PROJECT

Projects

Environmental & Social Review Summary

Project Number

25455

Company Name

SP-SSA INTERNATIONAL CONTAINER SEVICES JOINT VENTURE COMPANY

Date ESRS Disclosed

Sep 19, 2007

Country

Viet Nam

Region

East Asia and the Pacific

Last Updated Date

Jun 20, 2024

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Nov 1, 2007
Signed : Jun 29, 2009
Invested : Dec 17, 2009

Sector

Port and Harbor Operations

Industry

Infrastructure

Department

Regional Industry - INF Asia & Pac

Project Description

SP-SSA International Container Services Joint Venture Company (SSIT or the company) is developing a greenfield container terminal on the Cai Mep River in Ba Ria-Vung Tau province (the Terminal) to serve the Ho Chi Minh City (HCMC) area in Vietnam. Container volumes in the HCMC area have increased significantly in recent years, causing congestion at the region’s ports and within HCMC. The Terminal will help address this situation by providing much needed container handling capacity to relieve existing congestion. It will also be well positioned to capitalize on the region’s projected growth in container volumes. Located approximately 85 kilometers southeast of HCMC, the Terminal will have a draft of 14 meters and the latest container handling equipment, enabling it to serve today’s large containerships which cannot call at existing HCMC ports due to draft and LOA (turning) restrictions.

Overview of IFC's Scope of Review

IFC reviewed several documents related to the project’s development including:

- Vietnam Seaport System Development Master Plan -- 2010, prepared by VINAMARINE, 1999;
- Detailed Master Plan of Group No. 5 Seaports (2010 – 2020), prepared by VINAMARINE, 2005;
- Environmental Impact Assessment Report – Cai Mep-Thi Vai International Port Project, prepared by VINAMARINE, 2003;
- Environmental Impact Assessment Report – SP-SSA International Terminal, prepared by PORTCOAST Consultant Corporation, June 2007; and
- Minutes of Public Meeting to discuss project plans and compensation – Government Representatives and Affected Communities, December 8, 2005.

In addition, visits to the Cai Mep Port site and surrounds were conducted by IFC staff on February 5-7, 2007. Face-to-face meetings with SSIT operational and technical management staff (representing SSA Marine and Saigon Port sponsors) and PORTCOAST staff conducted during the site visits.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement