PROJECT

Projects

Environmental & Social Review Summary

Project Number

26619

Company Name

AZITO ENERGIE SA

Date ESRS Disclosed

Mar 30, 2012

Country

Cote D'Ivoire

Region

Africa

Last Updated Date

Dec 1, 2016

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : May 17, 2012
Signed : Oct 18, 2012
Invested : Mar 7, 2013

Sector

Gas - Thermal Power Generation

Industry

Infrastructure

Department

Gbl Infrastructure & Natural Resources

Project Description

The Project is an expansion (“Azito Phase III”) of the Azito Power Plant by converting the plant to combined cycle operation. This conversion essentially involves addition of two heat recovery steam generators (HRSG) and a 139 MW steam turbine, to the existing 2 x 144 MW simple cycle natural gas-fired turbines. The Project is expected to generate about 50 percent more power without using additional gas (gas turbines’ exhaust heat generates steam in a boiler to power a steam turbine) and with zero incremental emissions. This switch from simple-cycle power generation to combined cycle will increase energy efficiency of the Azito Power Plant from approximately 29.5 percent to approximately 44 percent (Gross HHV).

Azito Power Plant, as planned in the initial project design in 1998, consists of building, owning, operating and eventually transferring to the State, a gas-fired power station with a total capacity of approximately 420 MW, to be implemented in three phases. In the first phase 144 MW simple cycle gas turbine operation was commissioned in January 1999 and in the second phase the second 144 MW simple cycle gas turbine was commissioned in February 2000. Expansion of capacity through conversion to combined cycle, which was originally planned in the third phase (in 2002) has been delayed but is being undertaken now. The existing gas turbines are designed to operate with natural gas (mainly) and distillate oil (back-up only). However, since initial commissioning of the Plant in 1999, the turbines have exclusively operated on gas. The distillate oil storage tanks (2 x 6000 m3) and related facilities will continue to be maintained for back up operation. Gas for the Plant comes from three sources in CÔte d’ Ivoire: the Devon fields (Lion/Panthèere), the Foxtrot field; and the CNR fields (Espoir/Baobab), with Foxtrot field as the primary gas supplier.

Azito Power Plant is located on a 5 ha plot of land near the Azito village in Yopougon District, approximately six kilometers West of the port of Abidjan in CÔte d’ Ivoire . The Plant premises are located alongside the Western arm of the Ebrié lagoon and the finished ground level (±0.00 level) in the Plant is +4.5 m above mean sea level. Béago, a second village is located about 300 m North East from the Plant boundary. The Plant premises are bordered (along the Northern fence) by a gas treatment unit, independently operated by Foxtrot, which provides condensate-free feed gas to Azito Power Plant, and by an electrical switchyard operated by the Compagnie Ivoirienne d’Electicité (CIE – national electricity distribution company) on its Western fence. The existing transmission line (T-Line) is adequate to evacuate power from the expanded capacity.

The Project involves construction of: steam turbine installation and building; HRSG installation; air-cooled condenser installation; control and electrical building; water treatment building/de-mineralization plant; administrative building; and warehouse. The duration of the construction works will be approximately 27 months. The Project does not require any land acquisition, since the facilities will be built over land which is already part of the Azito Power Plant concession. The temporary lay down areas and workers accommodation camps during the construction phase may occupy land outside of the site limit but these will also be within the existing 300 m exclusion zone around the existing power plant. The Project site can be accessed by an existing road. Much of the construction material, and construction and project equipment will be transported on this access route but there is a possibility that construction and project equipment may be transported by barges from Abidjan port.

Overview of IFC's Scope of Review

The review of this Project builds upon the supervision, undertaken since the year 2000, of IFC’s previous investment (IFC project # 8503) in Azito Power Plant (the “Plant”). Azito Energie S.A, (“Azito” or the “Company”) is owner of the Plant and also the Project proponent. Up until early 2011 Azito reported to IFC regarding the ongoing management of environmental and social performance at the Plant, which had been satisfactory. IFC’s recent review in February 2012 consisted of appraising technical, environmental and social information submitted by the Company including:
Environmental and Social Impact Assessment (“ESIA”) for the Phase III expansion Project of the existing Azito Power Station in Abidjan, CÔte d’Ivoire dated March 5th, 2012 prepared by Environment Resources Management, including the Environmental and Social Management Plan (ESMP);
Azito Phase 3 Expansion Project Environment and Social Impact Assessment: Scoping Study dated November 2010 prepared by Environment Resources Management;
Environmental Impact Assessment (“EIA”) of Combined Cycle Gas Turbine (CCGT) Power Plant Project in Abidjan, CÔte d’Ivoire dated April 1998 prepared by Environment Resources Management;
Noise Abatement Plan for the Azito Power Plant Project in Abidjan, CÔte d’Ivoire dated December 1998 prepared by Environment Resources Management; and
Environmental Impact Assessment (“EIA”) of Azito - Abobo Transmission Line and Substation (Addendum to the EIA of CCGT Power Plant Project) dated April 1998 prepared by Environment Resources Management;

The review also included a discussion with: the technical and management professionals from Azito Energie and Azito Operation and Maintenance S.A. (“Azito O&M”, the power plant operator); Agence Nationale de l’Environnement (National Environmental Agency or “ANDE”); Cabinet d’Etudes, Conseils d’Assistance et de Formation (“CECAF” - the in country consulting firm involved in the ESIA process); and Environment Resource Management (ERM) team involved in the ESIA process. Further, the review included a visit to the Project site and the Attiéké factory at Azito village, all in Yopougon District of Abidjan city in the Republic of CÔte d’Ivoire.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
Azito Phase 3 ESAP March 23, 2012.pdf
Azito Phase 3 ESIA March 2012.pdf
Azito ESIA Annexes.pdf