PROJECT

Projects

Environmental & Social Review Summary

Project Number

35395

Company Name

ACWA GUC ELEKTRIK ISLETME VE YONETIM SANAYI VE TICARET ANONIM SIRKETI

Date ESRS Disclosed

Jul 7, 2014

Country

Turkiye

Region

Central Asia and Turkiye

Last Updated Date

Dec 1, 2016

Environmental Category

A - Significant

Status

Active

Previous Events

Approved : Nov 11, 2014
Signed : Dec 28, 2012
Invested : Jul 22, 2015

Sector

Gas - Thermal Power Generation

Industry

Infrastructure

Department

Regional Industry INF MCT

Project Description

The project is a greenfield natural gas fired combined cycle gas turbine (CCGT) power plant with an installed capacity up to about 928 MW (net generating capacity after deducting auxiliary electricity consumption), including an associated 119 km 380 kV transmission line, with an estimated project cost of about USD 1 billion. IFC’s proposed investment is an A Loan of up to USD125 million and a B Loan of up to USD75 million. EBRD is considering to co-finance this project.

The power plant will be located 50 km east of Ankara, near the city of Kirikkale, Turkey. The project is sponsored by International Company for Water and Power Projects (“ACWA Power”) and will be developed by Acwa Guc Elektrik Isletme ve Yonetim Sanayi ve Ticaret Anonim Sirketi (“ACWA Guc” or “the company”), which is currently owned 99% by ACWA Power. Natural gas will be supplied from the existing Samsun-Ankara natural gas pipeline owned by BOTAS Petroleum Pipeline Corporation which passes through at 3 to 4 km distance from the project site. The company selected a closed wet cooling system to limit water usage. Water will be extracted from 4 to 5 caisson wells to be established at the river bed of Kizilirmak River, which is located about 200 m from the project site. The electricity generating efficiency of the plant will be 59 % (net, LHV basis) or 60% (gross, LHV basis), and as such the plant will be one of the most energy efficient power plants in Turkey.

The power plant will be developed on about 18.5 ha of land located within the boundaries of Kiliclar Municipality of Yahsihan District in Kirikkale Province. Around 2.6 ha of this land and 2.5 ha of additional land required for the caisson wells are privately owned while the rest is owned by the Treasury of the Government of Turkey. This privately owned land is being acquired by the company. The remaining 15.9 ha owned by the Treasury will be leased to the company. The site is a natural meadow and is not presently used for any purposes. The routing of the associated transmission line has been determined by TEIAS (Turkish Electricity Transmission Company) to avoid urban or ecologically sensitive areas and minimize social and environmental impacts. The line will be developed from ACWA Kirikkale plant site to the existing Baglum Substation in Ankara. About 3km of existing rural road from the national Ankara-Kirikkale highway to the project site will be used as an access road. This existing road will be upgraded to allow transportation of heavy equipment.

The company plans to sign the Engineering, Procurement and Construction (“EPC”) agreement with Samsung C&T, and to start construction in late 2014. The construction period will be about 30 months, and the Generation License to be issued by Energy Market Regulatory Authority (EMRA) will allow the company to operate the plant for 49 years. The plant will be operated by ACWA Power’s subsidiary company called NOMAC, an Operation and Maintenance (O&M) operator.

Overview of IFC's Scope of Review

On July 30, 2012, IFC disclosed the ESRS for Farcan Enerji Uretim Anonim Sirketi project (#32503) to develop a greenfield 835 MW natural gas fired combined cycle gas turbine (CCGT) project in Kirikkale, Turkey and received board approval on October 18, 2012. Since then, this project did not move forward to the construction stage. One of the sponsors of that project (ACWA Power) is now planning to develop a new CCGT project with an installed capacity of up to about 928 MW (net) in the same Kirikkale Province, about 3 km from the previous project site. IFC re-conducted its review as described below.

IFC’s review of ACWA Kirikkale Natural Gas Combined Cycle Power Plant Project (“ACWA Kirikkale” or “the project”) consisted of appraising the following technical, environmental, and social information provided by ACWA Guc Elektrik Isletme ve Yonetim Sanayi ve Ticaret Anonim Sirketi (“ACWA Guc”):

Power plant:
Environmental and Social Impact Assessment Report (ESIA) for ACWA Kirikkale Natural Gas Combined Cycle Power Plant Project, June 2014;
ACWA Kirikkale Natural Gas Combined Cycle Power Plant Project, Non-Technical Summary, June 2014; and
ACWA Kirikkale Natural Gas Combined Cycle Power Plant Project, Environmental and Social Management and Monitoring Plan (ESMMP), June 2014.
Associated transmission line:
Environmental and Social Impact Assessment Report (ESIA) for ACWA Kirikkale Overhead Transmission Line Project, June 2014;
ACWA Kirikkale Overhead Transmission Line Project, Non-Technical Summary, June 2014; and
ACWA Kirikkale Overhead Transmission Line Project, Environmental and Social Management and Monitoring Plan (ESMMP), June 2014.
Joint Stakeholder Engagement Plan:
ACWA Power Kirikkale Natural Gas Combined Cycle Power Plant and Overhead Transmission Line Project, Stakeholder Engagement Plan, June 2014.

A visit to the project site and its surrounding areas was conducted by IFC staff on June 24-25, 2014. During the site visit, meetings were held with the representatives of sponsor and ACWA Guc including the project manager, as well as representatives from environmental consultancy that prepared the ESIAs.

IFC appraised ACWA Equity project #33736 (an equity investment in ACWA Power) in 2013 and its ESRS was disclosed on September 20, 2013. In conducting the E&S appraisal of ACWA Kirikkale project, ACWA Power’s corporate level information obtained through ACWA Equity project appraisal was also used.

IFC’s appraisal considered environmental and social management plans for the project and gaps between these plans and IFC requirements. Where necessary, corrective measures intended to close these gaps within a reasonable period of time, are summarized in the paragraphs that follow and in the agreed Environmental and Social Action Plan (ESAP) disclosed in this review summary. Through implementation of these management plans and the ESAP the project is expected to be designed and operated in accordance with Performance Standards objectives.

In addition to the ACWA Equity project (#33736) mentioned above, IFC has two existing portfolio projects owned by ACWA Power. The first was ACWA Power Jordan (#30794), an investment in an existing Jordanian electricity generation company called CEGCO in Jordan. The second project is Karadzhalovo SPP (#31543), a 60 MWp photovoltaic solar project in Bulgaria (previously developed by another company, but is now majority owned by ACWA Power). These projects are being monitored and to date IFC has evaluated their E&S performance as satisfactory.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
ACWA Power OHTL NTS Turkish.pdf
ACWA Power OHTL NTS English.pdf
ACWA Power OHTL ESMMP English.pdf
ACWA Power OHTL ESMMP Turkish.pdf
ACWA Power OHTL ESIA Annexes English.pdf
ACWA Power OHTL ESIA Annexes Turkish.pdf
ACWA Power OHTL ESIA Turkish.pdf
ACWA Power OHTL ESIA English.pdf
ACWA Power NGCCPP NTS Turkish.pdf
ACWA Power NGCCPP NTS English.pdf
ACWA Power NGCCPP ESMMP Turkish.pdf
ACWA Power NGCCPP ESMMP English.pdf
ACWA Power NGCCPP ESIA Turkish.pdf
ACWA Power NGCCPP ESIA Annexes English.pdf
ACWA Power NGCCPP ESIA Annexes Turkish.pdf
ACWA Power NGCCPP ESIA English.pdf
ACWA Power OHTL SEP Turkish.pdf
ACWA Power NGCCPP OHTL SEP Appendix English.pdf
ACWA Power NGCCPP OHTL SEP Appendix Turkish.pdf
ACWA Power NGCCPP OHTL SEP English.pdf