PROJECT

Projects

Environmental & Social Review Summary

Project Number

31759

Company Name

PJSC CCS GROUP

Date ESRS Disclosed

Sep 11, 2012

Country

Russian Federation

Region

Europe

Last Updated Date

Dec 1, 2016

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Nov 28, 2012
Signed : Dec 20, 2012
Invested : Oct 29, 2013

Sector

Integrated Utilities

Industry

Infrastructure

Department

Regional Industry INF LAC & EUR

Project Description

The project involves KKS Group (“KKS”), an independent utility providing space heating and hot water to customers in the Tula and Kemerovo regions of Russia. The project consists of: (i) improving the efficiency of existing KKS assets through capital expenditures; (ii) expanding KKS activities through acquisition and leasing of municipal heating assets; and (iii) developing and operating a combined heat and power plant (“CHP plant”) for an international industrial customer located in the Tula region. Currently, more than 80% of KKS heat sales is produced at the gas-fired assets, while the rest is produced at the coal-fired heat stations in Kiselevsk (Kemerovo oblast), where the use of coal is widely spread due to the geographical proximity of coal mines. The company will not increase its use of coal beyond 25% of total fuel consumption within the lifetime of the Project. IFC investment will provide a total of up to RUB 810 million (approximately US$25 million) in financing, or about 24% of the total project cost.

Overview of IFC's Scope of Review

IFC’s Environmental and Social (E&S) review of this project is based on:
Environmental, Health and Safety (EHS) Audit of KKS Group (“KKS” or the “Company”), commissioned by the request of EBRD, and performed in June 2012 by the consulting company Dekonta (in cooperation with the local consulting company Shaneco);
Review of available Company documentation related to environmental and social impacts and risks;
IFC specialist meetings and interviews with the Company’s corporate offices in Tula and site visits to the Company’s operational facilities in the city of Plavsk, in May 2012.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan