PROJECT

Projects

Environmental & Social Review Summary

Project Number

33274

Company Name

FLUIDIC, INC.

Date ESRS Disclosed

Aug 15, 2013

Country

World Region

Region

Global

Last Updated Date

Sep 30, 2022

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Sep 17, 2013
Signed : Oct 29, 2013
Invested : Nov 5, 2013

Sector

Electrical Machinery, Equipment and Components (Electric Lighting, Motors, Batteries, Insulated Wires and Cables, Fiber Optic Cable, Carbon and Graphite Products, etc.)

Industry

Manufacturing

Department

TMT, Venture Capital & Funds

Project Description

The project involves a proposed equity investment of $7 to $10 million in Fluidic Energy (“Fluidic” or “the Company”), an early stage project to produce zinc-air batteries to support critical loads and backup power applications worldwide. Fluidic’s solutions offer customers significant operating and capital savings making them a viable alternative to diesel generators and lead-acid batteries.

The proposed IFC investment will support expansion of assembly in Bogor, Indonesia, and business development in emerging markets. Fluidic also has operations in the United States, where the Company performs research and development, and manufactures some parts used in the assembly operations in Indonesia.

Fluidic’s battery assembly facility in Indonesia is a leased building of approximately 3,000 square meters, used for assembly, storage, and simulated site testing of Fluidic’s batteries. Those batteries are assembled with standard supplies purchased locally as well as elsewhere in emerging markets, notably anodes, printed circuit boards, and electronics. Fluidic’s assembly building contains electrolyte mixers, adhesive dispensers with heated drums, and other machinery. Fluidic workers employ standard equipment to mix the electrolyte recipe, while battery enclosures are sealed robotically to guarantee quality.

Overview of IFC's Scope of Review

The review of the proposed IFC investment in the Fluidic project consisted of a visit by IFC staff to Fluidic’s headquarters in the United States, and an appraisal of technical, environmental and social information submitted by Fluidic, including environmental and social assessment documentation, human resources policies and procedures, and separate environmental, health and safety policies and procedures.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan