Environmental & Social Review Summary

Project Number

29521

Company Name

CAI LAN INTERNATIONAL CONTAINER TERMINAL LLC

Date ESRS Disclosed

Jul 26, 2010

Country

Viet Nam

Region

East Asia and the Pacific

Last Updated Date

Jan 11, 2025

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Sep 17, 2010
Signed : Oct 26, 2010
Invested : Feb 24, 2011

Sector

Port and Harbor Operations

Industry

Infrastructure

Department

Regional Industry - INF Asia & Pac

Project Description

Cai Lan International Container Terminal LLC (“CICT”) is developing a new container terminal (the “Terminal”) within the Cai Lan Port in Quang Ninh Province in North Vietnam. The Terminal is expected to have a 594 meter berth, a 13 meter draft along-side the berth, four Panamax gantry cranes and supporting yard equipment, and a 25 hectare container yard. It would have 720,000 TEUs of handling capacity at completion. CICT will offer shipping lines significant cost savings by enabling the deployment of larger container ships which cannot call at the Hai Phong Port due to draft restrictions. This will provide much needed capacity to the market, improve Vietnam’s competitiveness and support the expected growth in Vietnamese exports.

The Project involves construction, equipping and operation of berths 2, 3 and 4 in the existing Cai Lan Port. The Project comprises during construction phase: (i) stabilizing the land; (ii) dredging; (iii) constructing the berths and installation of cranes; (iv) developing the container yard and the frontage road; and (v) construction of administration, maintenance, and lunchroom buildings as well as the terminal gates. The operational phase for the Project would primarily involve: (i) maintenance dredging; (ii) transportation activities including: berthing of vessels, barges and the associated operations; and movement of road transport vehicles/trucks; (iii) receipt and dispatch of cargo in the terminal area; (iv) storage of containers; (v) terminal cleaning activities; (vi) maintenance of equipment; and (vii) other activities such as office/administrative functions. All the cranes and RTGs will be electrically operated. Other equipment that will be deployed at the terminal include top picks, side picks, yard tractors and yard chassis.

Overview of IFC's Scope of Review

IFC’s review consisted of appraising technical, environmental and social information submitted by Cai Lan International Container Terminal LLC (“CICT” or the “Company”) including:
Environmental Impact Assessment (“EIA”) Report for Cai Lan Expansion Project, dated June 1998 prepared by Nippon Koei Co. Limited & Associates;
Draft Environmental Impact Assessment Report for CICT dated January 2010 prepared by PortCoast Consultant Corporation (“PortCoast”);
Environmental Review of CICT EIA and Gap Analysis Report, dated March 31, 2010 prepared by Environmental Resource Management (“ERM’);
Environmental and Social Action Plan prepared by CICT dated March/June 2010;
Updated baseline data on quality of material to be dredged;
Letter from Quang Ninh People’s Committee, Department of Transport;
Letter from Vietnam Maritime Administration; and
Publicly available UNESCO World Heritage Committee reports pertaining to Ha Long Bay

The review also included a discussion with the Directors of the Company, and technical management professionals representing the Project sponsors and CICT. Further, the review included visits to the Project Site and the existing Cai Lan Port.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
CICT PROJECT SITE LOCATION.pdf