Environmental & Social Review Summary

Project Number

33944

Company Name

SHANDONG HEKANGYUAN POULTRY BREEDING INC LTD

Date ESRS Disclosed

Dec 6, 2013

Country

China

Region

East Asia and the Pacific

Last Updated Date

Dec 1, 2016

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Jul 15, 2014
Signed : Nov 26, 2014
Invested : Apr 22, 2015

Sector

Poultry Farming

Industry

Agribusiness and Forestry

Department

Gbl Ind, Manufact, Agribus & Services

Project Description

Shandong Hekangyuan Poultry Breeding Company Ltd. (“Hekangyuan - HKY” or the “Company”) was established in December 2010. Currently, HKY operates through twenty one (21) active subsidiaries, organized across three (3) main business segments, including:

1) Duck breeding division has 8 subsidiaries, located in Shandong, Hebei and Jiangsu provinces. Both grandparent stock (GP) and parent stock (PS) ducks are bred, with existing capacity of around 80 million PS day-old ducklings (DODs) per annum;

2) Broiler breeding division has 3 subsidiaries, located in Shandong and Hebei provinces with capacity of around 38 million PS day-old chicken (DOCs) per annum;

3) Commercial growing poultry (duck and broiler) division, operated by 10 subsidiaries in Shandong with production capacity per annum of 4 million broilers birds and 10 million ducks. About 90% of the farming is contracted to independent farms.

Post the expansion, HKY can be the top 2 duck company and the top 5 broiler company by 2016, with total breeding capacity of 189 million day-old ducks and 90 million day-old broilers, and locations in Shandong, Jiangsu and Hebei provinces (the “Project”). The construction of the Project has already commenced and it is expected to be completed over the next 18-24 months.

The Project’s total cost is estimated to be US$51.7 million equivalent, including $34.6 million for equipment, building & construction including a 10% contingency, and $17.1 million for working capital. The Project is proposed to be financed by an IFC equity investment of US$10 million, existing cash balance and internal cash generation of US$15.5 million and a short-term loan of US$26.2 million equivalent from local banks.

Overview of IFC's Scope of Review

The scope of the appraisal by IFC’s environmental and social (E&S) specialist which took place from August 6-10, 2013 in Shandong Province, China, included the following:

Site visits to the duck hatcheries in Feicheng (leased facility) and in Ningyang (owned facility – in process of being completed), a feed mill in Cangshan, and the Parent Stock (PS) duck breeding farm in Ningyang using close-circuit television (CCTV), and contracted broiler and duck growing farms in Tai’an and in Linyi Country;
Meeting with members of HKY’s senior management, including Mr. Meng Qingli, Chairman President; Mr. Wang Sheng, Executive President; Mr. Xuan Jiafeng, Vice President; and Mr. Chen Jinpeng, HR Manager. Meetings with technical staff at each site (e.g., associated general director, technical director, farm head, veterinarian) also took place;
Review of key documents provided by HKY, including responses to the IFC’s E&S appraisal questionnaire, sample of Environmental Impact Assessment (EIA) Studies, construction and operational permits for the breeding/growing farms and hatcheries delivered by the local environmental and husbandry departments; environmental, human resources and occupational health and safety (OHS) policies, Standard Operating Procedures (SOPs) for duck production, monitoring reports, contractual agreement with licensed service providers (e.g. pest control and management, waste collection and disposal); veterinary disease control, including biosecurity measures and immunization plans; emergency preparedness and response procedures; energy and water consumption, and land leasing procedure.

IFC appraisal considered environmental and social management plans for the Project and gaps, if any between these plans and IFC requirements. Where necessary, corrective measures, intended to close these gaps within a reasonable period of time, are summarized in the paragraphs that follow and in the agreed Environmental and Social Action Plan (ESAP) disclosed in this review summary. Through implementation of these management plans and the ESAP, the Project is expected to be designed and operated in accordance with Performance Standards objectives.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan