PROJECT

Projects

Environmental & Social Review Summary

Project Number

33914

Company Name

REDE D'OR SAO LUIZ SA

Date ESRS Disclosed

Sep 10, 2014

Country

Brazil

Region

Latin America and the Caribbean

Last Updated Date

Jun 12, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Nov 5, 2014
Signed : Dec 4, 2014
Invested : Oct 28, 2015

Sector

Hospitals and Clinics

Industry

Health, Education and Life Sciences

Department

Gbl Ind, Manufact, Agribus & Services

Project Description

Founded in 1977 and based in Rio de Janeiro, Rede D''Or São Luiz S.A. ("Rede D''Or" or "the Company") is a for-profit healthcare provider with the largest network of private hospitals in Brazil. The company''s 23 hospitals, comprising 3,700 beds, and its 30 oncology clinics are located in the states of São Paulo, Rio de Janeiro, Pernambuco, and the Federal District (Brasilia). The IFC''s investment, which is a proposed loan of $50 million and the mobilization of up to $151 million in additional financing, is aimed at assisting Rede D''Or to increase the number of its beds by 1,900 by expanding the capacity of some of its existing hospitals or building new ones. In the period covered by the IFC''s investment, Rede D''Or plans to expand through 2-3 greenfield construction projects (in São Caetano, São Paulo, and at two locations in southern Rio de Janeiro city), and the company has major expansion plans for seven of its current hospitals. Expansion of Rede D''Or''s bed space through greenfield construction or adding wards to existing units involves the design, permitting, construction, and commissioning of this new capacity.

In addition, the company is seeking to expand beyond the targeted 1,900 additional beds through acquisition of existing hospitals. The exact location of potential acquisition targets is not yet known; however, it is likely that they will be located outside of Rede''s current geography of hospitals. Based on a gap analysis conducted prior to acquisition and implemented intensively during the first years after any purchase, Rede D''Or will integrate these hospital operations into its own systems, including those that form its Environmental and Social Management System (ESMS), and bring them into conformity with the company''s standards. Based on recent experiences with acquisitions, this process involves Rede D''Or investments and upgrades in the building design, equipment, and personnel of the acquired hospitals.

At the time of appraisal, Rede D''Or''s workforce consisted of 30,608 staff at its hospitals, clinics, research institute, and corporate offices. It has also hired third-party contractors for providing cleaning, catering services, unarmed site security, maintenance of certain types of equipment, and removal and disposal of hospital waste, including hazardous ones. Through the amalgamation of many back-office functions across the entire hospital group – such as appointment scheduling, IT, finance, and purchasing – Rede D''Or is seeking efficiency gains in its workforce through reassignments, consolidations, and organic attrition. For its greenfield construction and the expansion of existing units, Rede D''Or acts as its own general contractor but hires outside providers for specific architectural, engineering, and construction services.

Overview of IFC's Scope of Review

IFC’s Environmental and Social Due Diligence of this project included meetings with executives and senior managers in Brazil responsible for overall company management as well as for specialized areas such as facilities and maintenance, occupational health and safety, human resources, and design and construction of new facilities. In addition, the IFC met with safety technicians at each of the visited facilities.

The due diligence also included field visits to the following locations: (1) the newly-constructed Caxias D''Or hospital in Rio de Janeiro, (2) the Itaim maternity ward in São Paulo, (3) the recently-acquired Jabaquara hospital (formerly Nossa Senhora de Lourdes) in São Paulo, and (4) the recently-acquired Esperança hospital and maternity ward in Recife, Pernambuco.

The IFC appraisal considered environmental and social management plans for the project, and it sought to identify and analyze any gaps between these plans and IFC requirements. As Rede D’Or has been an IFC client since 2010 (project no. 28144), with IFC support previously assisting the company to invest in and support its organic growth strategy, this review also took into account information available on the company''s recent environmental and social performance during the IFC''s first investment, an ongoing loan. In the course of the appraisal it was determined that implementation of the Environmental and Social Action Plan (ESAP) under the first loan has not been in full compliance with regard to life and fire safety provisions, and the IFC and the client are working together to identify the most suitable solution.

Wherever necessary, corrective measures intended to close gaps under the new investment are summarized in the paragraphs that follow and in the agreed ESAP that is being disclosed together with this review summary. Through implementation of these management plans and the ESAP, this project is expected to be designed and operated in accordance with the objectives of the Performance Standards.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan