PROJECT

Projects

Environmental & Social Review Summary

Project Number

28079

Company Name

PAN AMERICAN ENERGY, S.L.

Date ESRS Disclosed

Jun 16, 2009

Country

Argentina

Region

Latin America and the Caribbean

Last Updated Date

Jun 3, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Aug 28, 2009
Signed : Sep 1, 2009
Invested : Sep 11, 2009

Sector

Oil and Gas Production (Includes Development)

Industry

Metals and Mining

Department

Gbl Infrastructure & Natural Resources

Project Description

PAE is the second largest oil and gas producer in Argentina and has blocks located in the four major hydrocarbon basins: Golfo San Jorge, Austral, Neuquina and Northwest. The most significant block in terms of both reserves and production is the Cerro Dragon block in the Golfo San Jorge basin, located in the south of Argentina which is the main subject of this investment.

Loan proceeds will fund the further development of PAE’s assets, Cerro Dragon, Piedra Clavada and Koluel Kaike in the Golfo San Jorge Basin (UG-GSJ) or “the Project”. The Project will partially fund part of the 2009 investment program which includes: drilling of 172 new production wells and 52 injection wells; b) three new projects for secondary recovery and expansion of existing projects; c) expansion of the on-site power generation capacity up to 40 MW; d) expansion of the two crude treatment plants and their pumping systems; e) approximately 80 programmed well interventions.

Overview of IFC's Scope of Review

The review of this project consisted of a document review, including the project’s technical, environmental and social reports and records; an on-site field visit to assess the operation of the Environmental Health and Safety (EHS) and Social Management System at the facilities in Chubut province in Argentina; and interviews with key personnel of the Company.

The following management elements were assessed:

- Adequacy of the existing Environmental, Health, Safety and Social Management System to satisfy IFC’s Performance Standards requirements;
- Assessment of potential EHS & Social impacts related to PAE’s projects;
- Labor issues and Human Resources policy;
- Health and Safety performance;
- Contractors’ EHS performance;
- Venting and Flaring and GHG emissions;
- Produced water disposal;
- Liquid and solid waste management;
- Drilling procedures including solid waste disposal;
- Emergency Response Plans;
- Community engagement;
- Potential land use and compensation issues;
- Cultural and Archaeological chance-find procedure.

As this project was the subject of a previous investment by IFC the company had already adapted its existing environmental and social management system to satisfy the requirements of IFC’s Performance Standards. This due diligence verified that the project continues to be in compliance with these requirements.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement