Environmental & Social Review Summary

Project Number

25554

Company Name

Bajaj Hindusthan Sugar Limited

Date ESRS Disclosed

Jan 16, 2007

Country

India

Region

South Asia

Last Updated Date

Nov 30, 2016

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Feb 28, 2007
Signed : Mar 7, 2007
Invested : Apr 16, 2007

Sector

Sugar and Confectionery

Industry

Agribusiness and Forestry

Department

Regional Industry - MAS Asia & Pac

Project Description

Bajaj Hindusthan Sugar & Industries Limited (the company) is a publicly listed company that produces and sells sugar and industrial alcohol/ethanol. BHSIL is undertaking to:

- expand a brown-field sugar plant from 3,200 to 6,000 tons crushed per day (TCD);
- construct three green-field sugar plants with combined capacity of 34,000 TCD; and
- build a distillery of 160 kiloliters per day (the project).

The project is located in the eastern Uttar Pradesh, specifically in:

- Pratappur, Deoria District (brown-field);
- Kunderki, Gonda District (green-field sugar plant);
- Utraula, Balrampur District (green-field sugar plant); and
- Rudauli, Basti District (green-field sugar plant and distillery).

The nearest community habitations are 0.5 to 1.5 km from the proposed project sites, the plants are located in predominantly agricultural area and there are no environmentally sensitive areas in the vicinity the proposed plant sites and the existing plant. The proposed IFC investment includes a debt and equity package for IFC’s own account and B loan from participating banks.

Overview of IFC's Scope of Review

The review of this project consisted of appraising technical, environmental and social information submitted by the project company including a review of:

- company’s business plan;
- completed Appraisal Information Sheet submitted by the company;
- Environment Impact Assessment reports;
- relevant consents/permits;
- recent annual environment statement;
- recent monitoring reports for stack emissions, treated effluent, ambient air quality, ambient noise, workplace air quality, workplace noise and drinking water quality;
- Environmental Clearance from Ministry of Environment and Forests;
- Project reports of each of the proposed plants;
- record notes of public hearing; and
- Human Resource Manual.

The appraisal team interviewed the corporate and site operations managers, and corporate and site EHS managers:

Further, the appraisal included sites visits to the company’s existing plants at Pratappur and one project site at Rudauli in the state of Uttar Pradesh, India. The following potential environment, health and safety and social aspect of the project were analyzed:

- Social and Environment assessment and environmental, social, and health and safety management systems;
- Labor and working conditions;
- Pollution prevention and abatement;
- Community health, safety and security; and
- Land acquisition and compensation.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
Final BHSIL ESAP January 13 2007.pdf