PROJECT

Projects

Environmental & Social Review Summary

Project Number

33853

Company Name

BAJRADAYA SENTRANUSA, PT

Date ESRS Disclosed

Feb 10, 2014

Country

Indonesia

Region

East Asia and the Pacific

Last Updated Date

Dec 1, 2016

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Apr 30, 2014
Signed : May 28, 2014
Invested : Sep 29, 2014

Sector

Large Hydro - Renewable Energy Generation

Industry

Infrastructure

Department

Gbl Infrastructure & Natural Resources

Project Description

IFC is considering an A-loan of up to USD 75 million, as well as a possible B-loan and small equity participation to support BDSN’s operational 180 MW Asahan-1 hydropower plant (HPP) in North Sumatra, Indonesia. The plant has been fully operational since January 2011 and sells electricity to PLN pursuant to a long-term PPA expiring on Dec 31, 2040 on a take-or-pay basis of 1,175 GWh of electricity per year. Asahan-1 is developed by the Independent Power Producer (IPP) BDSN, which is owned by Fareast Green Energy and PJB, a subsidiary of PLN (the national power company), respectively. The HPP located 25 km downstream of Lake Toba on the Asahan River in North Sumatra, Indonesia, approximately 130 km southeast of the city of Medan. Land acquisition and construction of the plant was initiated in 1997, but was stalled a year later following Indonesia’s financial crisis. Construction restarted in 2006/7 and the HPP was finally commissioned in 2010, having been constructed and part-financed by China Haudian Engineering Corporation (CHEC), which also acted as the EPC contractor and subsequently managed by CHD Power Plant Operation Co. Ltd (CHDOC) as the O&M contractor until December 31, 2013, whereupon it was replaced by PJB Services.

Asahan-1 is a run-of-river scheme developed to utilize the hydraulic head between the Regulating Dam and Siguragura Dam of the pre-existing Asahan-2 project, a three dam cascade developed between 1975-1982 to support the PT Inalum smelter, located on the North Sumatra coastline near Medan.The Asahan-2 scheme, which IFC is not supporting, comprises a 39 m Regulating Dam, a 47 m, 286 MW Siguragura Dam and HPP and a 73 m, 317 MW Tangga Dam and HPP. The scheme relies on releases from Lake Toba, the largest volcanic lake in the world, as the Asahan River is the primary drainage of this lake to the Straits of Malacca. The Asahan Authority, comprised of a number of state entities, was established to ensure smooth operation of the Asahan-2 project, including the Inalum smelter (originally developed and majority owned by several prominent Japanese companies, now owned and operated by the Indonesian Government).

The Asahan-1 HPP comprises of a 6.5 km tunnel, 70 m surge shaft, 275 m penstock, powerhouse with two 90 MW Francis turbines, accommodation camp and switchyard (the latter handed over to PLN). The intake is located in the pre-existing Regulating Dam which drains water directly from Lake Toba, and the powerhouse is located at the top end of the pre-existing Siguragura Dam, into which the tailrace empties. The project is linked to the grid by an 8 km transmission line, though BDSN only owns and maintains the three transmission towers that link the transformer at the powerhouse with the switchyard.

Overview of IFC's Scope of Review

IFC’s environmental and social appraisal of this project included a site visit held in December 2013.During this visit, the IFC teamtoured the main project facilities (intake area, powerhouse, staff accommodation camp) and met with BDSN management both on site in North Sumatra and at the company office in Jakarta. Discussions were also held on site with the leaders of the two closest villages, namely Ambar Halim and Siruar, in order to better understand any legacy social concerns as well as any possible ongoing concerns of affected communities.

IFC also reviewed various background project reports including technical descriptions, the Clean Development Mechanism (CDM) final report for the project, an internal environmental and social (E&S) due diligence report compiled by ERM Indonesia in 2012, and existing drafts of BDSN E&S procedures. IFC’s appraisal considered BDSN’s environmental and social management system and gaps, if any, between this system and IFC requirements. Where necessary, corrective measures intended to close these gaps within a reasonable period of time are summarized in the paragraphs that follow and in the agreed Environmental and Social Action Plan (ESAP). Through implementation of management procedures and the attached ESAP, BDSN is expected to operate its facilities in accordance with IFC Performance Standards objectives.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan