PROJECT

Projects

Environmental & Social Review Summary

Project Number

36828

Company Name

SONKER BUNKERING COMPANY S.A.E.

Date ESRS Disclosed

May 6, 2015

Country

Egypt, Arab Republic of

Region

Africa

Last Updated Date

Sep 30, 2022

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Nov 24, 2015
Signed : Dec 17, 2015
Invested : May 30, 2017

Sector

Port and Harbor Operations

Industry

Infrastructure

Department

Gbl Infrastructure & Natural Resources

Project Description

The proposed investment package consists of a senior debt investment of up to US$125 million in addition to a mezzanine facility of up to US$25 million to finance the development and operation of a Liquid Bulk Terminal (LBT, the Project) in Sokhna port on Egypt’s Red Sea coast. The project will be developed by Sonker Bunkering Company (Sonker), which was established in 2003 as a petroleum import, storage, handling, bunkering and blending company. Sonker is a public-private partnership jointly owned by Amiral (63%), Misr Petroleum Company (15%), the Egyptian Ministry of Finance (12%) and Cooperative Petroleum Company (10%).

The development of the LBT is part of the basin 3 port concession that was signed between DP World Sokhna (DPWS) and the Red Sea Port Authority (RSPA) in 2006 which was further amended and re-signed in March 2015.

The project consists of the construction and operation of a dedicated LBT in Sokhna Port, Egypt, with adequate equipment and storage capacity for the handling of Liquefied Petroleum Gas (LPG) and Gasoil imports, berthing of Floating Storage and Regasification Units (FSRU) for LNG imports; and operation of a jetty for import and export of oil and gas products, and chemicals.

The project will include the construction of three Gasoil tanks (total capacity of 100,000 m3), three LPG tanks (total capacity of 150,000 m3), a LPG pipeline (4.3 km), a Gasoil pipeline connecting to the national grid via Mina Sadat (37.5 km), and related infrastructure. The LBT will also berth a Floating Storage and Regasification Unit (FSRU) with a storage capacity of 170,000 m3 rented by the Egyptian Natural Gas Holding Company (EGAS) from Hoegh LNG under a five year rental contract. The FSRU arrived in April 2015 and following testing for the LNG pipelines it started operating and feeding the national grid since mid-April 2015.

The LBT currently includes an operational jetty and two ammonia tanks. The jetty is a free concrete structure, standing on piles in the water. It is designed to provide access for vessels with a capacity of up to 120,000 deadweight tonnage. The ammonia tanks are for temporary storage of exported ammonia product. Loading and unloading of tankers will take place using loading arms, linking the tank farm to the jetty.

The FSRU within the scope of the project will serve as a temporary storage of LNG in its cryogenic tanks, and conduct regasification of the LNG, and compress the natural gas after regasification and deliver the Compressed Natural Gas (CNG) into the national grid pipeline. The FSRU is operated by Hoegh and the pipelines by EGAS.

The FSRU will use seawater to heat and evaporate the LNG. After regasification the natural gas is compressed to approximately 80 bar and delivered through loading arms installed on the jetty into the national grid for distribution to the consumers in the country.

The FSRU has a regasification capacity of approximately 4 million tons (8 million m3) of LNG per year. The LNG will be delivered to the FSRU by a LNG Carrier (LNGC). The LNGC is moored alongside the FSRU and transfers its cargo load through a number of cryogenic flexible hoses into the tanks of the FSRU. The LNGC has capacity of about 170,000 m3.

To enable the safe maneuvering and mooring of the LNGC alongside the FSRU the Basin 3 of Sokhna Port had to be widened through dredging by approximately 70m. The width of the basin on the west side of the jetty after dredging is currently 180 m.

Overview of IFC's Scope of Review

IFC’s appraisal of this project included a site visit to the LBT in basin 3 of Sokhna Port in April 2015 and meetings with the Red Sea Ports Authority (RSPA) and DP World Sokhna. The visit was undertaken in order to review environmental and social policies, management systems and related procedures, including those related to Occupational Health and Safety (OHS).

Meetings were held with Sonker’s Managing Director, the Amiral team, the Project Engineering, Procurement, Construction (EPC) contractor Petrojet, the Project Technical Consultant, Nexant, and the project environmental and social consultant, Environics.

Documents reviewed during the appraisal included Environmental and Social Impact Assessment (ESIA) for the development of a LBT in Sokhna port, Environmental Impact Assessment for widening basin “3” and receiving LNG, marine and process HAZOP Report, basin No. 3 LNG maneuvering simulation and simulation for TUG usage at Ain Sokhna Port LNG Terminal, European Bank for Reconstruction and Development (EBRD) Environmental and Social Due Diligence Report for Sonker project, Sonker Health, Safety, Security and Environment (HSSE) policy, Sonker Fundamentals on Safety Policy, and Sonker Human Resources (HR) policies and procedures.

IFC’s appraisal considered environmental and social management plans for the project and gaps if any between these plans and IFC requirements. Where necessary, corrective measures, intended to close these gaps within a reasonable period of time, are summarized in the paragraphs that follow and in the agreed Environmental and Social Action Plan (ESAP) disclosed in this review summary. Through implementation of these management plans and the ESAP the Project is expected to be designed and operated in accordance with Performance Standards objectives.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan