PROJECT

Projects

Environmental & Social Review Summary

Project Number

34588

Company Name

ENERGIA DEL PACIFICO S.A. DE C.V.

Date ESRS Disclosed

Aug 1, 2018

Country

El Salvador

Region

Latin America and the Caribbean

Last Updated Date

Jun 12, 2021

Environmental Category

A - Significant

Status

Active

Previous Events

Approved : Jun 6, 2019
Signed : Nov 20, 2019
Invested : Dec 20, 2019

Sector

Gas - Thermal Power Generation

Industry

Infrastructure

Department

Regional Industry - INF LAC

Project Description

 Invenergy Clean Power El Salvador, Ltda. de C.V. (hereinafter Invenergy or ICPES) and Quantum Energy S.A. de C.V are the Sponsors of the “Acajutla LNG” project and shareholders of Energía del Pacífico Ltda. de C.V. (EDP), the project company. The project involves the construction and operation of a 378-megawatt (MW) thermal power plant at the port of Acajutla in the Department of Sonsonate in El Salvador and a marine terminal, consisting of a floating storage regasification unit (FSRU) permanently moored, for liquified natural gas (LNG) delivery, storage, and regasification, as well as a natural gas pipeline that will run from the FSRU to the power plant. The project includes the construction of a 44 km, 230 kilovolt (kV) transmission line and related substations to connect the power plant to the electrical grid of El Salvador. The power plant will be located in a brownfield port and industrial area in the municipality of Acajutla, in premises secured under a 24-year lease agreement with the Executive Commission of the Port of Acajutla (CEPA), who owns and manages the port.

The power plant will consist of 19 Wärtsilä 18V50SG internal combustion reciprocating engines with capacity of 18.9 MW each, and a combined steam cycle system that will use the exhaust gases of the engines to produce additional 26 MW.  The LNG marine import terminal consist of a Restricted Catenary Mooring (RCM) system and a dedicated and chartered FSRU located approximately 1.2 km offshore.  LNG carriers will moor directly to the FSRU with flexible hoses utilized to transfer LNG. The FSRU will receive approximately six LNG shipments per year.  A combination of a flexible 3-D riser and a subsea gas pipeline will transfer the re-gasified natural gas from the FSRU to the onshore power plant.  The transmission line (T-Line) between the Electricity Transmission Company of El Salvador (ETESAL) substations of Acajutla and Ahuachapán will have approximately 139 towers and a 38-meter wide right-of-way (ROW).  The project involves the construction of a switchyard inside the project site in the port of Acajutla and the expansion of both substations.

Civil works at the plant site are scheduled to commence in the second quarter of 2019 with a project’s commercial operation day (COD) planned for July 1st, 2021.  IFC’s proposed investment will comprise of a direct loan of US$ 100 million, a US$ 40 million credit guarantee and syndication of US$ 425 million.                                               

Overview of IFC's Scope of Review

 IFC’s environmental and social (E&S) review of this project consisted of appraising technical, environmental, health, safety and social information submitted by EDP and its consultants. The IFC scope of review during EDP’s appraisal included the environmental and social impact assessments (ESIAs) for the power plant, the marine terminal and the T-Line, including the addenda filed as a result of the modification of the marine terminal design and configuration, E&S field studies and monitoring reports, supplemental studies developed by EDP on biodiversity, cumulative impact assessment, occupational health and safety and E&S management plans, marine traffic safety, existing security management practices, and ongoing and planned stakeholder engagement activities.

IFC’s E&S specialists conducted a field visit from November 28th to December 1st, 2017. The visit included the power plant and marine terminal sites, selected areas of the T-Line ROW, the Acajutla substation to be expanded by EDP, and different areas of the port. In addition, RINA Consulting was retained to serve as independent environmental and social consultant for the Lenders participated in the field visit.

IFC’s appraisal included technical meetings with EDP, Invenergy and their E&S consultants (Dillon Consulting, Environmental Resources Management - ERM, and EcoIngenieros), interviews with fishermen, landowners and other project affected people, municipal government officials, port administrators and officials and representatives of institutions managing EDP’s social investment fund.  The team visited key biodiversity areas, including the shoreline, beach and other areas of significant biodiversity value along the T-Line.                                                  

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
3.2 Adenda ESIA Planta Generadora-Terminal Maritima - Parte 2.pdf
3.1 Adenda ESIA Planta Generadora-Terminal Maritima - Parte 1.pdf
2. Resolucion Permiso Ambiental MARN PP-MT.pdf
2. Resolucion Permiso Ambiental MARN T-Line.pdf
1.8 ESIA Original Planta Generadora-Terminal Maritima - Parte 8.pdf
1.7 ESIA Original Planta Generadora-Terminal Maritima - Parte 7.pdf
1.6 ESIA Original Planta Generadora-Terminal Maritima - Parte 6.pdf
1.5 ESIA Original Planta Generadora-Terminal Maritima - Parte 5.pdf
1.4 ESIA Original Planta Generadora-Terminal Maritima - Parte 4.pdf
1.3 ESIA Original Planta Generadora-Terminal Maritima - Parte 3.pdf
1.2 ESIA Linea de Transmision - Parte 2.pdf
1.1 ESIA Linea de Transmision - Parte 1.pdf