PROJECT

Projects

Environmental & Social Review Summary

Project Number

26529

Company Name

ENERGY DEVELOPMENT CORPORATION

Date ESRS Disclosed

Jun 3, 2008

Country

Philippines

Region

East Asia and the Pacific

Last Updated Date

Jun 18, 2026

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Jul 3, 2008
Signed : Nov 25, 2008
Invested : Jan 5, 2009

Sector

Geothernal - Renewable Energy Generation

Industry

Infrastructure

Department

Gbl Infrastructure & Natural Resources

Project Description

PNOC-EDC is an integrated geothermal steam and electric power producer with its core activities being the exploration, development, and production of geothermal energy. The company has five existing geothermal production fields: Bacon-Manito Geothermal Production Field (150MW), Leyte Geothermal Production Field (701MW), Southern Negros Geothermal Production Field (192.5MW), Mindanao Geothermal Production Field (106MW), Northern Negros Geothermal Production Field (49.4MW), totaling 1,199 MW, which is over 60% of the country’s total installed geothermal capacity of 1,905MW. The company is an existing IFC client and is seeking financing to support their medium term capital expenditure program. The proposed IFC investment will be a $100 million A loan and potentially a $100 million B loan. The proceeds of the loans will be used to partially finance the company’s medium term capital expenditure program.

Overview of IFC's Scope of Review

This is an IFC’s second investment in the PNOC Energy Development Corporation (PNOC EDC or the company). The previous investment was made in December 2006 (Project Number 25389). IFC’s review for this investment consisted of a desk review of the updated information on environmental and social assessment and management systems of the company. Documents reviewed include:

- the revised Corporate Environmental Policy and the Environmental Management System Manual approved by the company on August 21, 2007
- HESS (Health, Environment, Safety & Security) Reports dated February 19, 2008 and March 25, 2008
- examples of the quarterly Self- Monitoring Reports (SMRs) submitted by the company’s geothermal field sites to the Philippine Department of Environment and Natural Resources – Environmental management Bureau Regional Offices
- examples of Environmental Compliance Certificates (ECCs) secured in 2007

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement