PROJECT

Projects

Environmental & Social Review Summary

Project Number

25340

Company Name

WEST INDIAN OCEAN CABLE COMPANY LTD

Date ESRS Disclosed

Apr 27, 2007

Country

Eastern Africa Region

Region

Africa

Last Updated Date

Jun 3, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Aug 2, 2007
Signed : Nov 21, 2007
Invested : Jun 12, 2008

Sector

Cable and Broadband

Industry

Telecommunications and Technology

Department

TMT, Venture Capital & Funds

Project Description

The East African Submarine Cable System (EASSy) is an initiative to construct and operate a submarine fiber optic cable along the east coast of Africa to connect eight coastal countries and island nations to each other and to the rest of the world. A special purpose vehicle (SPV) has been established by EASSy which consists of a small management and marketing team who will manage the implementation of the project. The SPV has contracted Alcatel, a specialist international company, to construct the project in coordination with the respective national telecom operators.

The cable will have an initial equipped capacity of 20Gbits/sec, and an ultimate capacity when fully upgraded of 320Gbits/sec. The route will be from South Africa to Sudan, covering about 8,500 km, and connecting the following countries: South Africa, Mozambique, Madagascar, Tanzania, Kenya, Somalia, Djibouti and Sudan. Twenty-eight leading telecommunications operators (the Operators) from East and Southern Africa signed a Memorandum of Understanding (MOU) in December 2003 to carry out the construction and maintenance of EASSy. EASSy will be the first optical fiber connection for most of these countries to the global optical fiber network. In separate projects, EASSy signatories are working on the development of terrestrial backhaul connections to link land-locked countries of the region to the cable (including Botswana, Burundi, Ethiopia, Lesotho, Malawi, Rwanda, Uganda, Zambia and Zimbabwe). IFC has been asked to provide financing to the SPV, along with five other DFIs including EIB, AfDB, DBSA, AFD/Proparco, and KfW.

The terrestrial backhaul connections are separate from but associated with the project and are to be developed by the respective national operators. These components are being financed by the World Bank who will ensure adherence to their Safeguard Policies in implementing these projects.

Overview of IFC's Scope of Review

The scope of the project review with IFC’s Performance Standards included site visits, coordination with other lenders, and review of the documents as listed and described below:

- EASSy Detailed Feasibility Study, completed by Axiom, May 2005;
- Environmental and Social Impact Assessment (East African Submarine Cable System Project ESIA, February 2007, completed by EGS Ltd. - see link below);
- assessment of EASSy’ current and proposed management capacity and management systems; and
- review of EASSy’s framework Environmental and Social Management System (ESMS dated February 2007).
Site visits to selected landing stations were completed by the project team and meetings were held with senior management of the EASSy consortium, the ESIA consultants and national telecom operators (including Telkom Kenya, TELMA, Dalkom and Zantel) in February 2007.

In coordination with EASSy, Kreditanstalt für Wiederaufbau (KfW) and the African Development Bank (AfDB), and the World Bank/IDA who are lenders to the associated terrestrial backbone and backhaul components, a two phased approach to the Environmental and Social due diligence has been established. Phase I, now complete (see link below), included an assessment of international/deep water impacts, audits of national level requirements, and completion of a framework Environmental and Social Management System (ESMS). Phase II involves completion of national level ESIAs focusing on national/shallow water impacts and terrestrial impacts at landing points. IFC has been coordinating with these partners (and the World Bank) on the scope and depth of the ESIAs required. KfW and the AfDB are providing Technical Assistance for the two respective phases; IFC review of the Phase II will continue in coordination with these partners.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement