PROJECT

Projects

Environmental & Social Review Summary

Project Number

31587

Company Name

Grupo Calidra, S.A. de C.V.

Date ESRS Disclosed

Aug 17, 2012

Country

Mexico

Region

Latin America and the Caribbean

Last Updated Date

Jun 12, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Oct 15, 2012
Signed : Nov 30, 2012
Invested : Jan 10, 2013

Sector

Miscellaneous and Industrial Ores (Including Magnesite, Fluorite, Sulfur, Soda Ash, Clays, Gypsum, Lime, Peat, Boron, Diatomite, Feldspar, etc.)

Industry

Manufacturing

Department

Gbl Ind, Manufact, Agribus & Services

Project Description

Grupo Calidra S.A. de C.V. (Calidra or “the Company”); Mexico’s leading producer of lime, construction hydrated lime, quicklime, dolomitic lime, chemical hydrated lime, and calcium carbonate products; operates twenty plants across Mexico and one in Honduras. Nine of its plants comprise quarrying, calcination, hydration and packaging, 11 plants are combined hydration and packaging operations, and Calidra also has one paper bag manufacturing plant. Its products are used in the construction, steel, chemical, mining, agricultural, waste treatment industries, amongst other industries.
The proposed project with IFC includes:
Operations in Mexico. Strategic capital investments in Mexico including:
Purchase of equipment to increase production capacity as follows:
Installation of 400 tons per day (tpd) Maerz kilns at its Sonora and Minorte plants
Installation of hydration operations at Calidra de Occidente Santa Cruz site (25 tph), Cal de Apasco (11 tph) , and Cal Quimica Mexicana (25 tph)
Installation of a dry mortars plant at Calidra de Oriente,
Upgrade of the packing operations at various facilities as follows: (a) automatic packing at Calidra de Occidente Santa Cruz and semi-automatic packing at Zapoltiltic sites, (b) Cal Quimica Mexicana, (C) Cal de Apasco (increase existing capacity by 50%)
Installation of crushing and screening facilities at Minorte Durazno quarry, Cal de Apasco and Calhidra de Sonora plants;
New quarry and quicklime plant in Campeche
Quicklime handling facility at Arcelor Mittal in Lazaro Cardenas to support a long term contract
Joint venture with two existing lime producers located in central Mexico to implement the following projects:
A greenfield project that includes installation of crushing and screening operations, a 250 tpd Maerz kiln, a quicklime handling facility, and solid fuel installations at the Cal Los Arcos plant located in Vizarron, Queretaro
A 150 tpd Maerz kiln at the Cal Muro facility located in Michoacán
Adaptation of two production sites, Calidra de Oriente and Calidra de Occidente, to use biomass as a substitute fuel
Operations in Peru. Construction of two lime facilities in Peru. The Company is establishing a greenfield operation in Peru by associating with the owner of the concessioned quarry, and is planning to open a second facility later in 2013
Operations in Colombia. A 50% joint venture with Cementos Argos in Colombia to set up and operate two quicklime plants in the country
Mexico
The proposed upgrades to Calidra’s existing operations began in 2012 and will be complete by 2014. For the proposed biomass project, Calidra has already acquired a biomass collection center at approximately 120 km from the Calidra de Oriente Plant.

Calidra has established a subsidiary, Plantaciones Comerciales Forestales (PCF), to handle biomass related activities. Initially, PCF will acquire waste from wood processing facilities and will coordinate with plantation owners to acquire the discarded biomass resulting from plantations maintenance and clean-up. Ultimately, PCF will acquire land to establish its own operations. Calidra de Oriente is the first plant in Mexico to begin fuel replacement (18 % biomass) and Calidra de Occidente (36% biomass) will be the second Calidra plant by mid 2014.

To ensure biomass quality and quantity, the Company has set up a biomass collection and preparation center located 120 km from the plant, in Chignahuapan, Puebla, from which it sends the biomass to the Calidra de Oriente plant. For the Calidra de Occidente plant, it is considering to use mainly (90%) Agave bagasse with the remaining 10% from wood processors and forestry clean ups. Currently, the Company is developing a Planting and Harvesting Manual intended to identify the suitable species and establish the needed practices a plantation owner should apply aiming to establish a business model whereby plantation owners become PFC business partners and are in compliance with the IFC requirements. A copy of this Plan will be submitted to IFC as indicated in the Environmental and Social Action Plan (ESAP).

Peru
Calidra anticipates building two greenfield plants in Peru. The land acquisition and environmental permitting process for Calquipa, the first of these two plants, has been completed. The plant will be located in the Callalli district, at approximately 188 km from Arequipa, Peru’s second largest city and at 3800 m altitude. Calidra anticipates it will install the second plant by the end of 2012. The two plants will operate in full compliance with local as well as IFC E&S requirements.

The Peruvian government has granted a 400 ha quarry concession which will be associated to Calquipa. This quarry located 21 km from the plant and at 4880m altitude, will be operated by Calidra.

The plant will install a 400 tpd Maerz kiln to produce between 350-420 tons of quicklime per day. Initially, the plant will use anthracite and pet coke; however it expects to begin using natural gas once the Peruvian government installs a proposed nearby gas pipeline by 2014. The anthracite will be transported by ship from the northern part of the country to the Matarani port where it will be temporarily stored. The anthracite and the pet coke will be transported by railroad respectively from the port and the Matarani Petroperu storage areas to the Chasquipampa station and from there by truck to the plant. The electricity needed will be obtained from the power grid. Water needs will be supplied by the nearby Pulpera River, located 30 m from the project site. In addition to the plant installation, the Company will also build needed internal access roads, a 1.7 km transmission line, and a 2.5 MW electrical substation.

Calidra assessed three different sites prior its final site selection for the Calquipa plot based on environmental, technical, and socio economical aspects as indicated in the Environmental and Social Impact Assessment (ESIA) developed for the project.

Colombia
Calidra anticipates building two greenfield plants in Colombia.  The first plant is expected to be built near the town of Victoria in the department of Caldas (between Bogota and Medellin). It is planned that this facility will have a 400 tpd capacity kiln. A second plant is being evaluated, mainly to attend the export market, and could to be located in the Caribbean coast, near the town of Tolu, in the Sucre department.

Overview of IFC's Scope of Review

The review of this project consisted of appraising environmental, health, safety and social information submitted by the Company, and assessing the Company’s operations. This was done through a field visit conducted by the project team in February 2012. The environmental and social (E&S) appraisal team visited the proposed Company operations in Mexico, the proposed project site for one of the plants in Peru and conducted discussions in Colombia with Calidra’s joint venture partners related to the E&S issues for the proposed project.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
Calidra_Environmental and Social Action Plan.pdf