PROJECT

Projects

Environmental & Social Review Summary

Project Number

33985

Company Name

KOMPANIYA NADEZHDA, PP

Date ESRS Disclosed

Nov 4, 2013

Country

Ukraine

Region

Europe

Last Updated Date

Aug 25, 2023

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Apr 4, 2016
Signed : May 27, 2016
Invested : Nov 14, 2016

Sector

All Other Chemical Product

Industry

Manufacturing

Department

Regional Industry MAS LAC & EUR

Project Description

Nadezhda is a private Enterprise Company that operates as a retailer and wholesaler for the distribution of petroleum products focusing primarily on LPG. The company is the second largest LPG distributor in the Ukraine and has a strategic vision of building on its strength in LPG and expanding further both in LPG and traditional fuels e.g., gasoline and diesel, distribution. Nadezhda requested IFC to provide additional support to expand the number of fuel filling stations from 80 to nearly 97 through the acquisition or construction of 17 fuel stations and to replace short term working capital loans with long term financing (the “Project’). Most of the new stations will be LPG filling stations as planned at this stage.

The proposed Project is synergistic with the company’s existing infrastructure as the company owns an extensive network of depots and fuel filling stations in the Poltava, Kharkov, Sumy and Donetsk regions of the Ukraine.

Currently the company operates 80 filling stations which consists of 50 LPG filling stations, 30 multi-fuel stations, 5 fuel storage terminals (4 of which are owned and one small terminal which is leased on an annual basis), 40 LPG distribution trucks (the largest fleet in Ukraine) and 30 petroleum product distribution trucks. There is a train terminal within each fuel storage terminal for fuel transportation.

Overview of IFC's Scope of Review

The review of this project consisted of appraising technical, environmental, health, safety, and social information submitted by the project sponsor. The environmental and social (E&S) appraisal team visited liquefied natural gas (LPG) filling stations, fuel terminals, the LPG transportation fleet, and visited the corporate operations control center in Poltava, Ukraine. The E&S team held meetings with the corporate management team including the company Director, the Chief Engineer, the Chief Environmental Manager, Manger for Community Engagement and the Human Resources Manager. The team also reviewed the client’s E&S management documents, including various policies, procedures, monitoring reports, etc.

The paragraphs that follow describe the findings of this review and, where necessary, corrective measures intended to close these gaps within a reasonable period of time are summarized in the paragraphs that follow and in the agreed Environmental and Social Action Plan (ESAP) disclosed with this review summary. Through implementation of these management plans and the ESAP the Project is expected to be designed and operated in accordance with the Performance Standards objectives.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan