PROJECT

Projects

Environmental & Social Review Summary

Project Number

30846

Company Name

S.A. SAN MIGUEL A.G.I.C.I. y F.

Date ESRS Disclosed

Apr 28, 2011

Country

Argentina

Region

Latin America and the Caribbean

Last Updated Date

Jun 3, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : May 31, 2011
Signed : Aug 24, 2011
Invested : Dec 1, 2011

Sector

Fruits and Vegetables

Industry

Agribusiness and Forestry

Department

Gbl Ind, Manufact, Agribus & Services

Project Description

The proposed investment in San Miguel is a corporate loan, which maximizes mobilization under IFC’s umbrella with an A loan up to US$5 million and a B loan up to US$20 million. The funds from IFC will be utilized for a variety of purposes, including the replanting of older orchards with higher producing, more densely planted trees. A long-term IFC client, San Miguel has evolved its operations to comply with IFC’s E&S requirements and applicable WBG’s EHS Guidelines and to increase its sustainability in accordance with good industry’s standards such as GlobalGAP; and, is nearing completion of a complex industrial wastewater management system. San Miguel, with the imprimatur of its internationally recognized food safety certifications in raw materials production and in processing exported diverse products, achieved 2009 revenue of US$207 million. San Miguel core operations are in Argentina, with more than 5,500 ha in plantations and downstream processing/packing facilities.

Overview of IFC's Scope of Review

IFC’s environmental specialist visited San Miguel’s operations located in Tucuman and Famailla, Argentina. Famailla Industrial Plant area evaluations included the nursery and orchard at Monte Grande and the lemon processing plant. The fresh fruit packing operation located in the city of San Miguel de Tucuman was also evaluated. IFC participated in meetings with senior management, line management and staff responsible for operations and production. Of particular relevance to IFC’s appraisal of this investment were the meetings with management and staff responsible for the environmental, occupational health and safety issues and social/community relations. Special attention was paid to the status of corrective actions addressing E&S performance in prior Environmental and Social Action Plans (ESAP) associated with previous IFC investments, namely San Miguel II (#23850) and Milagro (#26890). These included specifically the evaluation of the industrial plant’s wastewater treatment operations, including the management of biosolids, OHS in both plants and orchards, and specific commercial and OHS-related management system certifications held by San Miguel. Company operations in Uruguay (ref. Milagro) were not visited as current reporting on E&S performance and completion of Milagro ESAP action items clearly demonstrates satisfactory overall environmental, social and OHS performance at these facilities. Previous Milagro ESAP action items completed were related to revision of human resources policies, the planning and implementation of a community engagement program, upgrades to the facility integrated pest and disease management program and planning and implementation of a water resources conservation program.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
SanMiguel_ESAP_April 20_2011_Final.pdf