PROJECT

Projects

Environmental & Social Review Summary

Project Number

27191

Company Name

ROTOR ELEKTRIK URETIMI AS

Date ESRS Disclosed

Jul 28, 2008

Country

Turkiye

Region

Central Asia and Turkiye

Last Updated Date

Oct 14, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Apr 3, 2009
Signed : May 8, 2009
Invested : Aug 27, 2009

Sector

Wind Power - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry INF MCT

Project Description

The proposed IFC loan will be extended to Rotor Elektrik, a subsidiary of Zorlu Enerji, one of Turkey’s largest private power companies. The proceeds of the loan will be used to finance the construction of a 135 MW, approximately EUR180 million wind farm in the province Osmaniye in Southern Turkey.

The project will significantly increase Turkey’s wind generation capacity and will be the country’s largest wind farm built to-date. It will contribute to addressing the Turkish power deficit and increase the country’s power generation from clean renewable sources while supporting the rapidly growing national economy.

Once operational, the project will:

- increase Turkey’s electricity output from wind energy;
- in doing so, displace carbon emissions, reducing pollution and contribute to the effort to reduce global warming;
- by size and nature of the transaction, influence Turkey’s ability to attract foreign investment in the renewable energy sector and position Turkey as an alternative emerging market destination for wind power investments;
- contribute to the development of merchant power operations and private sector investment in Turkey’s energy sector.

Overview of IFC's Scope of Review

Documents Reviewed

Project Introductory File (PIF)/Preliminary Environmental Impact Assessment, dated March 2008, prepared by Rotor Elektrik.
Transmission Line Environmental Impact Certficate, dated January 25, 2008 issued by the Osmaniye Environment and Forestry Directorates.
Environmental and Social Impact Assessment (ESIA), dated January 2009 prepared by Dokay Engineering and Consultancy Ltd.
Environmental and Social Management and Monitoring Plan (ESMMP) dated JANUARY 2009 prepared by Dokay Engineering and Consultancy Ltd.
Independent Ornithological Report, dated January 2009 prepared by Kerem Boyla.

Site Visits: Visits to the project site, neighboring Villages, transmission line route, existing substation, conducted by IFC staff June 2008.


Meetings and Discussions: Rotor Elektrik project team, Dokay Engineering ESIA Manager, Osmaniye Regional Environmental Directorate, Osamaniye Regional Forestry Directorate, Village Heads of Bahce and Hasan Beyli, officials of the Turkish Electricity Transmission Company, Turkish Electricity Generation Company Inc. (EUAS).

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement