Environmental & Social Review Summary

Project Number

31046

Company Name

REGULUS ARGENTINA SA

Date ESRS Disclosed

Oct 14, 2011

Country

Argentina

Region

Latin America and the Caribbean

Last Updated Date

Nov 30, 2016

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Aug 19, 2011
Signed : Aug 19, 2011
Invested : Nov 9, 2011

Sector

Copper

Industry

Metals and Mining

Department

Regional Industry INF LAC & EUR

Project Description

The Rio Grande Cu-Au-Ag porphyry early exploration project is located in the high Puna of NW Argentina, 450km west of the city of Salta. The main activities currently being undertaken are trench sampling and core drilling. The property has 77 drill holes (33,000 meters) which was completed as of year-end 2008 by Antares Minerals however no resource estimate has yet been prepared. Previous work has focused on the near surface, oxidized mineralization which contains respectable grades of copper and gold, including large areas of low grade with variable areas of higher grade mineralization. With the economic slowdown in 2008 Antares Minerals focused on developing other assets and has in 2011 reinitiated activities at Rio Grande by initiating a drilling program for a total of 15,000 m utilizing two diamond drills.

The exploration camp (3700 meters) is located in the camp facilities of the abandoned Mina Arita Onyx which has been closed down for several years. The camps hosts up to 70 people during drilling campaigns. The exploration area is located at 4700 meters. The area is arid with precipitation of 100-200 mm per year.

The project has 12 full time staff with the balance being provided by contractors of which Boart-Longyear (drilling) is the largest.

The project is located in an area with existing access roads. Other infrastructure available but less accessible includes a gas pipeline extending from Salta to Chuquicamata copper mine in Chile, with a branch line to the Hombre Muerto lithium mine 75 km east of Rio Grande. A high tension power line also extends from Salta to Chuquicamata, and this line lies about 200 km from the project site.

Overview of IFC's Scope of Review

The review of this exploration project consisted of appraising technical, environmental, health, safety and social information submitted by the company, and assessing the company’s operations through a field visit to the Rio Grande exploration site in April 2011, where meetings were held with field personnel and members of the nearest community, Tolar Grande.

In line with similar previous investments, this Environmental and Social Review Summary (ESRS) covers Regulus’ activities at the early exploration pre-feasibility and pre-development stage

Background:
This project is related to an earlier IFC investment in Antares Peru disclosed in May 2009. Regulus is a new company that was “spun out” of Antares following their take-over by First Quantum in 2010 and as a result, IFC now owns 13.2% of the 36.2 million Regulus shares. Regulus holds only one asset, which is a 50% interest in the Rio Grande Project.

Subsequent to becoming a shareholder of Regulus, IFC conducted an appraisal mission to the new property in order to assess the environmental and social performance of the project and in collaboration with the project sponsor developed an environmental and social action plan (ESAP) to ensure compliance with IFCs Performance Standards.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
ESAP - Environment & Social Action Plan.pdf