PROJECT

Projects

Environmental & Social Review Summary

Project Number

35364

Company Name

ENERGIA CINCO ESTRELLAS SA DE CV

Date ESRS Disclosed

Nov 18, 2014

Country

Honduras

Region

Latin America and the Caribbean

Last Updated Date

Jun 14, 2024

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Feb 26, 2015
Signed : Mar 20, 2015
Invested : Jun 19, 2015

Sector

Solar - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry INF LAC & EUR

Project Description

The Aura Solar II project (the “Project” or the “Company”) entails the development of a photovoltaic solar plant with capacity of 61MWdc/50MWac by the Sponsors. The plant is in stage of design and is expected to begin construction in Q4 2014. It will be sited in the Choluteca Municipality near the El Carrizo community, which is approximately located 152 km south of the capital city of Tegucigalpa. Aura Solar II is expected to generate approximately 125 GWh per annum. The Project will be located over an area of 150 hectares of modified habitat and agricultural pasture land. The Project will be interconnected to Santa Lucia - an existing substation located in the outskirts of Choluteca - via dedicated 34.5 kV single pole transmission lines with a length of 11 km, along an existing road. Given the peri-urban siting of the Santa Lucia substation, the last 50 meters of the transmission line will be buried.

The equipment for the Project will consist of proven ground mounted photovoltaic crystalline modules, and integrated inverter and transformation centers. Construction is expected to be completed by Q2 2015.

Overview of IFC's Scope of Review

IFC reviewed Corporación Aura Solar (“CAS”) and the Flores Family (together the "Sponsors") Environmental, Social and Health and Safety (ESHS) capabilities and ability to construct and operate the Aura Solar II project in accordance with the Honduran regulatory requirements and IFC’s Performance Standards. Specific items reviewed included, but were not limited to, the Environmental Impact Assessment (EIA), environmental licenses, operating contracts and other supporting documents, as well as the Sponsors’ corporate ESHS policies and procedures. IFC conducted a visit to the proposed project site in July 2014, and interviewed the project’s management team and site personnel.

IFC’s appraisal considered environmental and social management plans for the project, and gaps between these plans vis-à-vis IFC requirements. Corrective measures to close these gaps within a reasonable period of time are summarized in the paragraphs that follow and in the agreed Environmental and Social Action Plan (ESAP) disclosed together with this review summary. Through implementation of these management plans and the ESAP, the project is expected to be designed and operated in accordance with Performance Standards objectives

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
Estudio de impacto ambiental.pdf