PROJECT

Projects

Environmental & Social Review Summary

Project Number

27975

Company Name

Electron Investment SA

Date ESRS Disclosed

Nov 24, 2009

Country

Panama

Region

Latin America and the Caribbean

Last Updated Date

Nov 30, 2016

Environmental Category

A - Significant

Status

Completed

Previous Events

Approved : Feb 4, 2010
Signed : Jun 16, 2010
Invested : Mar 22, 2011

Sector

Large Hydro - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry INF LAC & EUR

Project Description

The Pando Monte Lirio project (“the Project”) is a hydropower development that plans to use the water of the Chiriqui Viejo River (CVR) in the Chiriqui Province in Western Panama. The project considers the construction of two run-of-river power schemes with an aggregate capacity of approximately 84 MW split in 32 MW at Pando powerhouse and 52 MW at Monte Lirio powerhouse.
Pando is in the upper part of the CVR catchment area (@ 184 km2). The main dam of the project would be located about 4 km downstream and west from the city of Volcan. The development includes the construction of a 28 m high dam, 150 m long at the crest and 90 meters long at its foundation, that will create a daily regulation reservoir with a total capacity of 900,000 m3, a useful volume of 440,000 m3 with an average storage of 8 hours and covering an area of 180,000 m2 , a tunnel of 3.0 m in diameter and 5.1 km length, a 2.1 km long penstock and diameters of 2.4 to 1.9 meters; a 60 m high oscillation tank and a powerhouse with 32 MW of installed capacity split in two units. The dam will have water-regulating equipment including ecological flow release valve and an overflow fixed-crest spillway structure. While the Pando dam will have storage for sediment transport from the upper basin for an estimated period of not more than 5 years, it will also have a sluiceway structure for removing sediment that may collect in the vicinity of the power intake. Gross head of the scheme is estimated at 280 m.

Monte Lirio would be immediately downstream of Pando with a catchment area of approximately 275 km2. This development includes a 15 m high by 46 m long dam, total capacity of 90,000 m3, and a total surface area of approximately 1,500 m2, a tunnel with a 3.2 m diameter and 8.2 km length; a 65.5 m high oscillation tank, penstock of 2.69 km long and diameters of 2.8 to 2.2 m, and a powerhouse with 52 MW of installed capacity split in two units. Gross head of the scheme is estimated at 314 m.

Additionally, the Project also involves the construction of a 19 km of 230 Kv TL from the plant to an interconnection substation with the Central American Interconnection System (“SIEPAC”).

The project is being developed by Electron Investment, S.A. (the “Company” or EISA), a SPV formed by Spanish and Panamanian investors.

Overview of IFC's Scope of Review

IFC’s appraisal of this project consisted on an extensive desk review of EHS information, including the revision of two Environmental Impact Assessments for Pando and Monte Lirio, respectively, as well as two reports with complementary information. Additionally, during the appraisal visit, a fairly advanced EIA for the transmission line (TL) was also reviewed. The Lenders hired Hatch as the Independent Engineer and Environmental, Social and Health and Safety Consultant to provide support during the appraisal.

Furthermore, the Project Team together with Hatch’s consultants and the teams of other Lenders, performed a visit to the project site, held meetings with EISA, and with representatives from the local Environmental Authority (ANAM). Since construction has not started yet, during the site visit, the Lender’s team inspected the project sites, including the future location of the reservoirs, regulating tanks, penstocks, the power houses, the tunnels openings, and the construction camps.


Additionally, in late September IFC environmental and social specialists visited the project site for a second time. The purpose of this second visit was mostly to document Broad Community Support and Free Prior Informed Consultation (BCS/FPIC) and assess progress on the development and implementation of the Community Relations and Engagement Plan and appropriate socialization of the project.


After the site visits, the Lenders EHS team has been in constant communication with the Sponsor’s EHS team to be able to clarify information, and assure the Sponsor generates adequate data and develops the appropriate EHS plans and procedures to assure timely compliance with the IFC EHS PS, and other Lender’s EHS policies and procedures. Leading to Board Approval, financial closing, and first disbursement, the IFC will continue with its ongoing monitoring and review of the deliverables required under the Environmental and Social Action Plans (ESAPs) agreed with EISA, including but not limited to the EHS management framework, continued disclosure and consultation process, TL EIA approval, finalization of the land acquisition, and transmission line right-of-way easement process, among others.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
10.1. PLANES AMBIENTALES5 PLAN DE EMERGENCIAS sept 09 copy.pdf
10.2. PLANES AMBIENTALES6 PLAN DE PREVENCION DE RIESGOS.pdf
10.3. PLANES AMBIENTALES4 Plan Almc Manejo SustPeligrosas LIRIO.pdf
10.4. PLANES AMBIENTALES9 Plan Interno de Ahorro.pdf
10.5. PLANES AMBIENTALES10 Prg Reciclaje y Reuso PANDO.pdf
11.1. INGEMARLinea Base1 Tabla Contenido.pdf
11.2. INGEMARLinea Base2 Resumen1 Part ONE.pdf
11.3. INGEMARLinea Base2 Resumen1 Part TWO.pdf
11.4. INGEMARLinea Base2 Resumen1 Part TREE.pdf
11.5. PLANES AMBIENTALES7 Plan de rescate de Fauna MONTE LIRIO.pdf
11.6. PLANES AMBIENTALES8 Plan de rescate de Fauna.pdf
12.1. ARQUEOLOGIA1 Informe Prospeccion Intensiva Hidro Monte Lirio copy.pdf
12.2. ARQUEOLOGIA2 Informe Arqueologico Pando.pdf
12.3. ARQUEOLOGIA3 Resolucion DNPH Hidro.pdf
1.1. IFC ESAP.pdf
1.2. Social Action Plan for Disclosure.pdf
2. Project Pictures.pdf
3.1. Executive Summary Monte Lirio.pdf
3.2. Informacion Adicional.pdf
3.3. Informacion Complementaria.pdf
3.4. RESOLUCION DINEORA IA 2004.pdf
4.1. Executive Summary Pando.pdf
4.2. Informacion Adicional.pdf
4.3. Informacion Complementaria.pdf
4.4. RESOLUCION DINEORA 2004.pdf
5.1. ESMP PMA FINAL Part ONE.pdf
5.2. ESMP PMA FINAL Part TWO.pdf
6. Executive Summary Transmission.pdf
8. Information and Community Relations Plan.pdf
9.1. SALUD SEGURIDAD1 PORTADA MANUAL DE SALUD Y SEGURIDAD OCUPACIONAL.pdf
9.2. SALUD SEGURIDAD2 MANUAL DE HIGIENE Y SEGURIDAD.pdf
7. Executive_Summary_of_CIA_2.pdf