PROJECT

Projects

Environmental & Social Review Summary

Project Number

36845

Company Name

MAINSTREAM RENEWABLE POWER AFRICA HOLDINGS LTD

Date ESRS Disclosed

Aug 7, 2015

Country

Africa Region

Region

Africa

Last Updated Date

Dec 1, 2016

Environmental Category

A - Significant

Status

Active

Previous Events

Approved : Jun 3, 2016
Signed : Jun 23, 2016
Invested : Jul 20, 2016

Sector

Renewable Energy Holding Companies

Industry

Infrastructure

Department

Regional Industry - INF Africa

Project Description

In December 2014, Mainstream Renewable Power Limited (“Mainstream” or “the Sponsor”) and Actis Capital LLP (“Actis”) set up Lekela Power BV (“Lekela”), an Actis/Mainstream joint-venture platform to develop, finance and build over 1 GW of wind and solar PV projects across Africa. Mainstream is an international renewable energy firm specialized in the development, financing, construction and operation of large-scale wind and solar power plants and has assets in operation and under construction in Africa, Europe, North America and South America. Actis is a leading private equity investor in emerging markets.

The proposed project is an equity investment of up to $40 m in Mainstream Renewable Power Africa Holdings Limited (“the Company”), which has been established with the sole purpose of holding Mainstream’s interest in Lekela. Mainstream’s pipeline will act as a feeder to Lekela, with each project being transferred to the platform at a late development stage. Lekela will also bid on some projects directly, with Mainstream providing development services. Mainstream will develop projects and manage construction and operations under service agreements with Lekela. Funds are expected to be utilized for equity financing of project-financed renewable energy assets across Africa. The current Lekela pipeline in Africa includes three wind projects under construction by Mainstream in South Africa and a number of wind and solar projects under development in South Africa, Ghana and Egypt. Additional early stage projects have been identified elsewhere in Africa.

The three most advanced Lekela projects in South Africa were initially awarded to a Mainstream-led consortium as a result of Round 3 of the country’s Renewable Energy IPP Procurement Process (REIPPPP) and transferred to Lekela in February 2015. Noupoort Wind Power Plant (WPP) is an 80 MW project located 10 km east of the town of Noupoort in the Northern Cape Province. Construction commenced in February 2015 and the planned commercial operations date is July 2016. Khobab and Loeriesfontein II WPPs will have a capacity of 140 MW each and will be sited on adjacent farms 60 km north of the town of Loeriesfontein in the Northern Cape. Construction of these two WPPs commenced in mid-2015 and commercial operations is expected in December 2017. Mainstream has also been awarded preferred bidder status on two REIPPPP Round 4 WPPs: the 140 MW Kangnas project located in the Northern Cape and the 110 MW Perdekraal East WPP in the Western Cape Province.

The most advanced pipeline project in Ghana is the 150 MW Ayitepa Phase 1 WPP located on the coast of Ghana 60 km east of Accra, within the Ningo-Prampram District. This project, Phase 2 of which would add a further 75 MW for a total of 225 MW, is currently under development with construction tentatively scheduled to commence in the first half of 2016. IFC is mandated to lead the financing arrangements for the Ayitepa WPP and, should the project proceed, will undertake and disclose a full and separate Environmental and Social Review Summary report (such as this one) together with associated documentation at least 60 days prior to the anticipated board date.

In Egypt, Lekela has been awarded a 50 MW WPP concession on the west bank of the Gulf of Suez and a 50 MW solar PV concession in Aswan Governorate. Both projects were awarded under Egypt’s Feed in Tariff scheme in January 2015 and are in early stages of development.

Lekela’s shareholders will provide construction equity to build the South Africa REIPPPP Round 3 projects, any projects with power purchase agreements won in Rounds 4 and 5, as well as projects that meet the investment criteria and are acquired across the rest of Africa.

Overview of IFC's Scope of Review

IFC has reviewed a series of environmental, health & safety and social (E&S) policies, business plans, Environmental & Social Impact Assessments (ESIAs), Environmental (and Social) Management Plans (EMPs), specialist bird and bat studies, permits, Local Economic Development plans and strategies, Equator Principle Reviews and other E&S documentation prepared by Mainstream and Lekela focusing on both corporate E&S management and individual projects in South Africa, Ghana and Egypt.

IFC undertook site visits to the under-construction 80 MW Noupoort WPP, the operational 50 MW De Aar solar PV project (both in Northern Cape Province) and the operational 138 MW Jeffreys Bay WPP in the Eastern Cape Province of South Africa in May 2015. Site meetings were held with construction and operations staff, including those responsible for oversight of E&S matters and local economic development activities. All of these power projects were constructed, or are under construction, by a Mainstream-led consortium. IFC also visited Mainstream’s South African offices in Cape Town and held discussions with key staff on a range of issues including early screening and risk assessment, environmental and social assessment and management, local economic development, security, human resources and bird & bat monitoring protocols.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
Pre-Construction Bird Monitoring Report Loeriesfontein 2 and Khobab.pdf
Loeriesfontein - Final EIA.pdf
Noupoort Pre-Construction Bird Report.pdf
Loeriesfontein - EMP.pdf
Khobab - Final EIA.pdf
Noupoort Final EMP.pdf
Noupoort - Final EIA.pdf
Noupoort Pre-Construction Bat Report.pdf
Khobab - EMP.pdf