PROJECT

Projects

Environmental & Social Review Summary

Project Number

26826

Company Name

CHINA GLASS HOLDING CO LTD

Date ESRS Disclosed

Apr 11, 2008

Country

China

Region

East Asia and the Pacific

Last Updated Date

Jun 3, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Jun 2, 2008
Signed : Jun 4, 2008
Invested : Jul 31, 2008

Sector

Glass and Glass Products (Including Glass and Mineral Wool)

Industry

Manufacturing

Department

Regional Industry - MAS Asia & Pac

Project Description

The project comprises implementation of a series of projects intended to reduce use of energy and water and reduce emissions to air of sulphur oxides and particulate matter at three sites of China Glass Holdings. These projects are:
- construction of a 3MWe waste heat recovery-driven electricity generation system at the Suhuada factory at Suqian;
- cold repairs of two furnaces at the Suqian, and Qinchang (Beijing) sites; these cold repairs will enhance energy efficiency, facilitate addition of coating technology to produce energy efficient low-E glass and will include secondary control of sulphur dioxide (SO2) and particulate emissions;
- closure of one city center float-glass production line in Weihai, and construction of a replacement line on an existing site situated on an industrial estate outside the city;
- addition of treatment systems to permit reuse of sanitary waste water in process cooling systems at all three sites.

Overview of IFC's Scope of Review

This would be IFC’s second project with China Glass Holdings (CGH or the company), following on from a project committed and disbursed in 2007. IFC’s review of the 2008 project included a review of CGH’s progress against the Environmental and Social Action Plan agreed in 2007, visits to the three sites at which the 2008 project will be implemented to discuss the projects with CGH’s central technical team and site-based local management. The Environmental Impact Assessment prepared to examine the impact of construction of the new line at Weihai was also reviewed.

IFC’s review of the 2007 project included environmental review visits to all of China Glass Holdings’ six manufacturing sites.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
ESAP CGH II Final.pdf