkey (LSTK) contract is under progress. The LSTK contract will include supply, erection and commissioning (“E&C”) of wind turbines. The SPVs will also sign a comprehensive O&M contract with Suzlon. The contract would also include land purchase, project approvals, construction of internal/access roads, SCADA building, turbine foundations, evacuation infrastructure, external & internal transmission lines and other associated civil works. The construction phase is expected to be 12 months. It will be a phased construction with full commissioning expected in/February-March 2017.

Transformers will be located near the turbine within an access controlled area and will be connected to the overhead conductor at 33 kV which in turn will connect to the transformer at the pooling substation. A pooling substation with two 220/33 kV 63 MVA capacity power transformers will be constructed at Perur villageand will be used for the project. The turbines are located within a 10-15 km radius of this substation. It will be connected to the project site through eight feeder lines of 33 KV each with a carrying capacity of around 25MW or similar suitable combination. Power from the pooling station will be evacuated through a 37 km 220KV double circuit transmission line to Grid Sub-station (GSS) at Borampalli (220/132). The transmission line along with other associated facilities will be handed over to the state owned utility, Andhra Pradesh Power Transmission Company Limited (APPTCL), after construction.

The project is spread across land belonging to eight villages in Ramagiri, Kambadur, Kanaganapalli mandal of Anantpur District of Andhra Pradesh. The nearest sensitive social receptor (habitation/school/temple) is located around 320-450 meters from the nearest wind turbine. Each turbine and associated transformer will be located in a land plot of approximately 3.0 Acres (1.21 ha). Additional land will be required for construction and maintenance period, like for use by cranes during both turbine installation and maintenance work, for access and internal roads, 33kv high tension line, site office, etc. The total estimated land area required for project is around 390 acres (158 ha) spread over non-contiguous parcels, including land for 94 wind turbines, pooling substation, transmission lines, access roads, internal lines, and a maintenance area amongst others.

All land required for this project will be private land, which is being purchased on a willing buyer-willing seller basis. This land is predominantly, non-cultivated and open scrub land also used for grazing purposes with a mix of singly crop (rain fed) agricultural. There are three other renewable energy projects located in the general vicinity of the project site. Two of them are wind projects in Rayala (Greenko) and Nimbaglu (Ostro, Orange and Tata), located at a distance of about 22 kms and 50 kms respectively north east of the project site. A solar power project in Borampalli is located at a distance of approximately 26 kms from the proposed project site.

Overview of IFC's Scope of Review

IFC’s review consisted of appraising technical, environmental, and social information submitted by the sponsors and the company including: the environment and social impact assessment (ESIA) for the project dated January 2016; the draft Environment and Social Management System (ESMS) manual dated January 2016; general guidelines for accommodation in Labour Camp; human resource manual and code of conduct of Ostro; Environment Health and Safety conditions for contractors; Ostro’s private security guidelines and public consultation meeting records. The review also included a visit to the project site from 27th to 30th December 2015 and discussions with relevant stakeholders including the project and management team, technical experts, the land team, affected communities, select governmental institutions and line departments (like land/revenue, forest). The appraisal visit also included meetings with the E&S specialist of Ostro, the corporate team (technical) and the ESIA consultants to understand and clarify on different environment and social issues/aspects pertaining to the project

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
Revised Ralla-ESIA Report 29 January 2016-Final.pdf