PPC BARNET DRC MANUFACTURING SA
Mar 25, 2014
Congo, Democratic Republic of
Africa
Dec 1, 2016
A - Significant
Active
Approved : Jun 5, 2014
Signed : Aug 12, 2014
Invested : Apr 16, 2015
Cement
Manufacturing
Gbl Ind, Manufact, Agribus & Services
| Title | Anticipated completion Date | Status | Comments | Completion Date |
|---|---|---|---|---|
| PPC will develop a clear social performance policy, approved by its board at the corporate level to, supplement its company-wide Environmental Policy as well as an overall environmental and social policy for its DRC operations, approved at the country board level. | 12/30/2014 09:00:00 PM | Completed | Completed | 11/27/2014 09:00:00 PM |
| PPC will complete and publicly disclose the comprehensive Environmental and Social Impact Assessment (ESIA) and Environmental and Social Management Plan (ESMP). In addition to the direct project activities, the ESIA and ESMP must address potential impacts / mitigation measures associated with the new power line. | 10/30/2014 10:00:00 PM | Completed | Completed | 12/04/2014 09:00:00 PM |
| PPC will finalize and implement a comprehensive Environmental and Social Management System (ESMS) for its DRC project by 31 December 2014, including an ESMP, additional management plans, and specific measures to address the following four items: | 12/30/2014 09:00:00 PM | Completed | Completed | 12/18/2014 09:00:00 PM |
| • Expanding and reinforcing its monitoring and reporting system with special regard to its DRC operations, including reporting regularly to communities and other key stakeholders on how risks are identified, analyzed, and mitigated and the progress (or lack thereof) that the company is achieving with regard to mitigating negative impacts and enhancing positive project benefits. | 12/30/2014 09:00:00 PM | Completed | Completed | 03/04/2015 10:00:00 PM |
| • Implement an effective external grievance mechanism. | 04/29/2014 11:00:00 PM | Completed | Completed | 04/24/2014 11:00:00 PM |
| • Apply a Cultural Heritage Management Plan (with a Chance-Find Procedure) by start of construction. | 03/30/2014 11:00:00 PM | Completed | Completed | 04/06/2014 11:00:00 PM |
| • Develop and implement a comprehensive Stakeholder Engagement Plan and Community Development Plan. The Community Development Plan shall include measures to strengthen the capacities of nearby towns such as Kimpese and, if relevant, Songololo to plan for and manage the increased impacts of secondary population influx (e.g., from the establishment of third-party trucking and logistics companies that will service PPC operations). | 10/30/2014 10:00:00 PM | Completed | Completed | 10/29/2014 10:00:00 PM |
| PPC will conduct a third-party labor and OHS audit of the EPC contractor’s practices ca. 6 months after the start of civil works under the EPC contract to ensure that the EPC contractor’s labor practices conform with IFC’s Performance Standard 2 and identify any gaps that PPC would need to address. | 09/29/2015 11:00:00 PM | In Progress | Due date revised as agreed with IFC client | |
| PPC is required to conduct a third-party audit of labor practices, including those related to occupational health and safety (OHS), for its principal providers of contracted/subcontracted services within one year of the start of full operations to ensure conformity with the IFC’s Performance Standard 2 and to identify any gaps that PPC would need to address. | 12/31/2017 | In Progress | In Progress | |
| PPC will create an internal action plan by 31 December 2014, based on the Community Health and Safety Plan to be disclosed by 31 October 2014, and develop appropriate partnerships with health authorities, local health providers including NGOs, and other relevant stakeholders to strengthen local health infrastructure and services and to begin implementing such a plan by 31 January 2015. PPC will conduct an audit of progress in implementing this plan by 31 December 2015. | 12/31/2015 | In Progress | In Progress | |
| PPC will include in its plant design an internal waiting area sufficiently large to accommodate 200-300 trucks per day. This waiting area will be secure and properly provisioned with sanitation, food services, and other small shops so as to minimize if not eliminate the need for waiting truckers to enter nearby villages for such services. | 05/30/2014 11:00:00 PM | Completed | Completed | 06/21/2014 11:00:00 PM |
| PPC will carry out a security risk assessment and develop appropriate policies and procedures for managing the project’s use of and relationship with security personnel, whether public or private (including either an in-house or third-party guard force), in accordance with IFC Performance Standard 4. | 08/30/2014 11:00:00 PM | Completed | Completed | 08/30/2014 11:00:00 PM |
| PPC will develop a comprehensive approach to land acquisition, compensation, and livelihood restoration for economic displacement as well as provisions for physical resettlement (if necessary in the future). Specifically, PPC will develop and approve a Resettlement and/or Livelihood Restoration Framework to guide the future acquisition of land (including compensation), to manage economic and any physical resettlement that might arise, to secure the replacement of productive land, to provide assistance for restoring and improving productive activities for those affected by economic displacement, and to provide social support networks of all vulnerable affected families. | 05/30/2014 11:00:00 PM | Completed | Completed | 06/16/2014 11:00:00 PM |
| PPC will by 31 December 2014 and within one year of any further displacement, whether economic and/or physical, complete a Land Acquisition, Compensation, and Livelihood Restoration Report, including: (a) detailed information on land/properties acquired and to be acquired; (b) socio-economic baseline information of affected owners and their families; (c) impact assessment on the livelihoods of vulnerable or land-dependent families, if relevant; (d) vulnerability analysis and eligibility for assisted resettlement and/or livelihood restoration for individual families, if relevant; (e) evidence of consultations and compensation alternatives offered by PPC; (f) compensation packages agreed upon with each affected village (if common land) or individual families in the event of direct impacts, if relevant; and (g) support given or to be given by PPC for community compensation, resettlement, employment/income restoration, and reestablishment of living conditions, if relevant. | 12/30/2014 09:00:00 PM | Completed | Completed | 12/18/2014 09:00:00 PM |
| PPC will conduct all future project-related land acquisition in accordance with the above-referenced Land Acquisition, Compensation, and Livelihood Restoration Framework. In the event that land acquisition for ancillary components (i.e. housing for permanent workforce, access roads, railway spur, etc.) results in economic and/or physical displacement, PPC will prepare a site-specific action plan that conforms with the Framework, a report on the implementation of such a plan, yearly livelihood monitoring reports (if relevant), and a completion audit. | 03/30/2016 11:00:00 PM | In Progress | Due date revised as agreed with IFC client | |
| PPC will update existing agreements with affected villages and bring them into alignment with PPC corporate approaches and good international industry practice, including detailed implementation plans and timetables. Any new or updated agreement with the affected villages should be in form and substance satisfactory to IFC. | 07/29/2014 11:00:00 PM | Completed | Completed | 08/31/2014 11:00:00 PM |
| PPC will prepare a quarry management and rehabilitation plan including the following distinct items: a: Tentative full quarry utilization plan including tentative final contours, with overburden and top soil application and vegetation. To be ready before production usage of the quarry starts: b: Overburden and top soil storage and reapplication planning. To be ready before the production usage of the quarry starts; c: Five year rolling quarry management and rehabilitation plans including quarry contours, overburden reapplication and top soil needs, and replanting goals: and d: One year detailed quarry utilization, contouring, overburden and top soil application plans, including re-vegetation details and targets. Establish a nursery providing the necessary seedlings for the rehabilitation of plant and quarry areas. Focus should be given to indigenous plants, with special focus on any potentially locally endangered species, which should be favored in the rehabilitation. Establish a quarry pit water control, that allows for all pit water to be controlled for and if needed treated for contaminants, especially ammonia caused by explosives usage, before any discharge to water courses or application to areas which could cause ground water contamination. Establish safety beams along ascent and decent roads in the quarry to provide safety for the haul trucks. | 08/30/2015 11:00:00 PM | In Progress | Due date revised as agreed with IFC client | |
| Establish continuous emission monitoring for NOx, SOx, and dust at the main stack and develop and implement an ambient air quality monitoring program with a specific focus on communities. Dec 31, 2016 | 12/31/2016 | In Progress | In Progress | |
| Establish procedures to ensure trucks delivering bulk raw materials to the plant and cement to the customers are not permitted to carry more load than what they are approved for. | 12/31/2016 | In Progress | In Progress |