B - Limited

Status

Completed

Previous Events

Approved : Sep 26, 2014
Signed : Nov 14, 2014
Invested : Nov 24, 2014

Sector

Elementary and Secondary Schools

Industry

Health, Education and Life Sciences

Department

Regional Industry - MAS Asia & Pac

Project Description

Founded in 1995 in Dalian, Maple Leaf offers a bilingual, dual-curriculum (Canadian and Chinese) and dual-diploma programs and currently operates the largest network of schools offering such an international program in China. (http://www.mapleleafschools.com)

As of August 2014, Maple Leaf’s footprint comprised of 7 high schools, 7 middle schools, 6 elementary schools, 11 preschools/kindergartens and 2 foreign national schools located primarily in Tier II, Tier III and Tier IV cities in China, with a total capacity of about 22,500 students. In addition, five new schools will open in September 2014 - two schools in Tianjin, two new schools in Pinddingshan and one new school in Shanghai.

Maple Leaf owns its school buildings and land use rights in 5 of the 8 cities in which it operates (Dalian, Wuhan, Tianjin, Chongqing, Zhenjiang, and Shanghai). However, since 2012, the company has adopted an asset-light approach by partnering with third parties, in particular local government, to develop new schools. Accordingly, the company signs a cooperation agreement making the third party responsible for acquiring the campus sites and building the school premises as per the specifications provided by Maple Leaf. The third party continues to own the asset while Maple Leaf takes it over only as the operator.

Maple Leaf is preparing for its listing on Hong Kong Stock Exchange and would like IFC to participate in this capital raise as a cornerstone investor. IFC is thus considering an equity investment of US$20 million in Maple Leaf, which would enable the company to further scale up its high quality and low cost private education network in Tier II, III and IV cities where equivalent offerings are scarce.

Proceeds of the planned IPO will be used to open sixteen new schools in Tier II, Tier III and Tier IV cities in China, creating additional capacity for over 11,000 new students (“Project”). The company is in advanced stages of negotiations and planning for a total of twelve new schools in Pinghu (a Tier 4 city), Xi’an (which is in a frontier region) and Yiwu (a Tier 4 city).

Overview of IFC's Scope of Review

IFC’s review of this proposed investment consisted of appraising technical; environment, health and safety, (EHS) and social related information provided by China Maple Leaf Education Systems ( (“Maple Leaf” or “the company”) such as organization chart, human resources (HR) policies and procedures; design briefs for new schools, standardized format of cooperation agreement for developing new schools by third parties, fire safety permits and designs for existing schools, campus safety regulations, emergency response plans, and EHS related key performance indicators (KPIs) and other operational documents.

The appraisal also included a site visits to Maple Leaf’s campuses in Dalian and Wuhan during 20-21 August 2014 and discussions with its senior management as well as the technical and HR teams at the company’s corporate headquarters in Dalian.

As the proposed investment is a corporate investment covering multiple campuses spread across China, IFC’s due-diligence reviewed the management systems at the corporate level – such as policies, procedures, organizational structure and capacity – to manage E&S risks and impacts. Visits to operational schools were thus made to assess the ground level implementation of these management systems.

IFC’s appraisal considered environmental and social (E&S) management plans for the Project and gaps, if any, between these plans and IFC requirements. Where necessary, corrective measures intended to close these gaps within a reasonable period of time are summarized in the paragraphs that follow. Through implementation of these actions, the Project is expected to be designed and operated in accordance with Performance Standards objectives.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan