PROJECT

Projects

Environmental & Social Review Summary

Project Number

26798

Company Name

JORDAN INDIA FERTILIZER COMPANY LLC

Date ESRS Disclosed

May 14, 2010

Country

Jordan

Region

Middle East

Last Updated Date

Mar 18, 2022

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Jul 8, 2010
Signed : May 6, 2011
Invested : Nov 23, 2011

Sector

Phosphatic Fertilizer

Industry

Manufacturing

Department

Regional Industry MAS MCT

Project Description

Indian Farmers Fertilizer Cooperative Limited (“IFFCO”) and Jordan Phosphate Mines Company (“JPMC”) have formed a joint venture, Jordan India Fertilizer Company (“JIFCO”) for the construction and operation of a 0.9 million tons per annum (“tpa”) merchant grade phosphoric acid plant in Eshidya, Jordan (the “Project”). The bulk of the phosphoric acid will be exported to India to be used as feedstock for IFFCO’s fertilizer plants. The Project will include a greenfield phosphoric acid manufacturing complex in Eshidiya and a phosphoric acid storage facility in Aqaba. Rock phosphate from JPMC’s Eshidiya mines will be used by the Project for the production of phosphoric acid. JPMC has sufficient supply and, hence, there is no need for JPMC to increase its production for this Project. The chemical complex and associated infrastructure and utilities will be located adjacent to the existing JPMC mining facility in Eshidiya, approximately 300 km south of Amman, and 200 km north east of Aqaba Port, from which phosphoric acid will be exported. Aqaba is connected to the Project site by road, as well as by railway which lies 30 km from the site.

Overview of IFC's Scope of Review

The review of this project consisted of appraising technical, environmental, health, safety and social information submitted by the project sponsor, and a field visit undertaken in February 2008. The environmental and social (E&S) appraisal team visited the proposed manufacturing site in Eshidiya, surrounding communities, proposed transportation route, storage facilities and Jetty in Aqaba. The E&S team held meetings with JIFCO management team and the consultants responsible for environmental and social impact assessment. JIFCO presented this project to IFC in 2008. However, the project design and environmental/social settings do not change in the past two years.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
ESAP - JIFCO (final).pdf
ESIA Report_JIFCO_Volume I.pdf
ESIA Report_JIFCO_Volume II.pdf