Environmental & Social Review Summary

Project Number

33606

Company Name

MUNICIPALITY BOTOSANI

Date ESRS Disclosed

Aug 2, 2013

Country

Romania

Region

Europe

Last Updated Date

Jun 12, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Sep 25, 2013
Signed : Oct 28, 2013
Invested : Nov 19, 2013

Sector

Water and Wastewater Utilities

Industry

Infrastructure

Department

Regional Industry INF LAC & EUR

Project Description

The proposed investment is a loan to Municipality, to help to finance the district heating plant (“DH”) and to update the transport and distribution networks in order to reduce energy losses.

With a population of 106,847 citizens according to the 2011 census, Botosani is among the largest Romanian municipalities in the North East regions of Romania. Botosani has several municipal utilities companies, performing a variety of services including transportation (SC Eltrans Botoşani SA), water and sewerage (SC Urban Serv SA Botosani) as well as theatres, sports clubs and Municipal Philharmonic. The City has full ownership over its heating system through the municipal company Modern Calor (SC Termica Botoşani SA), which provides heat generation, transmission and distribution to its urban area.

The district heating plant has 6 steam boilers, 2 gas turbines, 1 steam turbine and several heat recovery boilers and heat exchangers, commissioned through 1964 to 2003. The transportation network consists of 17.1 km dual pipes and distribution network is 57.4 km. There are 37 Group Heat Substations (GHS).

The project includes two phases;

Phase 1:
Modernization of the existing Combined Heath & Power plant (CHP, installation of two 4MWe gas engines and two 52 MWth heat-only boilers, and auxiliary equipment)
Rehabilitation of the worn-out part of the transmission network (6.53 km) ,
Rehabilitation of the worn-out part of the distribution network (14.3 km)
Rehabilitation of 14 Group Heat Substations (at the time of the visit, installation of gas engines, boilers and auxiliary equipments and almost 80 % of the network and group heat substations were completed. Demolition of the existing boilers is planned to be completed in 2014)

Phase 2 :
Re-connection of public building consumers to the DH system (transportation network re-connections 1.2 km)
Rehabilitation of the remaining 3.7 km of the distribution network and 7 Group Heat Substations
Improving energy efficiency of buildings (3 blocks of flats, a total of 172 apartments)

The project will help to reduce emissions and energy losses, improve energy efficiency and contribute to enhanced public health for surrounding communities. The project site is the Botosani city and surrounding industrial areas.

Overview of IFC's Scope of Review

The scope of review included assessment of Municipality and Modern Calor (MC, municipal company providing heat generation, transmission and distribution services to Botosani) environmental, social, health and safety management capacity and performance, in particular the likely impacts of the equipment modernization and rehabilitation plan. The review relied on documents and reports made available by the Municipality and MC and observation and interviews of IFC staff during a site visit made in July 2013 to the Municipality, MC’s heating plant, group heat substations and several project locations. During this visit, meetings and interviews were held with the key staff (management, human resources, technical, environmental, occupational health and safety, contractors), and numerous relevant documents demonstrating the client’s management capacity to provide adequate oversight of its environmental, social, health and safety performance in conducting its business were reviewed and discussed.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan