Environmental & Social Review Summary

Project Number

27807

Company Name

SunPower Philippines Manufacturing Ltd

Date ESRS Disclosed

Mar 13, 2009

Country

Philippines

Region

East Asia and the Pacific

Last Updated Date

Jun 3, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Feb 1, 2010
Signed : May 6, 2010
Invested : Nov 12, 2010

Sector

Electrical Machinery, Equipment and Components (Electric Lighting, Motors, Batteries, Insulated Wires and Cables, Fiber Optic Cable, Carbon and Graphite Products, etc.)

Industry

Manufacturing

Department

Regional Industry - MAS Asia & Pac

Project Description

SunPower is a global player in the solar industry. The company was founded in 1985 by Dr. Richard Swanson and his students while he was professor of electrical engineering at Stanford University. In 2008, SunPower generated revenue of $1.43 billion.

SunPower is in the process of completing its second solar cell fabrication facility in the Philippines (the “Project”). The project will result in the completion of twelve solar cell manufacturing lines with an aggregate nameplate capacity of 466 MW.

Overview of IFC's Scope of Review

The scope of review of SunPower Corporation''s (“SunPower” or the “Company”) compliance with IFC’s Performance Standards and local environmental, social and occupational health and safety standards, included assessment of the effectiveness of the Company’s environmental and social management system for its proposed capital expenditure projects and its ability to ensure and monitor compliance with regulatory requirements and IFC’s Performance Standards in its operations. The review relied on documents and reports made available by SunPower and interviews conducted by IFC staff during their site visits to their manufacturing facilities located in Laguna (Fab 1) and Batangas (Fab 2) in the Philippines. During the visit IFC staff conducted interviews with key management personnel including plant managers, EH&S staff and Human Resources, as well as various engineering and support staff.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
ESAP_SunPower_V2.pdf