PROJECT

Projects

Environmental & Social Review Summary

Project Number

25922

Company Name

THE BEST CONSTRUCTION SH.P.K.

Date ESRS Disclosed

Jun 29, 2007

Country

Albania

Region

Europe

Last Updated Date

Nov 30, 2016

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Feb 28, 2008
Signed : Feb 29, 2008
Invested : Apr 25, 2008

Sector

Construction and Real Estate

Industry

Tourism, Retail and Property

Department

Regional Industry MAS LAC & EUR

Project Description

The project is to design and construct the following two real estate developments in the wider Tirana area:

- in Lundra a complex of 22,000 m2 consisting of 26 town houses and 70 apartments along with commercial and retail space, and
- in the Curilla coastal area next to Durres, a complex of 33,000 m2 similar in design to the one of Lundra.
- In addition the project envisages financing BC’s principal activities of acquiring a Land Bank (investment properties not developed) to develop and provide quality serviced residential, commercial and/or mixed accommodation for customers.

The operations of the project consist in the construction of the aforementioned, sale of finished properties, and the rental of some of the commercial ones. The first part of the construction is the infrastructure within the property, consisting of roads, pipes for water, sewage and utilities. This will be followed by groundbreaking and basement construction, then vertical construction in parallel on all buildings. The two phase project will be implemented over a three year period.

Overview of IFC's Scope of Review

The review of this project consisted of appraising written technical, environmental and social information submitted by Best Construction (BC), in response to questions asked by IFC and a visit by IFC to the current project site, Lundra, and meeting with BC management.

When the design of the second real estate site, Curilla, is proceeding around the mid of 2008, IFC will review the detailed design and carry out an additional site appraisal to ensure that this phase of the project also fully comply with the IFC Performance standards and guidelines. During this EHS site appraisal IFC will assess what PS are applicable for any other developments that are or will be part of the project.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
Action Plan 2007June28 BC.pdf