Project Number

34448

Company Name

RECORDATI ILAÇ SAN.VE TIC. A.S.

Date ESRS Disclosed

Apr 24, 2014

Country

Turkiye

Region

Central Asia and Turkiye

Last Updated Date

Mar 2, 2023

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Jun 6, 2014
Signed : Jun 19, 2014
Invested : Oct 16, 2014

Sector

Pharmaceuticals and Medicine

Industry

Health, Education and Life Sciences

Department

Regional Industry MAS MCT

Project Description

Recordati Ilaç (the “Company”), the Turkish subsidiary of Italy-based Recordati S.p.A. (“Recordati” or “the Sponsor”), is one of the leaders in the Turkish pharmaceuticals market for urological and cardiovascular disorders. Recordati Ilaç has an existing manufacturing plant in Esenyurt, Istanbul, Turkey.

The Project involves establishment of a new pharmaceutical manufacturing plant in the Çerkezköy Organized Industrial Zone (“COSB”) in the Marmara region of Turkey, addressing the Company’s need to relocate, expand and upgrade its existing production activities. The new factory will have a production area of 5,000 m2, with additional utilities, warehousing and logistics areas on a 45,000 m2 plot, and is expected to be fully developed by 2018. IFC proposes to provide an A loan in the amount of €25 million equivalent in Turkish Lira to support Recordati Ilaç.

Overview of IFC's Scope of Review

IFC’s review included meetings at Recordati’s headquarters in Italy with Recordati’s project team and new process design consultants, a visit to the proposed site of the new facility at Çerkezköy Organized Industrial Zone, a meeting with the District Director of the zone and further meetings with Recordati Ilaç’s General Manager, Factory Manager, Human Resources Manager, and environmental and occupational health and safety specialists. These meetings were supplemented by a review of design data for the new Recordati Ilaç site, an assessment of the project’s likely environmental and social impacts, factory, human resources, environmental and occupational health and safety data describing operations of Recordati Ilaç’s existing facility at Esenyurt, Istanbul and a walk-through inspection of this facility.

IFC’s appraisal considered the environmental and social management planning process and documentation for the project, as described above, and gaps, if any, between these and IFC’s requirements. Where necessary, corrective measures, intended to close these gaps within a reasonable period of time, are summarized in the paragraphs that follow and in an agreed Environmental and Social Action Plan (ESAP). Through implementation of these measures, the Project is expected to be designed and operated in accordance with Performance Standards objectives.

If IFC’s investment proceeds, IFC will periodically review the project’s ongoing compliance with the Performance Standards.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan