PROJECT

Projects

Environmental & Social Review Summary

Project Number

26016

Company Name

ENERJISA ENERJI URETIM ANONIM SIRKETI

Date ESRS Disclosed

Jan 31, 2008

Country

Turkiye

Region

Central Asia and Turkiye

Last Updated Date

May 10, 2025

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Mar 13, 2008
Signed : Jun 13, 2008
Invested : Dec 17, 2008

Sector

Large Hydro - Renewable Energy Generation

Industry

Infrastructure

Department

Gbl Infrastructure & Natural Resources

Project Description

EnerjiSA is a 50:50 joint venture formed in May 2007 by H.O. Sabanci Holding A.S. (Sabanci) from Turkey and Österreichische Elektrizitätswirtschafts-Aktiengesellschaft (Verbund) from Austria. Sabanci is one of the leading industrial and financial conglomerates in Turkey, and Verbund is the largest vertically integrated electricity group in Austria. The joint venture will develop and operate a generation portfolio of hydropower, gas, coal, and wind power plants, as well as distribution and supply and wholesale/trading. IFC’s funds would not be used for any nuclear power investments by the company.

Through its own development, EnerjiSA currently owns and operates four natural gas-fired combined cycle and combined cycle-cogeneration plants (65 to 120 MW electricity capacity), and as a result of acquisitions owns and operates four hydroelectric power plants with capacities ranging from 7 to 48.5 MW. The project is to finance the first phase of EnerjiSA’s capital investment program, covering the 2008 to 2012 period. The first phase envisions the construction of the 933 MW Bandirma natural gas fired thermal power plant in western Turkey adjacent to the Marmara Sea, and – according to current planning – ten hydroelectric power plants with total capacity of 972MW, including Cambasi (45 MW) in the Solakli River basin in northern Turkey; Kusakli (29MW), Kavsakbendi (175 MW) Yamanli II (79 MW), Kopru (120 MW), and Menge (55 MW), located in the Seyhan River basin in the south of Turkey; and Dagdelen (11MW), Kandil (214 MW), Hacininoglu (142 MW), and Sariguzel (103 MW), located in the Ceyhan River basin in the south-east of Turkey. A technical and economic optimization of the individual projects is going on. For the subsequent phases of its long-term capital investment program, EnerjiSA continues to identify additional power generation projects and is in the process of acquiring new hydropower generation licenses and studying coal reserves for coal fired thermal plants.

Overview of IFC's Scope of Review

The proposed IFC investment will extend corporate loans to EnerjiSA Enerji Üretim A.S. (EnerjiSA or the company), secured with its underlying portfolio of energy assets and contracts, to finance the first phase of EnerjiSA’s capital investment program for the 2008 to 2012 period. IFC’s proposed investment will be in parallel with financing from the Turkish commercial bank Akbank and WestLB of the UK. WestLB is an Equator Bank, and thus also follows IFC’s Performance Standards. In view of scale of the projects to be funded, in addition to assessment of corporate social and environment management capacity, a preliminary project-centered social and environment assessment was undertaken. Specific aspects of EnerjiSA’s management system evaluated include:

- Company’s corporate environmental and social management systems, management performance in its existing operations, and its extension to new projects;
- Social and environmental assessment process and documentation for the proposed project; and
- Community engagement activities (public consultation and disclosure).

IFC, Akbank, and WestLB jointly engaged the engineering consulting firm Sargent & Lundy as their Independent Engineer for the project. Sargent & Lundy conducted a technical, environmental, and social due diligence review of EnerjiSA’s existing assets and projects under development. IFC and Sargent & Lundy staff conducted visits and interviews at EnerjiSA’s headquarters, at EnerjiSA’s engineering design and environmental/social consultants, and at representative company facilities. Sargent & Lundy’s December 2007 draft report was a principal source for IFC’s staff review of the project. IFC staff also reviewed the following documents:

- EnerjiSA Hydroelectric Power Plants, presentation, June 2007;
- General Information about EnerjiSA’s Natural Gas Powerplants, presentation, June 2007; and
- EnerjiSA Thermal and Hydro Projects, presentation July 2007.

EnerjiSA’s projects are under development, and project designs and social and environmental documentation are in preparation. As the Independent Engineer to the Lenders, Sargent & Lundy will review the design and E&S documentation for each project for consistency with IFC’s Performance Standards prior to disbursement of funds for that specific project. IFC will work with EnerjiSA and Sargent & Lundy on the first project (expected to be the Bandirma gas turbine plant, see below) to assist the company in the process.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement