Owned by 186 member countries and consistently rated AAA/Aaa. IFC aims to achieve our mission of promoting development by providing debt and equity to the private sector, through a range of benchmark and bespoke products.
31632
Alto Maipo SpA
Jul 29, 2013
Chile
Latin America and the Caribbean
Jun 12, 2021
A - Significant
Completed
Approved : Oct 24, 2013
Signed : Dec 9, 2013
Invested : Mar 5, 2014
Large Hydro - Renewable Energy Generation
Infrastructure
Regional Industry INF LAC & EUR
Policy
AES Gener maintains an Integrated Environmental, Health, Safety and Quality (EHSQ) Policy, which is aligned with its parent company’s (AES Corp.) corporate guidelines, and which is certified to ISO 14001:2004 and OHSAS 18001:2007. The EHSQ Policy which has been developed and approved by the Sponsor’s presidency is widely disseminated throughout AES Gener’s operations in Chile. It includes statements that give priority to safety of employees, contractors, and communities over all other business priorities and expressions of a commitment with environmental protection and the concept of continuous improvement. The Sponsor has also developed an Ethics and Compliance Policy mandated by the parent company AES Corp., a Policy on Community Liaison and Networks and a Management of Contractors and Subcontractors Policy, some of which are described in more detail in subsequent sections of this summary. These policies will be applied to the Project together with the applicable aspects of the IFC Performance Standards as described below.
Identification of Risks and Impacts
Through the implementation of the risk identification process in its EHSQ Policy, the PHAM commissioned the preparation of an Environmental and Social Impact Assessment (ESIA) based on Chilean regulations. The ESIA was initially completed in May 2008 and subsequently amended with Addenda in November 2008, January 2009, and March 2009. The revised ESIA for the Project was approved by the various authorities consulted with as part of the Chilean environmental licensing process, publicly documented since 2008 in the government website (http://www.e-seia.cl/expediente/expedientesEvaluacion.php?modo=ficha&id_expediente=2933044#-1). The Chilean Government subsequently issued an Environmental Authorization (Resolución de Calificación Ambiental - RCA), Resolución Exenta N°256/09, dated March 30, 2009 (seia.sea.gob.cl/archivos/bc4_RCA.pdf). The ESIA comprehensively identified key environmental and social impacts, and the corresponding mitigation measures, associated with the Project’s construction and operation.
As regards the construction, the impact identification included, among others, alteration of air quality resulting from transportation and construction activities; noise and vibrations; temporary alteration of water quality and flow; impacts on aquatic fauna; waste rock disposal; risk of soil contamination from waste and hazardous substances; soil erosion and compaction; loss of vegetation and forest cover; impacts on terrestrial fauna; project proximity to protected areas and glaciers; greenhouse gas emissions; alteration of the natural landscape; changes in the local labor market; temporary disruption of tourism activities; traffic and road use. Mitigation and management measures corresponding to each of the identified impacts were incorporated into the Project’s design and construction phase environmental and social management plans, as well as in the Contractor’s contracts. The ESIA comprehensively identified key environmental and social impacts likely to be generated during the Project’s operation including, for example: permanent changes in the water flow regime; alteration of sediment transport characteristics of the Maipo River; impacts to surface hydrology; proximity to protected areas; potential impacts to water rights holders in the intervened reach and immediately downstream of the Project discharge; impacts to community water intake structures in the intervened reach; visual impacts and instream recreational river use (e.g. kayaking) impacts. Mitigation and management measures corresponding to each impact have been proposed as part of the RCA and the Company is obligated to incorporate them into the Project’s operation phase environmental and social management plans prior to the initiation or during construction activities, as applicable.
The PHAM completed an Alternatives Analysis report which summarizes five Project alternatives that have been analyzed for the past 22 years. The report describes several important design, location and technology iterations for various Project components that were studied and modified to address environmental, social and cultural heritage aspects. The technical, financial and legal feasibility of those alternatives were also analyzed. Between 2006 and 2008, the PHAM made significant changes to the Project design based on input received during the stakeholder consultation process. Key changes incorporated to the Project design to address stakeholder concerns include:
Furthermore, after the ESIA approval, additional design and technology changes and operational procedures and mitigation measures will be incorporated to address further stakeholder concerns according to the applicable regulations. These measures primarily included:
The PHAM completed a comprehensive Cumulative Impacts Assessment (CIA) report following an internationally accepted methodology, incorporating qualitative and quantitative effects and taking into consideration issues raised by stakeholders as well as the recommendations from the IFC. An initial draft of the CIA report was disclosed on the Lender’s websites in October 2012 and later updated to address comments from the IFC and from stakeholders. The revised version included the participation and review of an international consultant with recognized experience in the development of cumulative impact assessments and their alignment with international standards. The CIA includes a detailed description of the geographic and temporal boundaries of the Project’s direct footprint, ancillary facilities and associated component, and existing or future planned projects within a basin-wide approach. The geographic boundaries are described for each selected Valued Environmental Component (VEC) in six maps. Temporal boundaries consider four periods which coincide with important infrastructure development events in the Maipo River watershed. VECs were identified based on the environmental, social and economic components assessed during the ESIA including topics raised during the ESIA consultation process and issues raised by opposing stakeholders. VECs identified included: river continuity; water flow; security in water availability for irrigation; recreational uses of water; sediments dynamics; socio economic component; local infrastructure, especially routes G-25, G-345 and G-455; biodiversity in water courses; surface water quality; air quality; cultural heritage patrimony; climate change; and protected areas and/or areas or touristic, cultural or patrimony use. The criteria for selection included (1) VEC of regional importance; (2) VEC affected by PHAM and (3) VEC affected by other projects/ activities. Seven cumulative effects are identified: reduced water flow in the system; reduced sediment transport capacity in the system and consequent effects on infrastructure and livelihoods; riverbed erosion; reduced tourist visits; increased risk of traffic accidents and deterioration of existing public roads; increased demand on basic services in the local communities; and disturbance of local communities from in-migrant workers. The CIA confirms the appropriateness of many of the existing and proposed mitigation, management, monitoring and compensation measures already included in the PHAM as part of the ESIA approval process, including specific measures and monitoring commitments including a description of how PHAM will minimize cumulative impacts and contribute, at a regional level, to improve certain conditions (e.g., capacity building for local employment). It further explains the adaptive management approach by which the PHAM will monitor on an ongoing basis potential cumulative impacts and implement additional prevention and mitigation measures as applicable.
The PHAM has evaluated the potential changes to the hydrology of the project area due to regional climate change projections. The evaluation consists of the application of the Stockholm Environment Institute’s Water Evaluation and Planning System (WEAP) hydrological model, together with three Global Circulation Models (GCM’s) downscaled to thirteen points of interest within project area rivers. The hydrologic model was calibrated and validated with observed streamflow data from six different hydrologic stations (San Alfonso, Queltehues, Olivares-Colorado, Colorado-Olivares, Colorado-Maipo and Las Melosas). Meteorological projections for the A2 scenario (most severe scenario with the highest air temperature projections from GCM’s) and for RCP2.6 scenario (most favorable in terms of radiation) were used to evaluate climate change impacts in the Maipo (including Yeso) and Colorado systems and their sub-watersheds for the time period between 2010 and 2070. Based on the model results, the Report states that anual streamflow in period 2041-2070 may decrease between 3.4% to 7.3% for the Maipo system and between 8% to 9% for the Colorado system without the shrinking of glaciers, in the period 2011-2040 annual streamflow may decrease 5.9% to 7.5% in the Maipo system and between 7.5% to 8.5% in the Colorado system without the shrinking of glaciers. The report also states that the Colorado system is more vulnerable to global warming than the Maipo system. However, when shrinking glaciers (approximately 1% per year) are considered, these negative percentages of streamflow are lower than without shrinking glaciers because runoff will be increased, particularly during the winter months. In order to address the potential cumulative aspects of impacts related to climate change, AES Gener is currently participating and sponsoring the study “Vulnerabilidad y Adaptación a la Variabilidad y al Cambio Climático en la cuenca del rio Maipo en Chile Central” (Pontificia Universidad Católica de Chile (PUC) and, International Development Research Center (IDRC)), together with other private companies, irrigation associations of the Maipo River, governmental services (DGA, municipalities) and ONGs. (cambioglobal.uc.cl/index.php/en/proyectos/idrc.html).
The above described assessments and evaluations can also be found on the website of Alto Maipo http://www.altomaipo.com/Temas%20de%20interes/Paginas/default.aspx
Going forward, the PHAM will ensure that potential environmental and social impacts for future expansions are evaluated in accordance with local legal and IFC requirements, including potential use of water resources from Laguna Negra, Laguna Lo Encañado, in accordance with the agreement between Aguas Andinas and AES Gener, and the Volcan River, in accordance with the agreement between AES Gener and RP Global Chile Energías Renovables, and any other future new expansions, if applicable.
Additionally, climate change related risks will be monitored and managed as defined in the Participatory Monitoring and Ecosystem Services Management Programs described in more detail below.
Management Programs
Based on the results of the ESIA and as a condition of the Environmental License (RCA) the project is required to develop and implement a series of environmental and social management plans to address the impacts and risks identified. The plans, which are to be developed in detail by construction contractors according to the PHAM’s legal requirements and defined terms of reference, include:
Additionally, AES Gener has an Integrated Environmental, Health and Safety and Quality (ESHQ) Management System, which covers all its operations (i.e., the Cordillera Complex). The EHSQ Management System specifically for the PHAM Project, to be developed by Alto Maipo SpA (the Company) will be based on the AES Gener system, adapted to the specifics of PHAM. During preliminary construction works in 2012 and 2013, EHS plans and procedures were implemented by CONPAX, the contractor performing the preliminary works that in turn have an ISO 14001 and OHSAS 18000 certified EHS management system that is consistent with the AES Gener’s and IFC requirements.
Going forward, AES Gener will complement the general operational management programs described in the environmental and social impact study (ESIA) and AES Gener’s existing management plans with detailed operational phase environmental, health, safety, and social (EHSS) management plans specific for the Alto Maipo Hydropower Project. Examples of those plans are described in more detail below.
Organizational Capacity and Competency
The PHAM Project is managed as an independent business unit supported by the larger AES Gener organization based in Chile, including personnel from the Cordillera Complex and other Chile operations, as well as from Antofagasta Minerals and the AES Corporation. The Project has a dedicated Construction Management Team supported by external consultants for Environmental Supervision, Owner’s Engineering and Technical Inspection. During 2012 and early 2013 the Company complemented its ESHS organizational structure with the incorporation of a dedicated Environmental Manager and dedicated Community Relations Manager, both reporting directly to the Project Director. The Project also has a dedicated Safety Manager who reports to the Project Director.
The Environmental Manager is supported by three Environmental Engineers, dedicated to implementation of the EHSQ Management System and to oversight of regulatory compliance with RCA conditions. During the preliminary works stage, this team was further supported by an external consultant (Cruz y Davila, C&D) with approximately 20 professionals at construction fronts responsible for day-to-day supervision of the implementation of environmental plans and procedures by contractors and subcontractors during the construction of the preparatory works (access roads and electric infrastructure) conducted since early 2012 in preparation for the main construction activities planned for early 2014. The Community Relations Manager who reports directly to the Project Director, is supported by the a Community Relations Chief, Communications Chief and Community Projects Administrator, in addition to a Community Relations Assistant based in the local office at San Jose de Maipo. The Community Relations team also includes three Contractor Monitors responsible for coordinating and monitoring all contractor activities related to each of the principal construction areas, the Volcan, Colorado and Yeso areas.In addition to the Company’s organizational structure for ESHS supervision and support from contractors, per the RCA permit, the Project has an independent auditor that reports directly to the authorities. This auditor is also part of the authorities’ regular on-site inspections and reviews compliance with RCA commitments and applicable Chilean regulations.
Going forward, AES Gener will define the organizational structure for the management of ESHS issues during the project’s operational phase, complementing the existing structure of the Cordillera Complex. Given the extent and complexity of ESHS monitoring and management requirements of the Project, the organizational structure will include at least one dedicated ESHS Manager supported by the required environmental, OHS, and social staff.
Emergency Preparedness and Response
The Project has developed a series of emergency preparedness and response plans (EPRPs) applicable to the construction and operational phases, addressing natural as well as anthropogenic hazards. EPRPs based on an initial identification of potential risks and impacts in the Project’s ESIA and on existing emergency plans currently developed for AES Gener’s hydropower operations in the Maipo River Valley region (referred to as the Cordillera Complex Operations). The EPRPs, mainly applicable to the construction phase of the project, cover aspects such as: avalanches and lahars; landslides and rockfalls; flooding; earthquakes; explosion hazards; drainage from waste rock disposal sites or tunnels; traffic accidents; hazardous substance spills; damages to places of cultural interest; damage to groundwater; work site fire; and falls from heights. Some of the aforementioned aspects are detailed in the Contingencies and Risk Prevention Manual (an Annex to the ESIA) which includes the following documents: Risk Prevention Plan for Contractor Companies; Contingency Plan for Contractor Companies; Cordillera Complex Emergency Plan and Annexes; Spillage Management Plan for the Cordillera Complex.
Although operational phase contingency plans are still to be developed, the Company has already developed a plan to respond to electricity grid blackouts in order to address one the key stakeholder concerns related to the potential temporary interruption or diminution of water flow downstream of the point of discharge of the project into the Maipo River, which could occur in the event of generalized electricity grid blackouts requiring the PHAM project to suddenly shut down. The Company describes the potential scenarios that may occur due to the event of internal or external shut downs (‘Blackouts’) in PHAM facilities in the following studies: Proyecto Hidroelectrico Alto Maipo: Minuta Operacion en eventos de detencion brusca y ‘Blackout’ and PHAM operation during ‘Blackout’ and/or abrupt stoppage events Operacion del PHAM durante un ‘Blackout’ y/o detencion brusca de las centrales. Among the stakeholder concerns is the potential generation of a surge wave due to the assumed abrupt return of water into the streams and rivers in the event of a facility shut down. However, this situation would require a generalized facility shutdown lasting nearly seven (7) hours. It should be noted that only seven (7) blackout events have occurred during the last 10 years of operation Alfalfal I, all of them lasting approximately two (2) hours.
Going forward, the PHAM will harmonize the existing EPRP plans into a discrete, comprehensive, EPRP document (a PHAM Prevention and Contingency Plan) specifically focusing on emergency situations and categorizing applicable risks by probability, severity, and magnitude, using up to date risk information, particularly on what refers to the mapping of natural hazards. As part of the harmonization of the EPRP documents, the PHAM shall adapt the existing Cordillera Complex Emergency Plans (including the Spillage Prevention Plan) to the specifics of the PHAM project’s construction and operational phases. The Prevention and Contingency Plan should include details necessary for implementation and specify which actions are required to occur sequentially or simultaneously, ensuring consistent treatment of cross-cutting risks. It should also define internal and external communication protocols to define the role of the Company, potentially affected communities, and local authorities (e.g. police, fire-fighting unit), clearly considering the capacity of each party to respond to emergencies related to the Project (either brought on by Project activities or natural risks affecting Project activities).
Given the stakeholder concerns surrounding plant shutdowns, which could temporarily affect the flow regime of stream or rivers, the EPRP should specifically outline communication protocols during this specific type of events or any other type of situations which could be perceived to affect downstream populations. The Company will ensure that the Plant Emergency Response Plan includes contingencies for all aspects related to plant operations, including filling of tunnels prior to start up and the event of a shutdown resulting from a electricity grid blackout including, but not limited to: infringement of water rights during filling of the tunnels; sudden changes in stream flow affecting intake structures for irrigation and potable water systems; and risks to communities health and safety caused by surge waves. The definition of the EPRP and contingencies should be done in close consultation with potentially affected stakeholders and should be proactively communicated to all interested parties.
Monitoring and Review
The Project’s monitoring programs which have been defined as part of the EIA (2008) and the RCA for implementation during the construction and operational phases of the project include the following:
Reports of the results of monitoring activities are being compiled into regulatory and management reports for respective presentation to the regulatory authorities, as required in the RCA, and to the Project’s EHS management team, as required in the construction contracts. Going forward, the full monitoring reports and summaries of key findings will be made available to interested parties at the Project offices in San Jose de Maipo. The results of the quarterly monitoring of social indicators can also be found on the website of Alto Maipo:
http://www.altomaipo.com/Descargas/Paginas/Monitoreo-de-indicadores-.aspx
The PHAM will develop a Participatory Monitoring Program as part of its expanded stakeholder engagement plan. The objective of the participatory monitoring program is to include local residents in ongoing monitoring of the Project’s environmental and social performance, with particular focus on issues of most relevance to local stakeholders. The participatory monitoring program will be initiated by the formation of a monitoring committee consisting of the PHAM Community Relations Director, the PHAM Environmental Manager, and three community representatives: one representative from the Union Communal de Juntas de Vecinos, the local school system, and the municipality of San Jose de Maipo, respectively. The monitoring committee will establish the monitoring indicators and procedures and assign specific roles and responsibility to each member. Once the monitoring committee has established the scope of the monitoring program, the monitoring program will be publicized in local communities and through the internet. The monitoring committee plans to conduct a monitoring inspection at least every four months throughout the project construction phase and one time per year during the operational phase, in order to monitor compliance with key environmental and social indicators in alignment with the RCA. A yearly survey will be conducted to verify that the monitoring panel and other participants are satisfied with the monitoring program in order to identify possibilities for ongoing improvement of the monitoring procedures.
Going forward, as an extension of the currently planned multi-stakeholder process to implement the social monitoring program, the PHAM will prepare and implement detailed participative monitoring programs to monitor, in cooperation with representatives of potentially affected stakeholders and other interested parties, potential impacts related to:
| Task Title/Description | Anticipated Completion Date | Status as per May 2017 | |
| PS1: Assessment and Management of Environmental and Social Risks and Impacts | |||
|
1
|
Assessment of Potential Future Project Developments
Perform complementary assessment of potential environmental and social impacts for future expansions in accordance with local legal and IFC requirements, including potential use of water resources from Laguna Negra, Laguna Lo Encañado, in accordance with the agreement between Aguas Andinas-and AES Gener, and the Volcan River, in accordance with the agreement between AES Gener and RP Global Chile Energías Renovables S.A., and any other future new expansions, if applicable. 1-) Assessment of potential impacts and mitigation measures consistent with local legal and IFC requirements. |
1-) Prior to project expansions, as required by local laws and IFC | 1-) No expansions planned to date, ESAP item not applicable. |
|
2
|
Operational Phase Management
Complement the general operational management programs described in the environmental and social impact study (ESIA) and PHAM’s existing management plans with detailed operational phase environmental, health, safety, and social (EHSS) management plans specific to the Alto Maipo Hydropower Project. 1-) Documented framework 2-) Documented management procedure 3-) Implementation of management procedure |
1-) December 31, 2015
2-) September 30, 2017 3-) December 31, 2018 or start of operations |
1-) Rescheduled to one year prior to start of operations of the first power plant
2-) Rescheduled to one year prior to start of operations of the first power plant 3-) Rescheduled to 30 days after the start of operations of the first power plant |
|
3
|
Organizational Capacity and Competency
Define the organizational structure for the management of ESHS issues during the project’s operational phase, complementing the existing structure of the Cordillera Complex. The organizational structure will include at least one dedicated ESHS Manager supported by the required environmental, OHS, and social staff. 1-) Defined organization structure, including terms of reference for management roles 2-) Evidence of hiring of new positions |
1-) September 30, 2017
2-) December 31, 2018 or start of operations |
1-) Rescheduled to one year prior to start of operations of the first power plant
2-) 60 days prior to start of operations |
|
4
|
Contractors Management
Ensure adequate monitoring of implementation of contractor management plans to verify that contractors and sub-contractors engaged on the construction phase comply with IFC requirements with regard to occupational health and safety, labor conditions, environmental performance and community engagement. The monitoring program will include regular monitoring by independent parties and tracking implementation of corrective actions by contractors. 1-) Documented management system including details of monitoring scope and frequency |
1-) December 31, 2013 | 1-) Completed January 2014 |
|
5
|
Emergency Preparedness and Response
Harmonize the existing EPRP plans into a discrete, comprehensive, EPRP document (a PHAM Prevention and Contingency Plan) specifically focusing on emergency situations and categorizing applicable risks by probability, severity, and magnitude, using up to date risk information, including mapping of natural hazards. As part of the harmonization of the EPRP documents, the Sponsor shall adapt of the existing Cordillera Complex Emergency Plans (including the Spillage Prevention Plan) to the specifics of the PHAM project’s construction and operational phases. Ensure that the Plant Emergency Response Plan includes contingencies for all aspects related to plant operations, including filling of tunnels prior to start up and the event of a shutdown resulting from a electricity grid blackout including, but not limited to: sudden changes in stream flow affecting intake structures for irrigation and potable water systems; and risks to communities health and safety caused by the unlikely event of surge waves. 1-) Documented management procedure for construction phase 2-) Implementation of management procedure for construction phase 3-) Framework EPRP for operational phase 4-) Evidence of documented management procedure for operational phase 5-) Evidence of implementation of management procedure for operational phase |
1-) November 30, 2013
2-) December 31, 2013 3-) December 31, 2015 4-) September 30, 2017 5-) December 31, 2018 or start of operations |
1-) Completed February 2015
2-) Completed February 2015 3-) Rescheduled to June 30, 2018 4-) Rescheduled to June 30, 2018 5-) Rescheduled to 30 days after the start of operations of the first power plant |
| PS2: Labor and Labor Conditions | |||
|
6
|
Human Resource (HR) Policy and Employee Grievance Mechanism
Develop and implement a human resources policy and grievance mechanism consistent with IFC’s requirements and national labor laws. The HR policy will make explicit reference to the Company’s commitments to non-discrimination and equal opportunity; minimum work age requirements; workers’ rights to freedom of association; respect for collective agreements, if these are present; maximum working hours; and working conditions and terms of employment. The HR Policy will be disseminated among all employees. The Grievance Mechanism will be applicable and disseminated to both contractors and employees. 1-) Completed HR Policy grievance mechanism and evidence of disclosure to company employees |
1-) December 31, 2013 | 1-) Completed January 2014 |
| PS3: Resource Efficiency and Pollution Prevention | |||
|
7
|
Stormwater, Tunnel Production Water, and Waste Rock Drainage Management
Develop and implement a comprehensive plan for stormwater management, to include estimation of stormwater to be generated, mitigation and control measures, and regular monitoring to ensure compliance with receiving water quality standards. Develop and implement a plan for managing tunnel production wastewater, including a complete list of chemical substances that will be used, handled and stored in tunnels; expected flow of production water in each tunnel section; capacity of wastewater treatment plants, the operating system and expected pollutants to be treated (i.e., high pH, high sediment load, oil and grease, other pollutants). The assessment should account for potential excess water production from fractured rock (i.e., “bolsones de agua”) and include regular monitoring to ensure compliance with receiving water quality standards. Complement the existing Contingency Plan for Acid Rocks with specific mitigation measures to be implemented in the event of encountering acid rock, including measures to prevent acid drainage from entering the water courses. 1-) Documented procedures 2-) Implementation of documented procedures |
1-) December 31, 2013
2-) March 31, 2014 |
1) Completed May 2015
2) Completed May 2015 |
|
8
|
Noise and Vibration
Complement the existing Noise and Vibration Monitoring Program to include a clear notification protocol to alert communities when blasting will occur and, if necessary, assist in preparing communities at risk to respond to emergencies. The monitoring of noise and vibration will also include households and sensitive receptors located in close proximity to roads where heavy traffic will occur due to the Project. 1-) Documented procedures 2-) Implementation of documented procedures |
1-) November 30, 2013
2-) December 31, 2013 |
1-) Completed May 2014
2-) Completed May 2014 |
| PS6: Biodiversity Conservation and Sustainable Natural Resource Management | |||
|
9
|
Ecological Flow Management Plan
As a complement to the Ecological Flow Management Plan, continue to gather baseline information on fish species, macro invertebrates, and other non-fish species as well as hydrological information with monitoring and sampling campaigns which provide detailed information on the pattern of habitat use of small catfish in the specific Maipo basin area. Complement the Ecological Flow Management Plan with specific mitigation measures for habitat conservation, compensation, and adaptive management measures. In addition to the adaptive management requirements set forth in the Environmental License, mitigation measures for the protection of the Small Catfish shall specifically include adjustment of flows and biodiversity offsets, in case these are deemed necessary, in order to maintain or improve their population in rivers affected by the project. 1-) Documented management plan 2-) Implementation of management plan |
1-) December 31, 2013
2-) December 31, 2018 or start of operations |
1-) Completed May 2014
2-) Rescheduled to June 30, 2019 |
|
10
|
Recreational Water Use Management Program
In consultation with commercial and private recreational boaters and other stakeholders, quantify the level of recreational use in affected rivers, the flow requirements for a quality recreation experience (including preferred river segments, time of year, and minimum and maximum flows for recreational uses in any of the bypass reach segments), and propose complementary mitigation and management measures, if required. 1-) Documented management plan 2-) Implementation of management plan |
1-) December 31, 2015
2-) December 31, 2018 or start of operations |
1-) Rescheduled to January 31, 2018
2-) Rescheduled to June 30, 2019 or start of operations |
|
11
|
Participative Monitoring Program
As an extension of the currently planned multi-stakeholder process to implement the social monitoring program, prepare and implement detailed participative monitoring programs to monitor, in cooperation with recognized representatives of potentially affected stakeholders potential impacts related to: • Changes in water flow regimes along the diverted reach and up to 5km downstream of the point of restitution during start up, normal operation, and potential emergency shutdown during “blackouts”, including access to real time water flow information in locations agreed upon with potentially affected stakeholders; • Changes in streambed sediment transport and any potential effects on the structural integrity of irrigation water intake and potable water intakes, along the diverted reach and up to 5km downstream of the point of restitution; • Potential impacts to groundwater or surface water bodies as a result of tunneling activities. 1-) Documented framework 2-) Evidence of documented plans and procedures as well as implementation for Construction Phase 3-) Documented framework for Operations Phase 4-) Evidence of documented plans and procedures as well as implementation of monitoring program for Operations Phase |
1) December 31, 2013
2-) March 31, 2014 3-) December 31, 2015 4-) December 31, 2018 or start of operations |
1) Completed May 2014
2-) Completed May 2014 3-) Completed May 2014 4-) Rescheduled to 60 days prior to start of operations |
|
12
|
Ecosystem Services Management Program
Develop and implement an ecosystem services management program to address identified cumulative impacts on ecosystem services in the project direct and indirect area of influence (diverted reach and up to 5km downstream of the point of restitution). The program shall include the following main elements: • Plans for outreach and engagement with relevant stakeholders to discuss joint regional approaches for the management of identified impacts on hydrology and sediment transport from the Participatory Monitoring Program, including impacts potentially associated with climate change (including continuation of AES’s participation and sponsorship of the study “Vulnerabilidad y Adaptación a la Variabilidad y al Cambio Climático en la cuenca del rio Maipo en Chile Central”. • Operational change management procedures to address those aspects that the company is able to influence independently on in collaboration with other stakeholders. • Compensation plans with clear commitments to address impacts to key stakeholders including but not limited to: commercial whitewater rafting operators along a section of the diverted reach in the Maipo River; and irrigation canal water intakes (from changes in riverbed sediments or water fluctuations); • Specific commitments to complete the Advanced Sediment Transport Study and to develop and implement specific management, mitigation, and compensation measures to address impacts from the Project in collaboration with affected stakeholders. 1-) Documented framework 2-) Evidence of documented management and compensation plans and their disclosure and consultation with potentially affected stakeholders 3-) Evidence of implementation of management and compensation plans |
1-) December 31, 2013
2-) December 31, 2014 3-) December 31, 2018 or start of operations |
1-) Completed January 2014
2-) Management and compensation plans completed. Disclosure and consultation pending 3-) Rescheduled to 30 days after the start of operations of the first power plant. |


