Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Nov 21, 2006
Signed : Dec 4, 2006
Invested : Dec 12, 2006

Sector

Geothernal - Renewable Energy Generation

Industry

Infrastructure

Department

Gbl Infrastructure & Natural Resources

Project Description

PNOC-EDC is an integrated geothermal steam and electricity producer with its core activities being the exploration, development and production of geothermal resources. The company has four existing geothermal production fields: Bacon-Manito Geothermal Production Field (150MW), Leyte Geothermal Production Field (701MW), Southern Negros Geothermal Production Field (192MW), and Mindanao Geothermal Production Field (106MW), totaling 1,149MW geothermal capacity, accounting about 60% of the country’s total installed geothermal capacity of 1,905MW. In 2005, the company’s existing geothermal production fields generated 7,080 GWh of electricity with annual capacity factor of about 70%. IFC is planning to provide financial support to the company to assist them in their medium term capital expenditure program which includes acquisition of a new drilling rig, rehabilitation of existing drilling rigs, and expansion / development of geothermal production fields. The proposed IFC investment will be up to $50 million.

Overview of IFC's Scope of Review

Note: The schedule for the Board meeting is driven by the financing timeline. To comply with the IFC disclosure requirements the decision of the Board meeting of November 16 will become effective upon the expiration of the required 30-day disclosure period for a Category B project. IFC’s review consisted of review of documents prepared by or published by PNOC Energy Development Corporation (PNOC EDC or the company), interviews with PNOC EDC representatives and selected project affected peoples, and site visits to selected PNOC EDC’s existing geothermal production fields: Documents reviewed by IFC included the following: - Environmental Compliance Certificates issued for PNOC EDC’s existing Geothermal Production Fields - “Report to Stakeholders, March 2, 2006”, a report prepared for the First PNOC EDC Stakeholders’ Meeting - PNOC EDC publication, Energy Forum, Volume VII No.1, April 2001, Special Feature: The 25-Year Saga - Environmental Impact Assessment Reports and Resettlement Action Plans, disclosed at World Bank’s external website related to the Company’s carbon financing projects - Environmental Management / Corporate Social Responsibility sections of PNOC EDC Annual Reports 2005, 2004 and 2003 - Contingency Plan of Bacon-Manito Geothermal Production Field (BGPF) on Spills and Accidents Involving Toxic Chemical Substances and Hazardous Wastes, DENR ID#: 05-05-0008. This includes various specific contingency plans such as Typhoon Emergency Plan, Earthquake Emergency Plan, etc. - PNOC EDC Resettlement and Development Policy Interviews: IFC Environmental Specialist conducted interviews with PNOC EDC’s management team including Vice President – Environment and External Affairs, Managers and Officers of Environmental Management Department, as well as Resident Managers, Environmental Officers, Community Partnership Officers of the selected geothermal production fields. Site visits: Out of the four existing geothermal production fields operated by PNOC EDC, IFC Environmental Specialist conducted site visits to Mindanao Geothermal Production Field and Leyte Geothermal Production Field in October 2006.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures