PROJECT

Projects

Environmental & Social Review Summary

Project Number

26466

Company Name

CENTRAL TERMOELECTRICA ANDINA S.A.

Date ESRS Disclosed

Feb 1, 2008

Country

Chile

Region

Latin America and the Caribbean

Last Updated Date

Jun 11, 2022

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Mar 13, 2008
Signed : Dec 18, 2008
Invested : Feb 6, 2009

Sector

Coal - Thermal Power Generation

Industry

Infrastructure

Department

Regional Industry INF LAC & EUR

Project Description

The proposed project consists of the construction and operation of 2x165MWe circulated fluidized bed (CFB) technology thermal power units in northern Chile to be fired by a combination of coal, petroleum coke, and biomass fuels. The project sponsor is Suez Energy Andino (project sponsor), a subsidiary of Suez S.A. (France). The first 165MWe unit (Unit 1) is to be developed by Central Termoeléctrica Andina S.A., (CTA), while the second 165MWe unit (Unit 2), with essentially the same characteristics, will be developed through a separate special purpose company. The Unit 1 operator will be Empresa Electrica del Norte Grande S.A., (Edelnor), a company controlled by the project sponsor, which operates several energy generation assets in Chile’s Region I and Region II, including two pulverized coal and petcoke generation units with respective capacities of 165 MWe and 175MWe and a 250 MWe combined-cycle unit located adjacent to the proposed project site. The Unit 2 operator is to be determined at a later stage. Some operation facilities of the first 165MWe unit will be shared with the existing Edelnor facilities as well as Unit 2. If IFC is requested to participate in the financing of Unit 2, O&M of the second unit will be conducted according to the Environmental and Social standards of the IFC.

The project will be connected to the grid through the existing Chacaya substation, which is adjacent to Edelnor’s existing facility and therefore adjacent to the project. Electricity transmission to the principal offtaker for Unit 1 will require either the construction of a new stretch of approximately 200 km of double circuit transmission line (Chacaya – Crucero) or the new construction of a new stretch of approximately 110 km of double circuit transmission line to connect to the existing transmission line between Crucero – Escondida and the construction of a new substation (called COBRE) at the connection between the new and existing line. Final choice of optimal solution is under study.

The project will require limestone for sulfur dioxide (SO2) emissions control to be sourced from a yet to be determined mine, and potentially the construction of a new ash disposal site

Overview of IFC's Scope of Review

IFC visited the proposed project site and interviewed environmental specialists at Edelnor facilities in Mejillones to evaluate Edelnor’s management systems and procedures and to understand how these will be implemented during operation of the proposed project facility for Unit 1. IFC reviewed a series of environmental and social impact assessment documents and permits for the proposed project as well as miscellaneous information describing the company’s environmental, health, and safety (EHS) management systems and corporate social responsibility programs, including information of the Edelnor facilities, which will be applied to the proposed project, including:

- Environmental Impact Assessment, Central Termica Andino, and related addenda;
- Environmental Permit (Resolución Exenta No. 0145/2007) issued by Chile’s National Environmental Commission, regional representation (COREMA), on May 16, 2007;
- Documentation of Health and Safety Management Programs and Procedures for the Edelnor facilities;
- Documentation of the project sponsor’s social and community programs in the project affected communities;
- Documentation on human resources policy and procedures of the Edelnor facilities;
- Environmental, health, safety and social safeguard requirements included in the engineering, procurement, and construction (EPC) contract for the construction of Units 1 and 2 of the proposed project.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
Final Adenda 2 .pdf
Environmental Permit.pdf
ESIA Final Part 1.pdf
ESIA Final Part 2.pdf
ESIA Final Part 3-A.pdf
ESIA Final Part 3-B.pdf
ESIA Final Part 4.pdf
ESIA Final Part 5.pdf
Final ADENDA 1 FIN.pdf
Final ADENDA 1 Part 1.pdf
Final ADENDA 1 Part 2.pdf
Final ADENDA 1 Part 3-A.pdf
Final ADENDA 1 Part-B.pdf