PROJECT

Projects

Environmental & Social Review Summary

Project Number

27783

Company Name

Pandurata Alimentos Ltda.

Date ESRS Disclosed

May 14, 2009

Country

Brazil

Region

Latin America and the Caribbean

Last Updated Date

Jun 3, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Jun 19, 2009
Signed : Jun 22, 2009
Invested : Aug 19, 2009

Sector

Other Food

Industry

Agribusiness and Forestry

Department

Gbl Ind, Manufact, Agribus & Services

Project Description

Bauducco is one of the leading food producers in Brazil. It produces and distributes basic food, staples, cookies and biscuits, part of which directed to the bottom of the social pyramid. The Bauducco owns 5 state-of-the-art, high capacity, and modern production facilities, for all product lines which allow them to be among the most competitive companies in the market.

The Northeast region is one of the main biscuits markets in Brazil, where Bauducco has to compete with local players like M. Dias Branco and J. Macedo, which have plants in the region and have lower logistics costs. In order to be a competitive player in the market, Bauducco has decided to implement a plant in the region.

The Project entails a $50 million investment to implement an industrial plant and a distribution center in Rio Largo, state of Alagoas. In December 2010, Bauducco expects to initiate the operations of the distribution center and the wafer product line (productive capacity of 9,000 mt), which is Bauducco’s most demanded product in Northeast.

The Bauducco’s expansion project in Northeast of Brazil is in advanced negotiations with Alagoas State (AL) and the City of Rio Largo, to be built in the border of the Rio Largo urban area in an Industrial site. Rio largo is part of Maceio, AL metropolitan area that already has other industries like a sugar cane mill and a textile company. The new plant design is intended to be very similar to the existing Extrema factory with some improvements. It will be a state-of-the-art plant in terms of technology and Environmental Healthe and Safety (EHS)control. The plant will be built in stages and the first one will be a waffles production line with a distribution center.

Overview of IFC's Scope of Review

IFC’s review of this Category B project consisted of appraising Pandurata Alimentos Ltda.’s (Bauducco) own assessment of its environmental, occupational health and safety, labor and social development information as per:

- During IFC’s appraisal the following actions took place:

- Presentation by the company of the proposed investment;
- Presentation by the company on the Human Resources policy and actions and on Occupational Health and Safety issues;
- Presentation by the company of the Social assistance/responsibility area;
- Site visits to Guarullhos Plants (Argentina St and Endres St), Bom sucesso Plant, Extrema plant and Fernão Dias Distribution Centers to evaluate both social and environmental issues.
- The company submitted statistics on occupational health and safety issues, as well as on more general labor and social responsibility issues
- Meeting with the company’s quality assurance team.
- Presentation by the company of the Rio Largo, AL new factory and Distribution center project design and selected area in negotiation for construction of the plant.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement