PROJECT

Projects

Environmental & Social Review Summary

Project Number

25797

Company Name

COASTAL GUJARAT POWER LIMITED

Date ESRS Disclosed

Nov 27, 2007

Country

India

Region

South Asia

Last Updated Date

Jun 3, 2021

Environmental Category

A - Significant

Status

Completed

Previous Events

Approved : Apr 8, 2008
Signed : Apr 24, 2008
Invested : Dec 4, 2008

Sector

Coal - Thermal Power Generation

Industry

Infrastructure

Department

Regional Industry - INF Asia & Pac

Project Description

Coastal Gujarat Power Limited (CGPL or the company) will build, own and operate a 4,000 MW (5 units of 800 MW each) ‘ultra mega’ imported coal, supercritical technology and once through sea water cooling based power plant at Tundawand Village, Taluka Mundra, District Kutch in the state of Gujarat, India. The project will be the first 800MW unit size supercritical plant in India, and hence, will be amongst the most energy efficient coal fired power plant of the country, contributing to the country’s coal fired power sector energy efficiency and CO2 emissions performance improvement. The current project plan includes a dedicated railway system from Mundra port to transport coal to the plant and two open channels to the sea for intake and discharge of condenser cooling sea water, which will be approximately 6.5 km and 4.9 km in length respectively.

The project includes transmission lines, which are associated facilities, to be constructed, operated and maintained by Powergrid Corporation of India Limited (PGCIL). The project, awarded by India’s Ministry of Power (MoP) through tariff based competitive bidding, is being sponsored by Tata Power Company Limited (Tata Power or the sponsor, India’s largest private power utility). CGPL, established as a wholly owned subsidiary of Power Finance Corporation Ltd, carried out the early/project conceptualization stage social and environmental assessment, participated in the environmental public hearing of September 2006 and obtained environmental and other regulatory clearances, including initiation of land acquisition process all before March 2007, before CGPL was transferred to the successful bidder, Tata Power in this case, in April 2007. CGPL will sell its generation to the utilities of five different states (the procurers) in the power starved regions of western and northern India through long term 25 year take-or-pay Power Purchase Agreements (PPAs). In order to facilitate the development of ultra mega power projects, the GoI, through Power Finance Corporation Ltd, has taken care of providing necessary clearances through established administrative mechanism and securing land and other facilities for selected bidders. IFC is considering providing debt and equity to CGPL.

Overview of IFC's Scope of Review

Coastal Gujarat Power Limited (CGPL or the company), a wholly owned subsidiary of The Tata Power Company Limited (Tata Power or the sponsor) is setting up a 4000 MW supercritical coal based power plant near village Tundawand, Taluka Mundra in Kutch District, in the state of Gujarat, India. IFC is considering providing debt and equity to CGPL.

CGPL has carried out a Rapid Environmental Impact Assessment (REIA) for the period March to May 2006; has conducted a public hearing for the project on September 19, 2006; has been accorded environmental clearance dated March 2, 2007 (including a corrigendum dated April 5, 2007), by Ministry of Environment and Forests (MoEF), Government of India (GoI); has been accorded Coastal Regulation Zone (CRZ) clearance (for condenser cooling seawater intake and discharge channels) dated February 8, 2007; has carried out Rapid Marine Environmental Impact Assessment (RMEIA) dated January 2007; carried out a Comprehensive Environmental Impact Assessment during March 2006 – February 2007; and has carried out supplemental environmental assessment work including cumulative air quality impact assessment (limited to impacts on account of SO2 emissions) during October – November 2007.

The company has commissioned a third party to undertake a Social Impact Assessment (SIA) in accordance with IFC Performance Standards (PS) 1 and 5 requirements. The company will, in consultation with the affected communities, also develop a community development plan (CDP). The Baseline Social Impact Assessment (BSIA) was completed during October – November 2007. It identifies key project impacts on project affected persons (PAPs), in particular the most vulnerable PAPs among them; and proposes a framework for mitigation of the identified impacts. The company will, in consultation with affected communities, develop and implement measures to mitigate the identified impacts including livelihood restoration and community development.

Review of this project consisted of appraising technical, environmental and social information submitted by the company including the REIA, RMEIA, CEIA, BSIA, supplemental environmental assessment documents, regulatory approvals, public hearing record notes, various supply and construction contract documents, and Tata Power’s Human Resource (HR) manuals. The appraisal team also interviewed both Tata Power’s and CGPL’s corporate and project management, plant construction, environment, occupational health, safety, human resources and community relations professionals. Further, the appraisal included:

- a site visit to the proposed power plant site near village Tundawand in Kutch District of Gujarat;
- interactions with representatives of affected communities; and
- interactions with members of the project affected households (PAHs) from the two of the four affected villages.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
Supplemental EIA-CGPL.pdf
Baseline SIA-CGPL.pdf
Comprehensive EIA-CGPL Vol1.pdf
Comprehensive EIA-CGPL Vol2.pdf
Comprehensive EIA-CGPL Vol3.pdf
Comprehensive EIA-CGPL.pdf
ESAP-CGPL.pdf
Rapid Marine EIA-CGPL Vol1.pdf
Rapid Marine EIA-CGPL Vol2.pdf
Rapid Marine EIA-CGPL Vol3.pdf
Rapid Marine EIA-CGPL Vol4.pdf
Rapid Marine EIA-CGPL Vol5.pdf
Rapid Marine EIA-CGPL.pdf
Supplemental EIA-CGPL Vol1.pdf
Supplemental EIA-CGPL Vol2.pdf
Supplemental EIA-CGPL Vol3.pdf
Supplemental EIA-CGPL Vol4.pdf
Final Stakeholders Engagemant Policy.pdf
Final Compensation Management Framework.pdf
Influx Management Plan-CGPL.pdf
Security Management Plan-CGPL.pdf
CSR_Initiatives_UMPP.pdf
Local Hiring and Purchase Plan.pdf
Household Survey and Needs Assessment Study.pdf