32522
PORTUCEL MOCAMBIQUE LDA
Sep 29, 2014
Mozambique
Africa
Dec 1, 2016
A - Significant
Active
Approved : Dec 11, 2014
Signed : Dec 15, 2014
Invested : Jul 25, 2016
Plantation Forests
Agribusiness and Forestry
Regional Industry - MAS Africa
| S.no | Description | Anticipated Completion Date | Status |
|---|---|---|---|
| 1 | ESIA: The Company will secure approval by relevant Mozambican authorities of a complete and fully-disclosed Environmental and Social Impact Assessment, including documentation and assessment of the level of informed consultation and participation by communities where Portucel has started or intends to start its proposed plantation activities. | 09/30/2014 | Completed |
| 2 | Influx Management: The Company will complete a supplementary study on potential project-induced in-migration so as to better understand (i) the dynamics around reported influx of new residents into the Portucel Mozambique land-use concessions (DUATs), (ii) what impacts and risks such an influx might pose for the project as such, for local health services and other social infrastructure, and for social relations in the project area, and (iii) key elements of an Influx Management Plan to assist Portucel Mozambique and local authorities to best manage these issues. The management plan should clearly identify the Company and public sector responsibilities and operational policies to guide Portucel in the event government is unable to assume its anticipated respective role. | 01/31/2015 | Completed |
| 3 | ESMS: Portucel Mozambique shall establish an Environmental & Social Management Systemwhich responds to the E&S risks and impacts identified during the ESIA. The program shall be applied across the Company’s forestry operations including contractors and primary suppliers over which the organization has control or influence. The ESMS shall include at least the following items: (i) policy, (ii) identification of the risks and impacts, (iii) management programs, (iv) organizational capacity and competence requirements, (v) emergency preparedness and response mechanisms, (vi) approach to stakeholder engagement, and (vii) monitoring and review of system performance on at least an annual basis. | 09/30/2014 | Completed |
| 4 | Organigram and Recruitment: The Company shall, as a matter of priority, develop clear requirements for the full organizational capacity and competences necessary for organizing and implementing its Environmental & Social Management System (ESMS) and accelerate recruitment of qualified, full-time personnel for these functions at the Company and operational levels. | 09/30/2014 | Completed |
| 5 | Forestry Good Practices Code: The Company shall issue a version of its corporate Forestry Code (Código de boas prácticas florestais) suitable for its Mozambican operations. | 01/31/2015 | Completed |
| 6 | SOPs: The Company shall finalize and ensure full implementation of all Standardized Operating Principles and Procedures related to environmental and social issues, particularly concerning land acquisition and livelihood improvement measures. | 07/31/2015 | Completed |
| 7 | Emergency Preparedness and Response: As part of the ESMS, the Company shall operationalize an emergency preparedness and response system across its forestry operations, particularly concerning standard first-aid kits, training, field orientation materials, and communications protocols for workplace accidents. This effort will include staff training and collaboration with local authorities, government agencies, affected communities, and other, relevant third parties to facilitate response to accidental and emergency situations, including fires and workplace accidents. | 12/31/2014 | Completed |
| 8 | Monitoring and Evaluation: Involving representatives from Affected Communities and other stakeholders as appropriate, the Company shall establish procedures and systems to monitor the effectiveness of its ESMS and management programs, compliant with applicable regulations and consistent with third-party verification systems with which the Company anticipates conforming, when appropriate. This M&E system should be fully integrated the Company’s geographic information system (GIS) and forestry planning and management systems, and among its numerous tasks, the system should be capable of tracking, monitoring, and evaluating the impacts of land acquisition and the effectiveness of livelihood improvement measures in particular. | 06/30/2015 | Completed |
| 9 | Stakeholder Engagement Plan: Based on advice from the IFC, the Company shall develop and implement a Stakeholder Engagement Plan scaled to project risks and impacts identified in the ESIA and baseline surveys and tailored to the characteristics and needs of the Affected Parties and local government authorities. Such a plan will include differentiated measures to allow the effective participation of those identified as disadvantaged or vulnerable. | 10/31/2014 | Completed |
| 10 | First Annual E&S Public Report: The Company will begin reporting publicly to all stakeholders, particularly local authorities and Affected Communities, on an annual basis regarding Portucel Mozambique’s full E&S performance. Among other performance indicators, the Company will report publicly on its land access practices, livelihood improvement measures, and grievance management (including the numbers and types of grievances received, by location, and measures taken to address them). | 04/30/2016 | Completed |
| 11 | Community Development Plan: Based on IFC advice, the Company shall develop an approach to strategic partnerships for community investments aligned with relevant plans organized by local authorities, the Company’s own Forest Management Plan, and the Communicable Diseases Prevention Program (see below), including the resources required to ensure its implementation. | 10/31/2014 | Completed |
| 12 | Community Grievance Mechanism: Based on the first six months of functioning of Portucel Mozambique's grievance mechanism (September 2014-March 2015), the Company will analyze the effectiveness of its procedures and identify and implement any necessary improvements to them. | 04/30/2015 | Completed |
| 13 | Communications Plan: In conjunction with the Stakeholder Engagement Plan, Community Development Plan, and Community Grievance Mechanism, Portucel Mozambique will develop a corporate communication strategy, elaborate a plan at the sub-national, national, and international levels for dialogue, and create operational capacity and internal coordination mechanisms for ensuring appropriate communication with Affected Communities and other interested parties. | 09/30/2014 | Completed |
| 14 | Human Resources Policy (Direct-Hire Employees/Contractors): The Company will adopt and implement human resources policies and procedures appropriate to its direct-hire workforce and those of its contractors, including provision of understandable information appropriate to their employment circumstances regarding workers’ rights under Mozambican labor and employment law including rights related to hours of work, wages, overtime, compensation, freedom to associate and form worker organizations, occupational health and safety, non-discrimination, grievance mechanisms, retrenchment, and benefits upon beginning the working relationship and when any material changes occur. | 09/30/2014 | Completed |
| 15 | Human Resources Policy (Temporary Workers/Casual Laborers): In light of the large-scale mobilization of unskilled labor at the community level during land clearing and planting processes, Portucel Mozambique will provide temporary workers mobilized at the local level with understandable information appropriate to their employment circumstances regarding workers’ rights under Mozambican labor and employment law including rights related to hours of work, wages, overtime, compensation, freedom to associate and form worker organizations, occupational health and safety, non-discrimination, grievance mechanisms, retrenchment, and benefits upon beginning the working relationship and when any material changes occur. Due to the need for consultation with and clarification from the Ministry of Labor on many of these issues (see below), this item's due date may be subject to modification. | 12/31/2015 | Completed |
| 16 | Standardized Orientations for Temporary Workers: The Company will develop and begin providing temporary workers with standard orientations on terms of employment, working conditions, and occupational health and safety on a regular basis and in understandable terms. | 10/31/2014 | Completed |
| 17 | Checklist for Temporary Workers: The Company will develop a checklist of evaluative criteria for its field supervisors to assess the degree to which local traditional authorities responsible for the recruitment and mobilization of temporary workers are meeting Company principles and goals, including non-discrimination, equal opportunity, livelihood restoration and support for vulnerable households, and prohibitions on child labor. | 10/31/2014 | Completed |
| 18 | HR Dissemination Strategy: The Company shall develop a strategy for how all employment-related information is communicated consistently amongst all employees, contractors, temporary workers, and interested parties in accessible, understandable terms. | 06/30/2015 | Completed |
| 19 | Third-Party Labor Audit: The Company will conduct a third-party audit of its labor practices and make appropriate adjustments in its policies and practices, particularly with regard to protections for temporary/casual laborers. | 07/31/2016 | Completed |
| 20 | Standardized Contracts and Working Conditions for Temporary Workers (First Quarterly Report): The Company will consult with the Ministry of Labor and report to the IFC on efforts to develop and begin providing standard written contracts and working conditions for temporary/casual laborers. | 12/31/2014 | Completed |
| 21 | Standardized Contracts and Working Conditions for Temporary Workers (Second Quarterly Report): The Company will consult with the Ministry of Labor and report to the IFC on efforts to develop and begin providing standard written contracts and working conditions for temporary/casual laborers. | 03/31/2015 | Completed |
| 22 | Standardized Contracts and Working Conditions for Temporary Workers (Third Quarterly Report): The Company will consult with the Ministry of Labor and report to the IFC on efforts to develop and begin providing standard written contracts and working conditions for temporary/casual laborers. | 06/30/2015 | Completed |
| 23 | Standardized Contracts and Working Conditions for Temporary Workers (Fourth Quarterly Report): The Company will consult with the Ministry of Labor and report to the IFC on efforts to develop and begin providing standard written contracts and working conditions for temporary/casual laborers. | 09/30/2015 | Completed |
| 24 | Standardized Contracts and Working Conditions for Temporary Workers (Fifth Quarterly Report): The Company will consult with the Ministry of Labor and report to the IFC on efforts to develop and begin providing standard written contracts and working conditions for temporary/casual laborers. | 12/31/2015 | Completed |
| 25 | OHS Self-Assessment and Development of an OHS Management System: Based on a self-assessment of its OHS risks, the Company will develop an occupational health and safety (OHS) management system, begin the use of personal protective equipment (PPE) for temporary workers, and track and investigate all OHS incidents. The plan will identify training needs and specify the resources, including staffing, necessary for an effective OHS management system, and the Company will establish and implement policies and procedures for managing and monitoring the OHS performance of all workers, including contractor employees and temporary/casual laborers. | 11/15/2014 | Completed |
| 26 | PPE Procurement Plan: As part of its overall OHS plan, the Company will source and begin the use of PPE appropriate for risks and work tasks, including for temporary workers. | 11/15/2014 | Completed |
| 27 | Third-Party Audit of OHS Systems and Practices: The Company will commission a third-party audit of its OHS systems and practices with a view to improving them and identifying gaps to be addressed when seeking OHSAS 18001 certification. | 07/31/2015 | Completed |
| 28 | Worker Grievance Mechanism: For its permanent and contractor workforces (grievances arising from casual day laborers recruited from the community be handled via the Company's community relations and external grievance mechanisms), the Company will establish a worker grievance mechanism in compliance with the requirements of PS 2 and that will be accessible and communicated to workers and contractors. The grievance mechanisms should be appropriate to the localities and shield workers from retribution, allow for timely response and feedback, be gender sensitive, and be developed in close consultation with relevant labor authorities. | 06/30/2015 | Completed |
| 29 | Measuring GHG Emissions: The Company will develop a system for measuring the GHG emissions associated with its forestry operations. This system will have clear procedures to guide its assessment and reporting of GHG emissions within the Company's Forest Management Plans and Code of Good Forestry Practices, specify clear responsibility for the accounting process, and communicate effective procedures to appropriate personnel and contractors, including the disposal of residual wood waste. | 12/31/2014 | Completed |
| 30 | Soil Erosion Control: The Company will establish specific guidelines and procedures, communicate them to staff and contractors, and ensure their implementation in order to minimize soil erosion and loss of soil fertility in forestry operations, including measures to reduce erosion during road construction, site preparation, and anticipated harvest activities. Fertility guidelines will outline the Company’s methods for soil mapping, assessing pre-plantation fertility, and ongoing use of amendments. | 11/15/2014 | Completed |
| 31 | Hazardous Materials: The Company wil develop comprehensive operational policies and procedures and guidelines for the appropriate procurement, storage, application and disposal of all hazardous materials, including fuels, lubricants, and agrochemicals. These procedures and the determination of agrochemical permissibility will be approved by Senior Management and shall be compliant with applicable Mozambican regulations, the IFC Performance Standards, and the FSC Principles and Criteria | 11/15/2014 | Completed |
| 32 | Fire Risk Management Plan: In conjunction with the Emergency Preparedness and Response Plan (see above), the Company will develop and implement a fire risk management plan that addresses an assessment of all associated risks and impacts of wild fire and arson and that involves community-based approaches and the use of temporary workers in fire prevention efforts. The plan will identify fire prevention, detection and suppression practices and establish the necessary budgetary and human resources and management responsibilities for implementing procedures which reduce effectively the frequency and severity of fire incidents. | 10/31/2014 | Completed |
| 33 | Transportation Safety Procedures: The Company will establish transportation safety procedures as part of the Company's SOPs, make them routinely available to employees, contractors and Affected Communities, and implement appropriate training (e.g. defensive driving) and control mechanisms (e.g. tracking excessive speed via GPSs) to ensure compliance with its procedures. | 10/31/2014 | Completed |
| 34 | Self-Assessment on Security and Human Rights: The Company will carry out a self-assessment regarding security risks and, if necessary, develop appropriate policies and procedures for managing the project’s use of and relationship with security personnel, whether public or private (including either an in-house or third-party guard force), in light of IFC Performance Standard 4. If any armed guards are envisioned in providing security for Company personnel, assets and/or installations, the risk assessment and resulting procedures should reflect appropriate measures (e.g. human rights vetting of personnel, a written code of conduct, training, investigative procedures in the event of any incident or alleged violation) to ensure effective oversight and accountability for the guard force. | 10/31/2015 | Completed |
| 35 | Land Access Procedure (First Report on Land Action Plan): On the basis of the Company's new land acquisition procedure, Portucel Mozambique will begin updating land acquisition documentation for areas planted prior to September 2014 and new areas to be planted by December 2014. | 12/31/2014 | Completed |
| 36 | Land Access Procedure (Second Report on Land Action Plan): On the basis of the Company's new land acquisition procedure, Portucel Mozambique will complete land acquisition documentation for all areas planted as of December 2014. | 03/31/2015 | Completed |
| 37 | Land Access Procedure (Third Report on Land Action Plan): On the basis of the Company's new land acquisition procedure, Portucel Mozambique will begin land acquisition documentation for areas to be planted in 2015. | 07/31/2015 | Completed |
| 38 | Land Access Procedure (Fourth Report on Land Action Plan): On the basis of the Company's new land acquisition procedure, Portucel Mozambique will complete land acquisition documentation for all areas to be planted by December 2015. | 12/31/2015 | Completed |
| 39 | Strategy for Livelihood Restoration Measures: In lieu of a formal Livelihood Restoration Plan, the Company will design a written strategy for developing and implementing livelihood restoration measures in response to the economic displacement experienced by individuals and communities ceding land to the project. To be developed by the Company on the basis of IFC advice, the strategy should define eligibility criteria for Affected Persons and Affected Communities and describe the component measures that together will seek to restore livelihoods, including short-term employment and the provision of improved agricultural techniques and other forms of technical assistance for land-based livelihoods and special measures to improve the livelihoods of economically vulnerable households. | 10/31/2014 | Completed |
| 40 | M&E Plan for Livelihood Measures: As part of the measures to restore if not improve livelihoods, the Company will develop monitoring and evaluation plan based on collecting and analyzing data for household-level livelihood outcomes among Affected Persons and Affected Communities over a three-year period after economic displacement in a given area, including yearly third-party monitoring reports that will be made public. | 10/31/2014 | Completed |
| 41 | Ecosystem Services: Based on the ecosystem services assessment carried out as part of the ESIA, the Company shall incorporate appropriate measures into its Forest Management Plan to fully mitigate the reduction/degradation of identified ecosystem services, particularly watershed functions, and others that may be exacerbated by climate change. | 02/01/2015 | Completed |
| 42 | Methodology for Identifying High Conservation Value Forests & Action Plan for Protecting Such Areas: The Company will develop a methodology for identifying and mapping HCVFs, including through community participation, and implement an Action Plan to ensure that intact natural forests and other HCV areas are not converted during project implementation. The Company shall include all legally-established protected areas, including hunting reserves and registered community-based lands, in geographic and management information systems. | 11/30/2014 | Completed |
| 43 | Pre-Assessment for Forest Certification: Six months prior to the elaboration of an Action Plan for obtaining third-party certification of forests under its management control, the Company will carry out a pre-assessment to identify gaps and prepare a draft action plan to be reviewed by a competent FSC or PEFC auditor or other certifying body to ensure that it is realistic and achievable. | 07/31/2016 | Completed |
| 44 | Action Plan for Forest Certification: The Company will finalize an Action Plan to identify what reasonable measures and controls Portucel Mozambique will use to assess conformity with third-party certification systems (e.g. FSC or PEFC) and at what time it shall pursue third-party verification of compliance with these standards. | 12/31/2016 | Completed |
| 45 | Water Balance Protocol: Based on a review of expertise available in Mozambique and the region, the Company will establish protocols and tools and select appropriate methods and equipment to identify and monitor impacts of plantations on surface water, both in terms of quality and quantity. | 12/31/2016 | Completed |
| 46 | Cultural Heritage Risk Identification and Protection Program: Based upon results of the ESIA and other information gathered during its operations, the Company will carry out a self-assessment of the procedures necessary for ensuring that Portucel Mozambique has a cultural heritage risk and identification assessment and protection program that complies with applicable Mozambican law on the protection of cultural heritage and the Country’s obligation under the Convention Concerning the Protection of the World Cultural and Natural Heritage, including with regard to chance finds. | 12/31/2014 | Completed |
| 47 | Updating SOPs to Protect Cultural Heritage: Based on its self-assessment on identifying and protecting cultural heritage, including chance finds (see above), the Company will develop and include relevant procedures its Code of Good Forestry Practices and its SOPs and ensure that such procedures are effectively communicated to field staff and transferred to contractors. | 04/30/2015 | Completed |
| 48 | Initial Areas to be Returned: Provide IFC the list of initial areas in Manica province to be returned to previous owners/users, including a registry of the company’s outstanding commitments or promised benefits to such owners/users under the Land Access Procedure so that these commitments can be completed and tracked accurately. Additional Areas to be Returned: Provide IFC a finalized list of additional areas in Manica province to be returned to previous owners/users, including a registry of the company’s outstanding commitments or promised benefits to such owners/users under the Land Access Procedure so that these commitments can be completed and tracked accurately. MITADER Support: Provide IFC evidence of MITADER support for the company’s proposed approach to bringing all Portucel areas currently outside of DUATs within formally authorized DUATs within a reasonable period of time. | 08/15/2016 | Completed |
| 49 | Communications Plan for Land Returns/Regularization Process: Prepare a communications plan for informing and consulting with key stakeholders, including local communities, on measures to return lands in Manica and to regularize areas outside of existing DUATs. | 06/30/2016 | Completed |
| 50 | ESIA/EMP Gaps: Submit to IFC a plan for how the company will address gaps in its ESIAs and EMPs as identified during the Impacto review. Regularization of off-DUAT areas: Provide a quarterly update on regularization of the areas the company has acquired outside of the DUAT’s provided by the GoM in 2009 and 2011. | 07/31/2016 | Completed |