PROJECT

Projects

Environmental & Social Review Summary

Project Number

30518

Company Name

MARKET SHOPPING CENTER LIMITED

Date ESRS Disclosed

Mar 25, 2011

Country

Rwanda

Region

Africa

Last Updated Date

Nov 30, 2016

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : May 19, 2011
Signed : Jun 22, 2011
Invested : Dec 6, 2011

Sector

Construction and Real Estate

Industry

Tourism, Retail and Property

Department

Regional Industry - MAS Africa

Project Description

The proposed investment consists of an up to $10 million A loan to, and an up to $3 million Equity investment in Market Shopping Centre Limited (MSC Limited) for the development of a mixed use commercial property (the “Complex”) in the Central Business District (CBD) of Kigali, the capital city of Rwanda. MSC Limited is owned by Mr. B. Makuza, a local businessman. MSC Limited is a newly created real estate company that will undertake development of the $37 million greenfield mixed-use commercial property Complex, with a gross leasable area of approximately 29,000 m². The Complex will be the first purpose built mixed-use commercial Complex in Kigali which will include a combination of retail, accommodation and office space, along with areas allocated to food outlets and entertainment. The Complex has been designed as an 11 storey commercial building comprising of: parking space on two basement floors; retail space and food court on the lower ground, upper ground, first and second floors; and office space along with several residential units on the third to eleventh floors. The Complex will utilize the entire site, and no portion of the site will remain open for gardens and the like. The project site is located in Nyarugenge Hill, a prime area in central Kigali, on a site that was previously occupied by a state-owned post office and a privately owned fuel service station. The post office and service station were both demolished, and the land was cleared and the construction at the site is underway at the lower ground floor. The total area of the two sites combined is 3780 m². The site is situated adjacent to Centenary House, housing Cogebank, to the north; the partially constructed Social Security Fund Building to the east; the Bank of Kigali to the south; and a few relatively smaller low rise commercial buildings, accommodating a number of small trading businesses, to the west. MCSL commissioned GMK Architects (GMK), a local company specializing in architectural design, engineering and project management, to design the Complex and undertake quality assurance during project implementation. The China Civil Engineering Construction Corporation (CCECC), a Chinese state owned company, has been commissioned to construct the Complex. Construction activities commenced in April 2010, with completion of the superstructure anticipated in 2012, and opening of the complex planned for 2014. While construction has been delayed by approximately six months, the contractor has committed to advance work to ensure completion within the original timeframes. Whist the management structure during the operational phase has not been defined; it is likely that a professional property management company will be commissioned to manage the Complex on behalf of Mr. Makuza.

Overview of IFC's Scope of Review

IFC’s review for this project included meetings with the client, Mr. B. Makuza, the financial consultant for the project, Mr. E. Luyombya, the architect and Project Manager, Mr. V. Kamiya, the environmental consultant Mr. N. Rubangura, and the Kigali City Planning Department Ms. D. Rubinoff, and a site visit of the construction site. In addition the following information was reviewed: Reponses to the environmental and social appraisal questionnaire The Environmental Impact Assessment (EIA) Various authority approvals, including those related to the EIA and planning approval Contractual documentation between MSC Limited and CCECC The green building and energy efficiency plan compiled by the architect

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
MSCL ESAP Final_24 Mar 2011.pdf
ENVIRONMENTAL IMPACT ASSESMENT.pdf