PROJECT

Projects

Environmental & Social Review Summary

Project Number

29251

Company Name

ZORLU ENERJI PAKISTAN LIMITED

Date ESRS Disclosed

Apr 11, 2011

Country

Pakistan

Region

Middle East

Last Updated Date

May 23, 2025

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : May 20, 2011
Signed : Sep 22, 2011
Invested : Jun 4, 2012

Sector

Wind Power - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry INF MCT

Project Description

The project consists of the construction, operation and maintenance of a 56.4 MW wind farm and associated transmission facilities in the Jhimpir area of Thatta District, Sindh Province, in south-eastern Pakistan, about 100 km east of Karachi (“Project”). The Project site is within the Gharo air corridor and has an average wind speed of 7.8 m/s. The Project will be an Independent Power Producer and will sell electricity to the National Transmission and Dispatch Company Limited (“NTDC”) under a 20-year Energy Purchase Agreement. The Project is the first internationally financed wind power project in Pakistan. The Project is being developed in two phases, with the 6 MW phase I already installed and phase II comprising the remaining 50.4 MW. The inauguration of Phase I was made in April 2009 attended by the Prime Minister of Pakistan. The five 1.2MW each wind turbine generators (“WTGs”) for phase I was procured from Vensys Energy and the twenty eight 1.8 MW each WTGs for Phase II are being procured from Vestas. The 1.2 MW WTG will be placed at 69m height tower with its peak height of 100m. The 1.8 MW WTG will be placed at 80m height with its peak height of 125 m. All the 33 WTGs will be connected to a substation with an underground power cable. The substation is planned to be connected to the national grid system of NTDC. The Project has been developed by Zorlu Enerji Pakistan Limited (“Zorlu Pakistan” or the “Company”), a special purpose company incorporated in Islamabad. Zorlu Pakistan is an almost wholly-owned subsidiary of Zorlu Enerji Elektrik Uretim A.S “Zorlu Enerji” or the “Sponsor”). A subsidiary of Zorlu O&M Enerji Tesisleri Isletme A.S. (“Zorlu O&M”, wholly-owned by Zorlu Holding) will be responsible for the Project’s operation and maintenance. The Project is located in the operational jurisdiction of Hyderabad Electric Supply Company (“HESCO”), and the Project will be connected to the Zorlu Pakistan’s substation (20/132 kV) to be developed within the Project area by underground cable, and then, connected to the existing 132 kV transmission line network of HESCO. An associated 2 km 132 kV transmission line from the Project area to the HESCO network will be developed by NTDC.

Overview of IFC's Scope of Review

Documents reviewed:
- Regional Environmental Assessment Study (“REA”) of the Gharo Wind Corridor in Pakistan, prepared with assistance by the United Nations Development Programme (UNDP) of Pakistan, June 2009
This REA consists of (i) Section I (Environmental & Socio-Economic Baseline Report, (ii) Section II (Cumulative Impact Assessment & Alternatives), and (iii) Section III (Environmental Management Plan). These are available at:
http://www.wep.org.pk/05_reference_material/wep_publications.php
http://un.org.pk/undpnew/images/publications/Sec02.pdf
http://un.org.pk/undpnew/images/publications/Sec03.pdf
- Wind Power Project – Sindh, Environmental Impact Assessment, Final updated Report, April 2010, Prepared for Zorlu Enerji

- Decision on Environmental Impact Assessment (EIA) for Zorlu Enerji Pakistan Limited 50MW Wind Power Project, Issued by Environmental Protection Agency of Government of Sindh, March 19, 2009

Site Visits: Visits to the project site, neighboring villages, transmission line route, phase I (6MW) operation, Keenjhar Lake, conducted by IFC staff in February 2010.

Meetings and Discussions in February 2010.
- Officers in charge of environmental, health and safety and social matters of Zorlu Pakistan
- Environmental consulting firm (Elan Partners (Pvt) Ltd) that prepared the Project’s EIA
- Sindh Environmental Protection Agency
- An environmental organization (WWF-Pakistan)

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
Gharo Wind Corridor REA (Section 3).pdf
Zorlu Pakistan EIA April 2010.pdf
Zorlu Pakistan ESAP March 30 2011.pdf