Environmental & Social Review Summary

Project Number

33456

Company Name

San Andres SpA

Date ESRS Disclosed

May 17, 2013

Country

Chile

Region

Latin America and the Caribbean

Last Updated Date

Jul 28, 2017

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Jun 26, 2013
Signed : Nov 5, 2013
Invested : Nov 26, 2013

Sector

Solar - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry INF LAC & EUR

Project Description

The Project involves the installation of an approximately 50 MW solar photovoltaic plant on a site of approximately 135 hectares within the Atacama Desert in the Copiapo municipality in Chile’s Atacama Region, at an altitude of 952 meters above sea level. The landscape in the region is typical of deserts and arid areas. However, in the project site there is scarce vegetation of which there are four native species and twelve endemic species. Even though none is identified as vulnerable or critical being unique desert species they will be preserved by the project. The closest national preserved area, “Desierto Florido”, is located 23 km distant from the project site. The nearest population settlement is Copiapó, 24.7 km from the project site.

The project will be developed by SunEdison Chile Construction Limitada (the “Contractor”) which is a wholly own subsidiary of a world class solar integrator and existing IFC client, Sun Edison LLC (“SunEdison”). The ground mounted photovoltaic crystalline modules will be provided by SunEdison parent company, MEMC. The photovoltaic modules to be installed will convert sunlight to DC (Direct Current) electricity. The DC power will be sent to an Inverter to convert the DC power into AC (Alternate Current) power which will then be fed into the Sistema Interconectado Central (SIC). The project is expected to have an annual generation capacity of approximately 130 GWh based on an estimated energy yield (post availability of 99%) of approximately 2,659 kWh/kWp. SunEdison will build the project through an EPC contract with the Company. As part of the project, the Company will install an approximately 135 meters transmission line (220 kV) to transport the generated electricity to the 220 kV Carrera Pinto – Cardones main grid transmission line.

Overview of IFC's Scope of Review

IFC reviewed San Andres SpA (the “Company”)’s Environmental, Health and Safety (EHS), and Social capabilities and its ability to construct and operate the project in accordance with the Chilean regulatory requirements and IFC’s Performance Standards. Specific items reviewed included: (a) Environmental Impact Assessment (EIA) dated January 2013 and (b) Site Specific Safety Plans. IFC conducted a visit to the proposed project site and conducted interviews with the Company’s project management team including EHS staff in March 2013.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan