PROJECT

Projects

Environmental & Social Review Summary

Project Number

25332

Company Name

SOCIETE CONCESSIONNAIRE DE L'AEROPORT

Date ESRS Disclosed

Mar 6, 2007

Country

Cambodia

Region

East Asia and the Pacific

Last Updated Date

Jun 3, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Jun 6, 2007
Signed : Jun 7, 2007
Invested : Jul 18, 2008

Sector

Other Support Activities for Transportation (Grain Terminals, Cargo Terminals, Airport Operations)

Industry

Infrastructure

Department

Regional Industry - INF Asia & Pac

Project Description

The project company is Société Concessionnaire de l’Aéroport (SCA), a special purpose company that holds a 45-year concession (from 1995) from the Royal Government of Cambodia (RGC) to operate the Phnom Penh International Airport (PPIA) at Phnom Penh, the Siem Reap International Airport (SRIA) at Siem Reap, and the Sihanoukville Airport (SIA) at Sihanoukville. PPIA serves as the main gateway to Cambodia while Siem Reap mainly caters to the tourist traffic visiting the various Angkor temples located in the nearby Angkor Archeological Park, a UNESCO World Heritage site. Sihanoukville was established in the 1950s and forms together with Phnom Penh and Siem Reap one of the destinations that has been identified by the RGC as cornerstones for the country’s tourism development. The Sihanoukville airport, located 15 km from the city center, was built in the 1960''s and remains a small airport with limited facilities. SCA’s airport concession was modified to include the development and operation of Sihanoukville Airport in March 2006 by the RGC to the company. SIA, which had been closed in May 2006, reopened in January 2007.

The proposed project, expected to cost $40.1 million, consists of:


- the mandatory capital investments required under the concession for SIA for 2006 and 2007;
- the terminal capacity increase at SRIA to provide service to the increasing passenger growth; and
- future capital investments required at SIA in 2008-10, should traffic at the airport increase in accordance with the
company’s projections.

This would be a second IFC investment in SCA. In June 2004, IFC provided a $10 million to SCA to support capital expenditures at PPIA and SRIA.

Overview of IFC's Scope of Review

Documents Reviewed (desk reviews):

- Sihanoukville International Airport, Social & Environmental Impact Assessment (SEIA), prepared by JacobsGIBB Ltd for Société Concessionnaire de l’Aéroport, December 2006;
- Phnom Penh, Siem Reap & Sihanoukville International Airports, Investment Program Review, prepared by Jacobs Consultancy, October 2006;
- IFC Annual Environmental and Social Monitoring Report for Phnom Penh and Siem Reap International Airports, 2005 (DRAFT), prepared by SCA, October 2006;
- Addendum No. 6 to the Concession Contract between the Royal Government of Cambodia and SCA, March 2006.

Site Visits: Visits to the Sihanoukville Airport site and surrounds conducted by JacobsGIBB staff (as part of the preparation of the Social & Environmental Impact Assessment carried out at the request of IFC) on October 9 through 13, 2006, and by IFC Investment Department staff in September 2006.

Sponsor Interviews: Face-to-face meetings with SCA operational and technical management staff conducted by JacobsGIBB staff during the site visits. Teleconference with SCA staff (Jean Serge Boissavit and Charles Winter) conducted by IFC’s staff on 01/29/2007 and 2/6/07.

Other: Ongoing IFC supervision of Phnom Penh and Siem Reap airports environmental and social performance per the conditions of IFC’s existing investment in SCA (Project #21363) in June 2004.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement