PROJECT

Projects

Environmental & Social Review Summary

Project Number

27626

Company Name

ZAO MONOCRYSTAL

Date ESRS Disclosed

May 27, 2009

Country

Russian Federation

Region

Europe

Last Updated Date

Apr 5, 2017

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Dec 22, 2009
Signed : Dec 23, 2009
Invested : Feb 4, 2010

Sector

Electrical Machinery, Equipment and Components (Electric Lighting, Motors, Batteries, Insulated Wires and Cables, Fiber Optic Cable, Carbon and Graphite Products, etc.)

Industry

Manufacturing

Department

Gbl Ind, Manufact, Agribus & Services

Project Description

Established in 1996 and headquartered in Stavropol, Russia, Monocrystal is one of the world’s largest producers of synthetic single crystal sapphire, aluminum and silver composite pastes for solar power generation, as well as other electronic materials for such industries as production of semiconductors, optics and photovoltaics. After its purchase of PKF Atlas (“Atlas”) in 2008, Monocrystal ranked among the four largest synthetic sapphire producers by revenues globally. Monocrystal has approached IFC to finance a portion of its medium-term modernization program and working capital needs. The proposed project cost is $20 million.

Overview of IFC's Scope of Review

The environmental and social review of the project included a site visit by an environmental consultant on behalf of IFC in October 2008 to Energomera’s HQ in Stavropol and field visit to Monocrystal – producer of synthetic single crystal sapphire, and aluminum and silver composite pastes for solar power generation. The consultant has reviewed environmental and social (E&S) management policies and procedures; occupational health and safety (OHS) accident records; monitoring programs and data on air emissions, effluent discharges and waste disposal; plans to improve energy efficiency. Since Belgorod-based PKF Atlas (“Atlas”), a 100% owned subsidiary of Monocrystal, was not visited, the Company and IFC agreed on specific actions in the Environmental and Social Action Plan to ensure that the project will comply with IFC’s Policy and Performance Standards (PS) on Social and Environmental Sustainability.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
ESAP Energomera.docx.pdf
ESAPupdated16December09.pdf