PROJECT

Projects

Environmental & Social Review Summary

Project Number

26500

Company Name

AD HYDRO POWER LIMITED

Date ESRS Disclosed

Dec 8, 2007

Country

India

Region

South Asia

Last Updated Date

Nov 9, 2022

Environmental Category

A - Significant

Status

Completed

Previous Events

Approved : Feb 21, 2008
Signed : Apr 23, 2008
Invested : Sep 29, 2009

Sector

Large Hydro - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry - INF Asia & Pac

Project Description

AD Hydro Power Limited (ADHPL or the project) involves the construction, operation and maintenance of a 192MW run-of-the-river hydro-electric merchant power plant in the Kullu district of Himachal Pradesh and the construction of a 174km, 220kV transmission line for evacuating power to the regional grid. The project will utilize the perennial flows of the Allain and Duhangan rivers, and combine the flows through two underground tunnels to feed a single powerhouse near Prini Village. The project is one of the first private hydropower plants financed on a merchant basis in South Asia.

IFC financing was approved by IFC’s Board on September 28, 2004 and project construction began in early 2005 with the plan of commissioning by June 2008. However, as of end October 2007, the project is behind schedule and is now expected to be commissioned in two stages, with ADHPL projecting the Allain component to start operation in June 2009 and the Duhangan component in January 2010. ADHPL is seeking additional financing from IFC to partially cover cost over-runs of the project.

Overview of IFC's Scope of Review

The investment involves additional financing to support the completion of 192 MW Allain Duhangan Hydro Power project in Himachal Pradesh, India. IFC disclosed its environmental and social review of the original project in December 2003 and the project was approved for financing by the IFC Board in September 2004. Apart from the cost and completion schedule, the original project has not changed. Therefore, IFC’s original environmental and social review remains valid and precedent.

In addition to its ongoing environmental and social monitoring of the project, IFC undertook a separate environmental and social review to assess the project in relation to IFC’s Social and Environmental Sustainablility Policy and Performance Standards, which were introduced in April 2006, nearly 18 months after the original project was approved by IFC’s Board. IFC''s environmental and social review consisted of:


- a physical inspection of all project construction sites;
- interviews with locally elected officials and their predecessors, representatives of local women’s organizations and individuals belonging to project-affected communities;
- interviews with the team of IFC''s Independent Engineer, including the team''s Environmental Consultant; and
- a review of the status of the company''s implementation of its Environmental and Social Management and Monitoring Plan.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
ADHPL Commitments Register Update December 1st 2007.pdf